| -- | -- | Leaking gutter seam above back deck | Davenport | |
| -- | -- | Flooring issue in pantry - bulging | Jill will look at it | |
| Sun | Nov 2 | Verify Window & Roof Structure (0) | ||
| Sun | Nov 2 | Rough In Microwave Vent (0) | ||
| Sun | Nov 2 | Order Plumbing / Lighting Fixtures (0) | ||
| Sun | Nov 2 | Blower Door Test (1) | ||
| -- | -- | Needs front window (bedroom) | ||
| -- | -- | Liners needed in all bathtubs | ||
| -- | -- | Microwave vent needs framing (drywall covering it) 4/10 | ||
| -- | -- | Pulls needed on up vanities 4/18 | Just MB vanity now | |
| -- | -- | Flashing above front door looks odd | ||
| -- | -- | |||
| -- | -- | Missing pull kitchen | ||
| -- | -- | Back patio step needed? 5/18 | ||
| -- | -- | CODED LOCKBOX 0130 | ||
| -- | -- | MICROWAVE VENTED? | Happy to confirm when electric is on 6/12 | |
| -- | -- | Powder baths need junction boxes | ||
| -- | -- | Paint master bedroom door | ||
| -- | -- | Kitchen blemish drywall repair 6/12 | Painter | |
| -- | -- | Doorknob to master bed needed | ||
| -- | -- | Living room snap light needed | ||
| -- | -- | These steps needed stained as well | ||
| -- | -- | Shower rod needed | ||
| -- | -- | Electrical cover hall bath needed | And laundry | |
| -- | -- | Front light needed | And rear lights | |
| -- | -- | Powder fan needed | And hall bath | |
| -- | -- | Paint tops and bottoms of doors | Painter - July 8 | |
| -- | -- | Replace deck board with purple stain? | Tom | |
| -- | -- | Cracked deck boards - replace? | Tom. Court green-taped | |
| -- | -- | Put back insulation | Jill | |
| -- | -- | Patch LR ceiling | Drywaller | |
| -- | -- | Touch up paint needed | Painter | |
| -- | -- | Laundry electrical cover needed | Jill | |
| -- | -- | Put globes on powder bath after straightening fixture | Jill | |
| -- | -- | Remove trash behind townhouse | Jill | |
| -- | -- | Final clean | Cleaner | |
| -- | -- | Drywall seam to be sanded over island and around pendant lights | ||
| -- | -- | Plugs in French and front door | Jill | |
| -- | -- | Lots of little drywall and paint issues in powder bathroom | Painter | |
| -- | -- | Finish installing light in powder bathroom | ||
| -- | -- | Small hole to be patched by stairs to the upper level | Drywaller | |
| -- | -- | Sand drywall ceiling hall bath | Drywaller | |
| -- | -- | Paint touch ups | Painter | |
| -- | -- | Drywall repair at pendant light on kitchen ceiling | Painter | |
| -- | -- | Repair living room ceiling near snap light | Drywaller | |
| -- | -- | More screws needed for powder bath light switch | Jill | |
| -- | -- | Paint tops of all doors | ||
| -- | -- | Install window screens | ||
| -- | -- | Put globes on powder bathroom light | ||
| -- | -- | Various Drywall issues and paint issues in front hall closet | Drywall | |
| -- | -- | Fix wobbly ceiling fan in master bedroom | Tom or electrician | |
| -- | -- | Adjust second and third bedroom closet doors | ||
| -- | -- | Reattach basement insulation | ||
| -- | -- | Install media cover in basement | ||
| -- | -- | Many drywall issues throughout the home | ||
| -- | -- | Final paint touch up | Painter | |
| -- | -- | |||
| -- | -- | Trash can storage area | need siding | |
| -- | -- | Ratified Contract? (0) 11.21.2021 | ||
| Add Ceiling fan to Living Room | ||||
| Amendment to increase price by $6,750 | ||||
| -- | -- | $2500 Deposit Received (0) 11.21.2021 | ||
| -- | -- | Association Packet Requested (0) 11.21.2021 | ||
| -- | -- | Association Packet Received (0) 11.21.2021 | ||
| -- | -- | Selections Meeting (0) 12.14.2021 | ||
| -- | -- | Selections Sheet Signed (0) 01.11.2022 | 1/4/2022: sent to Maggie for buyer signatures | |
| -- | -- | Amendment for Upgrades (B,S,L,T,BCP) (0) 01.22.2022 | 1/21/2022: sent to Jerry for signature | |
| -- | -- | Deposit For Upgrades Received (0) 01.22.2022 | ||
| -- | -- | Building Permit (30) * 11.11.2021 | ||
| -- | -- | Order Roof & Floor Trusses (1) 11.11.2021 | ||
| -- | -- | Order Windows & Doors (0) 11.11.2021 | ||
| -- | -- | Stake Out Home (1) 11.08.2021 | ||
| -- | -- | Excavate (2) 11.29.2021 | ||
| -- | -- | Inspection (Footers) (1) 11.29.2021 | ||
| -- | -- | Inspection (Concrete Wall) (1) 01.05.2023 | ||
| -- | -- | Pour Footers (1) * 11.29.2021 | ||
| -- | -- | Set Forms (2) 12.06.2021 | in process 12/1 | |
| -- | -- | Pour Foundation Walls (1) 12.09.2021 | ||
| -- | -- | Plumb Slab (2) 12.13.2021 | ||
| -- | -- | Inspection (Plumbing Under Slab) (1) 12.20.2021 | ||
| -- | -- | Inspection (Conduit Under Slab) (1) 01.05.2023 | ||
| -- | -- | Prepare Slab (1) 12.20.2021 | ||
| -- | -- | Inspection (Slab) (1) 12.20.2021 | ||
| -- | -- | Inspection (Drain Tile) (0) 01.05.2023 | ||
| -- | -- | Pour Slab (1) * 12.20.2021 | ||
| -- | -- | Settlement Agent Confirmed (0) 01.26.2022 | ||
| -- | -- | Framing I (9) 01.03.2022 | ||
| -- | -- | Order Steps (0) 12.20.2021 | ||
| Oak Stairs to Bedroom Level | ||||
| -- | -- | Order Tubs / Showers (0) 12.09.2021 | ||
| -- | -- | Framing II (8) 01.17.2022 | ||
| -- | -- | Framing III (8) * 02.03.2022 | ||
| -- | -- | Install Stairs (0) * 02.24.2022 | ||
| -- | -- | Windows & Doors (0) * 03.13.2022 | ||
| -- | -- | House Number and Status in Window (0) 02.28.2022 | ||
| -- | -- | Roofing (0) * 02.17.2022 | ||
| -- | -- | Order Cabinets (0) 01.31.2022 | ||
| -- | -- | Order Appliances (0) 02.24.2022 | Standard | |
| -- | -- | Deck (0) 04.25.2022 | In process 2-16 Expanded Deck 12 x 18 | |
| Expanded deck- 12 x 18 | ||||
| -- | -- | Gutters (0) 05.02.2022 | ||
| -- | -- | Driveway (0) * 06.18.2022 | STANDARD - Fri, June 17 | |
| -- | -- | Patio (0) 01.05.2023 | ||
| -- | -- | Privacy Divider / Fence (0) * 04.25.2022 | ||
| -- | -- | Sod / Seed / Landscaping (0) 06.29.2022 | ||
| -- | -- | HVAC Rough In (4) 02.24.2022 | in process 2/16 | |
| -- | -- | Plumbing Rough In (4) 03.21.2022 | In process 3/12 | |
| Vent microwave to exterior | ||||
| -- | -- | Electric Rough In (4) 03.17.2022 | ||
| -- | -- | Inspection (Rough In HVAC) (1) 03.24.2022 | ||
| -- | -- | Inspection (Rough In Plumbing) (1) 01.05.2023 | ||
| -- | -- | Inspection (Rough In Electric) (1) 01.05.2023 | ||
| -- | -- | Inspection (Framing) (1) * 01.05.2023 | ||
| -- | -- | Inspection (Deck Piers) (0) 01.05.2023 | ||
| -- | -- | Exterior Vinyl (0) * 04.18.2022 | ||
| -- | -- | Exterior Stone (0) 04.14.2022 | ||
| -- | -- | Insulation (2) * 03.30.2022 | 3/25 or 3/26 | |
| -- | -- | Inspection (Insulation) (1) 03.31.2022 | ||
| -- | -- | Inspection (Electric Service) (0) 06.02.2022 | ||
| -- | -- | Set Electric Meter (0) * 04.11.2023 | ||
| -- | -- | Inspection (Main Sewer Line) (0) 04.14.2022 | ||
| -- | -- | Inspection (Main Water Line) (0) 01.05.2023 | ||
| -- | -- | Order Interior Doors & Trim (0) 03.10.2022 | ||
| -- | -- | Drywall (Hang) (4) * 04.10.2022 | ||
| -- | -- | Loan Approval (0) 06.30.2022 | ||
| -- | -- | Deed Preparation (0) 04.13.2022 | ||
| -- | -- | Drywall (Tape, Block, Skim, Sand) (6) * 04.18.2022 | In process 4/10 | |
| -- | -- | Paint 1 (1) 04.20.2022 | ||
| -- | -- | Garage Door (0) 04.04.2022 | ||
| -- | -- | House Numbers (0) 06.29.2022 | ||
| -- | -- | Mailbox (0) 07.03.2022 | ||
| -- | -- | Cabinet Installation (2) * 04.18.2022 | 4/14 | |
| -- | -- | Granite Installation (1) * 05.07.2022 | 5/6 | |
| -- | -- | Interior Trim - Install (3) * 05.07.2022 | Needs painting 4/27 | |
| -- | -- | Interior Trim - Paint (1) 01.05.2023 | ||
| -- | -- | Luxury Vinyl Plank (3) * 05.26.2022 | In process 5/25 | |
| -- | -- | Luxury Vinyl Tile (0) 05.25.2022 | In process 5/21 | |
| -- | -- | Paint 2 (3) 05.30.2022 | ||
| -- | -- | Cover Floors (1) 06.01.2022 | ||
| -- | -- | Deliver Plumbing / Lighting Fixtures (0) 05.26.2022 | ||
| -- | -- | Shoe Moulding (0) 06.05.2022 | In process 6/1 | |
| -- | -- | Shelving, Door Knobs, Fire Extinguisher (0) * 06.05.2022 | Brushed Nickel accessories. In process 6/1 | |
| -- | -- | Install Coded Lockbox (add extra keys) (0) 06.08.2022 | ||
| -- | -- | Pay Water / Sewer Taps (0) 05.19.2022 | ||
| -- | -- | Set Water Meter (0) * 06.09.2022 | ||
| -- | -- | Electric Trim Out (3) * 06.18.2022 | Few items need completion 6/15 | |
| -- | -- | Ceiling Fans (0) 06.08.2022 | Living Room | |
| -- | -- | HVAC Trim Out (1) * 06.15.2022 | Furnace set 6/1 | |
| -- | -- | Plumbing Trim Out (2) * 06.05.2022 | Brushed Nickel Standard. In process 6/1 | |
| -- | -- | Install Appliances (0) * 06.08.2022 | ||
| -- | -- | Paint 3 (2) * 05.30.2022 | ||
| -- | -- | Carpet (2) 05.26.2022 | ||
| -- | -- | Appraiser Confirms Construction Completion (0) 07.05.2022 | ||
| -- | -- | Inspection (Final HVAC) (1) 01.05.2023 | ||
| -- | -- | Inspection (Final Plumbing) (1) 01.05.2023 | ||
| -- | -- | Inspection (Final Electric) (1) 01.05.2023 | ||
| -- | -- | Inspection (Final Building) (2) * 06.29.2022 | Wed, Jun 29 | |
| -- | -- | Pre Walk Through (0) 07.03.2022 | ||
| -- | -- | Stain Hardwood Stairs (1) * 06.29.2022 | ||
| -- | -- | Cleaning (1) 07.06.2022 | ||
| -- | -- | Certificate of Occupancy (1) * 06.30.2022 | ||
| -- | -- | C.O. to Lender (0) 06.30.2022 | ||
| -- | -- | Schedule Closing (0) 07.07.2022 | ||
| -- | -- | Buyer Walk Through (1) * 07.07.2022 | ||
| -- | -- | Payment for Upgrades (0) 06.30.2022 | ||
| -- | -- | Keys to Settlement Agent (0) 06.28.2022 | ||
| -- | -- | Review Settlement Statement (0) 07.08.2022 | ||
| -- | -- | Jerry Signs Closing Documents (0) 06.30.2022 | Wednesday, June 29, 1:00 PM | |
| -- | -- | Request Trash Tote From POA Manager (0) 06.28.2022 | ||
| -- | -- | Closing (1) 07.08.2022 | Brittany @ West View Title | |
| -- | -- | Remove Coded Lockbox (0) 07.27.2022 | ||