CONGERS-4 - * * * $3,2  ::  mgttsi
[ APPROVED PLANS ]       [ BUILD: 2a4q72 ]       [ ELEC: lzdema ]       [ PLUMB: mowjc1 ]       [ HVAC: j1nf2h ]
CRITICAL PATH   |   INSPECTIONS   |   FLOOR PLANS   |   SELECTIONS   |   SPECS   |   CHANGES   |   NHS
view photo archive
 
Sat    Oct 25      Ratified Contract? (0)      
Sat    Oct 25      $2500 Deposit Received (0)      
Sat    Oct 25      Association Packet Requested (0)      
Sat    Oct 25      Association Packet Received (0)      
Sat    Oct 25      Selections Meeting (0)      
Sat    Oct 25      Selections Sheet Signed (0)      
Sat    Oct 25      Amendment for Upgrades (B,S,L,T,BCP) (0)      
Sat    Oct 25      Deposit For Upgrades Received (0)      
Sat    Oct 25      Building Permit (30) *       
Fri    Dec 5      Order Roof & Floor Trusses (1)      
Mon    Dec 8      Order Windows & Doors (0)      
Mon    Dec 8      Stake Out Home (1)      
Tue    Dec 9      Excavate (2)      
Thu    Dec 11      Inspection (Footers) (1)      
Fri    Dec 12      Inspection (Concrete Wall) (1)      
Mon    Dec 15      Pour Footers (1) *       
Tue    Dec 16      Set Forms (2)      
Thu    Dec 18      Pour Foundation Walls (1)      
Fri    Dec 19      Plumb Slab (2)      
Tue    Dec 23      Inspection (Plumbing Under Slab) (1)      
Wed    Dec 24      Inspection (Conduit Under Slab) (1)      
Thu    Dec 25      Prepare Slab (1)      
Fri    Dec 26      Inspection (Slab) (1)      
Mon    Dec 29      Inspection (Drain Tile) (0)      
Mon    Dec 29      Pour Slab (1) *       
Tue    Dec 30      Settlement Agent Confirmed (0)      
Tue    Dec 30      Framing I (9)      
Mon    Jan 12      Order Steps (0)      
Mon    Jan 12      Order Tubs / Showers (0)      
Mon    Jan 12      Framing II (8)      
Thu    Jan 22      Framing III (8) *       
Tue    Feb 3      Verify Window & Roof Structure (0)      
Tue    Feb 3      Install Stairs (0) *       
Tue    Feb 3      Windows & Doors (0) *       
Tue    Feb 3      House Number and Status in Window (0)      
Tue    Feb 3      Roofing (0) *       
Tue    Feb 3      Order Cabinets (0)      
Tue    Feb 3      Order Appliances (0)      
Tue    Feb 3      Deck (0)      
Tue    Feb 3      Gutters (0)      
Tue    Feb 3      Driveway (0) *       
Tue    Feb 3      Patio (0)      
Tue    Feb 3      Privacy Divider / Fence (0) *       
Tue    Feb 3      Sod / Seed / Landscaping (0)      
Tue    Feb 3      HVAC Rough In (4)      
Mon    Feb 9      Rough In Microwave Vent (0)      
Mon    Feb 9      Plumbing Rough In (4)      
Fri    Feb 13      Electric Rough In (4)      
Thu    Feb 19      Inspection (Rough In HVAC) (1)      
Fri    Feb 20      Inspection (Rough In Plumbing) (1)      
Mon    Feb 23      Inspection (Rough In Electric) (1)      
Tue    Feb 24      Inspection (Framing) (1) *       
Wed    Feb 25      Inspection (Deck Piers) (0)      
Wed    Feb 25      Exterior Vinyl (0) *       
Wed    Feb 25      Exterior Stone (0)      
Wed    Feb 25      Insulation (2) *       
Fri    Feb 27      Inspection (Insulation) (1)      
Mon    Mar 2      Inspection (Electric Service) (0)      
Mon    Mar 2      Set Electric Meter (0) *       
Mon    Mar 2      Inspection (Main Sewer Line) (0)      
Mon    Mar 2      Inspection (Main Water Line) (0)      
Mon    Mar 2      Order Interior Doors & Trim (0)      
Mon    Mar 2      Drywall (Hang) (4) *       
Fri    Mar 6      Loan Approval (0)      
Fri    Mar 6      Deed Preparation (0)      
Fri    Mar 6      Drywall (Tape, Block, Skim, Sand) (6) *       
Mon    Mar 16      Paint 1 (1)      
Tue    Mar 17      Garage Door (0)      
Tue    Mar 17      House Numbers (0)      
Tue    Mar 17      Mailbox (0)      
Tue    Mar 17      Cabinet Installation (2) *       
Thu    Mar 19      Granite Installation (1) *       
Fri    Mar 20      Interior Trim - Install (3) *       
Wed    Mar 25      Order Plumbing / Lighting Fixtures (0)      
Wed    Mar 25      Interior Trim - Paint (1)      
Thu    Mar 26      Luxury Vinyl Plank (3) *       
Tue    Mar 31      Luxury Vinyl Tile (0)      
Tue    Mar 31      Paint 2 (3)      
Fri    Apr 3      Cover Floors (1)      
Mon    Apr 6      Deliver Plumbing / Lighting Fixtures (0)      
Mon    Apr 6      Shoe Moulding (0)      
Mon    Apr 6      Shelving, Door Knobs, Fire Extinguisher (0) *       
Mon    Apr 6      Install Coded Lockbox (add extra keys) (0)      
Mon    Apr 6      Pay Water / Sewer Taps (0)      
Mon    Apr 6      Set Water Meter (0) *       
Mon    Apr 6      Electric Trim Out (3) *       
Thu    Apr 9      Ceiling Fans (0)      
Thu    Apr 9      HVAC Trim Out (1) *       
Fri    Apr 10      Blower Door Test (1)      
Mon    Apr 13      Plumbing Trim Out (2) *       
Wed    Apr 15      Install Appliances (0) *       
Wed    Apr 15      Paint 3 (2) *       
Fri    Apr 17      Carpet (2)      
Tue    Apr 21      Appraiser Confirms Construction Completion (0)      
Tue    Apr 21      Inspection (Final HVAC) (1)      
Wed    Apr 22      Inspection (Final Plumbing) (1)      
Thu    Apr 23      Inspection (Final Electric) (1)      
Fri    Apr 24      Inspection (Final Building) (2) *       
Tue    Apr 28      Pre Walk Through (0)      
Tue    Apr 28      Stain Hardwood Stairs (1) *       
Wed    Apr 29      Cleaning (1)      
Thu    Apr 30      Certificate of Occupancy (1) *       
Fri    May 1      C.O. to Lender (0)      
Fri    May 1      Schedule Closing (0)      
Fri    May 1      Buyer Walk Through (1) *       
Mon    May 4      Payment for Upgrades (0)      
Mon    May 4      Keys to Settlement Agent (0)      
Mon    May 4      Review Settlement Statement (0)      
Mon    May 4      Jerry Signs Closing Documents (0)      
Mon    May 4      Request Trash Tote From POA Manager (0)      
Mon    May 4      Closing (1)      
Tue    May 5      Remove Coded Lockbox (0)