| TO DO |
|
|
Missing window screens |
|
|
|
| UPGRADES |
| --- |
|
| CRITICAL PATH |
|
Tue
|
Feb 3
|
Inspection (Concrete Wall) (1) |
|
|
|
Wed
|
Feb 4
|
Inspection (Conduit Under Slab) (1) |
|
|
|
|
|
Inspection (Drain Tile) (0) |
|
|
|
|
|
Verify Window & Roof Structure (0) |
|
|
|
|
|
Patio (0) |
|
|
|
|
|
Rough In Microwave Vent (0) |
|
|
|
Thu
|
Feb 5
|
Inspection (Rough In Plumbing) (1) |
|
|
|
Fri
|
Feb 6
|
Inspection (Rough In Electric) (1) |
|
|
|
Mon
|
Feb 9
|
Inspection (Framing) (1) * |
|
|
|
|
|
Inspection (Deck Piers) (0) |
|
|
|
|
|
Exterior Stone (0) |
|
|
|
|
|
Set Electric Meter (0) * |
|
|
|
|
|
Inspection (Main Water Line) (0) |
|
|
|
|
|
Order Plumbing / Lighting Fixtures (0) |
|
|
|
Tue
|
Feb 10
|
Interior Trim - Paint (1) |
|
|
|
|
|
Ceiling Fans (0) |
|
|
|
Wed
|
Feb 11
|
Blower Door Test (1) |
|
|
|
|
|
Inspection (Final HVAC) (0) |
|
|
|
|
|
Inspection (Final Plumbing) (0) |
|
|
|
|
|
Inspection (Final Electric) (0) |
|
|
|
Thu
|
Feb 12
|
Stain Hardwood Stairs (1) * |
|
|
|
| TO DO - COMPLETED OR DELETED |
|
|
Trim needs painting |
|
|
|
|
Garage drywall repairs |
|
|
|
|
MB shelving |
Few shelving pieces needed. |
|
|
|
CODED LOCKBOX 2222 |
|
|
|
|
Siding "bubbles" |
|
|
|
|
Garage door needed 10/2 |
|
|
|
|
Garage trim |
|
|
|
|
Stove drywall repair |
|
|
|
|
Under stairs shelving needed |
|
|
|
|
Pocket door hardware |
|
|
|
|
Paint garage |
|
|
|
|
Hook up garage door opener |
|
|
|
|
Stove needs installed |
|
|
|
|
Mbath globe |
Now two are missing - Jill |
|
|
|
Missing siding on the back of the townhouse |
side of master bedroom bump out |
|
|
|
Patch at kitchen outlet |
|
|
|
|
Cabinet touch up kit |
Kate will deliver |
|
|
|
Clean ceiling fan |
Jill |
|
|
|
LR window wont close |
Tom will handle it |
|
|
|
Brace back deck |
Tom |
|
|
|
Stove bracket |
Tom |
|
|
|
Owners manuals for faucets |
Kate will email info |
|
|
|
Remove glue from bonus room ceiling |
Jill |
|
|
|
Cracked Patio Door |
Tom will take a look at it. |
|
|
|
Cover cable box in bonus room |
Tom |
|
|
|
Paint edge of door to deck |
|
|
|
|
Install master closet shelving |
|
|
|
|
Touch up paint at dirty hand print on ceiling |
|
|
|
|
Window screen |
|
|
|
| UPGRADES - COMPLETED |
| |
|
Painted Kitchen Cabinets
|
|
|
| CRITICAL PATH - COMPLETED |
| -- |
-- |
Ratified Contract? (0) 12.28.2021 |
|
|
| -- |
-- |
$2500 Deposit Received (0) 12.28.2021 |
|
|
| -- |
-- |
Association Packet Requested (0) 12.28.2021 |
|
|
| -- |
-- |
Association Packet Received (0) 12.28.2021 |
|
|
| -- |
-- |
Selections Meeting (0) 12.28.2021 |
|
|
| -- |
-- |
Selections Sheet Signed (0) 12.28.2021 |
|
|
| -- |
-- |
Amendment for Upgrades (B,S,L,T,BCP) (0) 12.28.2021 |
|
|
| -- |
-- |
Deposit For Upgrades Received (0) 12.28.2021 |
|
|
| -- |
-- |
Building Permit (30) * |
|
|
| -- |
-- |
Order Roof & Floor Trusses (1) |
|
|
| -- |
-- |
Order Windows & Doors (0) |
|
|
| -- |
-- |
Stake Out Home (1) |
|
|
| -- |
-- |
Excavate (2) |
|
|
| -- |
-- |
Inspection (Footers) (1) |
|
|
| -- |
-- |
Pour Footers (1) * |
|
|
| -- |
-- |
Set Forms (2) |
in process 3/24 |
|
| -- |
-- |
Pour Foundation Walls (1) |
|
|
| -- |
-- |
Plumb Slab (2) |
|
|
| -- |
-- |
Inspection (Plumbing Under Slab) (1) |
|
|
| -- |
-- |
Prepare Slab (1) |
|
|
| -- |
-- |
Inspection (Slab) (1) |
|
|
| -- |
-- |
Pour Slab (1) * |
|
|
| -- |
-- |
Settlement Agent Confirmed (0) 12.28.2021 |
|
|
| -- |
-- |
Framing I (9) |
|
|
| -- |
-- |
Order Steps (0) |
|
|
| -- |
-- |
Order Tubs / Showers (0) |
|
|
| -- |
-- |
Framing II (8) |
|
|
| -- |
-- |
Framing III (8) * |
|
|
| -- |
-- |
Install Stairs (0) * |
|
|
| -- |
-- |
Windows & Doors (0) * |
|
|
| -- |
-- |
House Number and Status in Window (0) |
|
|
| -- |
-- |
Roofing (0) * |
|
|
| -- |
-- |
Order Cabinets (0) 08.23.2021 |
|
|
| -- |
-- |
Order Appliances (0) 08.23.2021 |
SS Standard |
|
| -- |
-- |
Deck (0) 09.29.2021 |
|
|
| -- |
-- |
Gutters (0) 10.16.2021 |
|
|
| -- |
-- |
Driveway (0) * 10.23.2021 |
Apron/sidewalk needed |
|
| -- |
-- |
Privacy Divider / Fence (0) * 09.29.2021 |
|
|
| -- |
-- |
Sod / Seed / Landscaping (0) 11.01.2021 |
after concrete |
|
| -- |
-- |
HVAC Rough In (4) 10.04.2021 |
In process 6/23 |
|
| -- |
-- |
Plumbing Rough In (4) |
In process 6/30 |
|
| -- |
-- |
Electric Rough In (4) |
|
|
| -- |
-- |
Inspection (Rough In HVAC) (1) |
|
|
| -- |
-- |
Exterior Vinyl (0) * 09.26.2021 |
in process 9/15 |
|
| -- |
-- |
Insulation (2) * |
|
|
| -- |
-- |
Inspection (Insulation) (1) |
|
|
| -- |
-- |
Inspection (Electric Service) (0) 09.07.2021 |
|
|
| -- |
-- |
Inspection (Main Sewer Line) (0) 08.23.2021 |
|
|
| -- |
-- |
Order Interior Doors & Trim (0) 08.23.2021 |
Black Hinges |
|
| -- |
-- |
Drywall (Hang) (4) * |
|
|
| -- |
-- |
Loan Approval (0) 12.28.2021 |
|
|
| -- |
-- |
Deed Preparation (0) 12.28.2021 |
|
|
| -- |
-- |
Drywall (Tape, Block, Skim, Sand) (6) * |
In process 7/28 |
|
| -- |
-- |
Paint 1 (1) |
In process 8/4 |
|
| -- |
-- |
Garage Door (0) 09.26.2021 |
|
|
| -- |
-- |
House Numbers (0) 10.02.2021 |
|
|
| -- |
-- |
Mailbox (0) 12.28.2021 |
|
|
| -- |
-- |
Cabinet Installation (2) * 08.23.2021 |
8/18-on site 8/18 |
|
| -- |
-- |
Granite Installation (1) * 09.11.2021 |
9/10 |
|
| -- |
-- |
Interior Trim - Install (3) * 08.28.2021 |
In process 8/25-almost complete |
|
| -- |
-- |
Luxury Vinyl Plank (3) * 09.22.2021 |
In process 9/18 |
|
| -- |
-- |
Luxury Vinyl Tile (0) 09.22.2021 |
|
|
| -- |
-- |
Paint 2 (3) 09.22.2021 |
In process 9/18 |
|
| -- |
-- |
Cover Floors (0) 10.02.2021 |
|
|
| -- |
-- |
Deliver Plumbing / Lighting Fixtures (0) 09.26.2021 |
|
|
| -- |
-- |
Shoe Moulding (0) 09.26.2021 |
|
|
| -- |
-- |
Shelving, Door Knobs, Fire Extinguisher (1) * 09.29.2021 |
Black levers and bathroom accessories |
|
| -- |
-- |
Install Coded Lockbox (add extra keys) (0) 09.30.2021 |
|
|
| -- |
-- |
Pay Water / Sewer Taps (0) 09.23.2021 |
|
|
| -- |
-- |
Set Water Meter (1) * 09.30.2021 |
|
|
| -- |
-- |
Electric Trim Out (3) * 10.06.2021 |
Black Lighting. In process 10/2 |
|
| -- |
-- |
HVAC Trim Out (1) * 10.02.2021 |
In process 9/29 |
|
| -- |
-- |
Plumbing Trim Out (2) * 09.29.2021 |
Black Plumbing. In process. Powder bath needs plumbed and kitchen 9/26 |
|
| -- |
-- |
Install Appliances (0) * 10.10.2021 |
SS Standard. In process 10/6 |
|
| -- |
-- |
Paint 3 (2) * 09.22.2021 |
|
|
| -- |
-- |
Carpet (2) 09.29.2021 |
|
|
| -- |
-- |
Appraiser Confirms Construction Completion (0) 10.21.2021 |
|
|
| -- |
-- |
Inspection (Final Building) (4) * 10.14.2021 |
Mon, 10/11 |
|
| -- |
-- |
Pre Walk Through (0) 10.14.2021 |
|
|
| -- |
-- |
Cleaning (1) 10.14.2021 |
Cleaning 10/9 |
|
| -- |
-- |
Certificate of Occupancy (1) * 10.15.2021 |
|
|
| -- |
-- |
C.O. to Lender (0) 10.15.2021 |
|
|
| -- |
-- |
Schedule Closing (0) 10.18.2021 |
|
|
| -- |
-- |
Buyer Walk Through (1) * 10.21.2021 |
Thu, 10/14 at 1:00 PM |
|
| -- |
-- |
Payment for Upgrades (0) 10.25.2021 |
$600 |
|
| -- |
-- |
Keys to Settlement Agent (0) 10.14.2021 |
|
|
| -- |
-- |
Review Settlement Statement (0) 10.21.2021 |
|
|
| -- |
-- |
Jerry Signs Closing Documents (0) 10.21.2021 |
|
|
| -- |
-- |
Request Trash Tote From POA Manager (0) 10.15.2021 |
|
|
| -- |
-- |
Closing (1) 10.25.2021 |
October 22 |
|
| -- |
-- |
Remove Coded Lockbox (0) 10.28.2021 |
|
|