Grading Plan |
Comments or approval by Oct 31, 2025 |
|
-- |
-- |
Full Site Plan Approval |
County, VDOT, VDH |
|
|
-- |
-- |
Ratified Contract? (0) 10.21.2025 |
|
|
-- |
-- |
$2500 Deposit Received (0) 10.21.2025 |
|
|
-- |
-- |
Association Packet Requested (0) 10.21.2025 |
|
|
-- |
-- |
Association Packet Received (0) 10.21.2025 |
|
|
-- |
-- |
Selections Meeting (0) 10.21.2025 |
|
|
-- |
-- |
Selections Sheet Signed (0) 10.21.2025 |
|
|
-- |
-- |
Amendment for Upgrades (B,S,L,T,BCP) (0) 10.21.2025 |
|
|
-- |
-- |
Deposit For Upgrades Received (0) 10.21.2025 |
|
|
-- |
-- |
Building Permit (30) * 10.21.2025 |
|
|
-- |
-- |
Order Roof & Floor Trusses (1) 10.21.2025 |
|
|
-- |
-- |
Order Windows & Doors (0) 10.21.2025 |
|
|
-- |
-- |
Stake Out Home (1) 10.21.2025 |
|
|
-- |
-- |
Excavate (2) 10.21.2025 |
|
|
-- |
-- |
Inspection (Footers) (1) 10.21.2025 |
|
|
-- |
-- |
Inspection (Concrete Wall) (1) 10.21.2025 |
|
|
-- |
-- |
Pour Footers (1) * 10.21.2025 |
|
|
-- |
-- |
Set Forms (2) 10.21.2025 |
|
|
-- |
-- |
Pour Foundation Walls (1) 10.21.2025 |
|
|
-- |
-- |
Plumb Slab (2) 10.21.2025 |
|
|
-- |
-- |
Inspection (Plumbing Under Slab) (1) 10.21.2025 |
|
|
-- |
-- |
Inspection (Conduit Under Slab) (1) 10.21.2025 |
|
|
-- |
-- |
Prepare Slab (1) 10.21.2025 |
|
|
-- |
-- |
Inspection (Slab) (1) 10.21.2025 |
|
|
-- |
-- |
Inspection (Drain Tile) (0) 10.21.2025 |
|
|
-- |
-- |
Pour Slab (1) * 10.21.2025 |
|
|
-- |
-- |
Settlement Agent Confirmed (0) 10.21.2025 |
|
|
-- |
-- |
Framing I (9) 10.21.2025 |
|
|
-- |
-- |
Order Steps (0) 10.21.2025 |
|
|
-- |
-- |
Order Tubs / Showers (0) 10.21.2025 |
|
|
-- |
-- |
Framing II (8) 10.21.2025 |
|
|
-- |
-- |
Framing III (8) * 10.21.2025 |
|
|
-- |
-- |
Verify Window & Roof Structure (0) 10.21.2025 |
|
|
-- |
-- |
Install Stairs (0) * 10.21.2025 |
|
|
-- |
-- |
Windows & Doors (0) * 10.21.2025 |
|
|
-- |
-- |
House Number and Status in Window (0) 10.21.2025 |
|
|
-- |
-- |
Roofing (0) * 10.21.2025 |
|
|
-- |
-- |
Order Cabinets (0) 10.21.2025 |
|
|
-- |
-- |
Order Appliances (0) 10.21.2025 |
|
|
-- |
-- |
Deck (0) 10.21.2025 |
|
|
-- |
-- |
Gutters (0) 10.21.2025 |
|
|
-- |
-- |
Driveway (0) * 10.21.2025 |
|
|
-- |
-- |
Patio (0) 10.21.2025 |
|
|
-- |
-- |
Privacy Divider / Fence (0) * 10.21.2025 |
|
|
-- |
-- |
Sod / Seed / Landscaping (0) 10.21.2025 |
|
|
-- |
-- |
HVAC Rough In (4) 10.21.2025 |
|
|
-- |
-- |
Rough In Microwave Vent (0) 10.21.2025 |
|
|
-- |
-- |
Plumbing Rough In (4) 10.21.2025 |
|
|
-- |
-- |
Electric Rough In (4) 10.21.2025 |
|
|
-- |
-- |
Inspection (Rough In HVAC) (1) 10.21.2025 |
|
|
-- |
-- |
Inspection (Rough In Plumbing) (1) 10.21.2025 |
|
|
-- |
-- |
Inspection (Rough In Electric) (1) 10.21.2025 |
|
|
-- |
-- |
Inspection (Framing) (1) * 10.21.2025 |
|
|
-- |
-- |
Inspection (Deck Piers) (0) 10.21.2025 |
|
|
-- |
-- |
Exterior Vinyl (0) * 10.21.2025 |
|
|
-- |
-- |
Exterior Stone (0) 10.21.2025 |
|
|
-- |
-- |
Insulation (2) * 10.21.2025 |
|
|
-- |
-- |
Inspection (Insulation) (1) 10.21.2025 |
|
|
-- |
-- |
Inspection (Electric Service) (0) 10.21.2025 |
|
|
-- |
-- |
Set Electric Meter (0) * 10.21.2025 |
|
|
-- |
-- |
Inspection (Main Sewer Line) (0) 10.21.2025 |
|
|
-- |
-- |
Inspection (Main Water Line) (0) 10.21.2025 |
|
|
-- |
-- |
Order Interior Doors & Trim (0) 10.21.2025 |
|
|
-- |
-- |
Drywall (Hang) (4) * 10.21.2025 |
|
|
-- |
-- |
Loan Approval (0) 10.21.2025 |
|
|
-- |
-- |
Deed Preparation (0) 10.21.2025 |
|
|
-- |
-- |
Drywall (Tape, Block, Skim, Sand) (6) * 10.21.2025 |
|
|
-- |
-- |
Paint 1 (1) 10.21.2025 |
|
|
-- |
-- |
Garage Door (0) 10.21.2025 |
|
|
-- |
-- |
House Numbers (0) 10.21.2025 |
|
|
-- |
-- |
Mailbox (0) 10.21.2025 |
|
|
-- |
-- |
Cabinet Installation (2) * 10.21.2025 |
|
|
-- |
-- |
Granite Installation (1) * 10.21.2025 |
|
|
-- |
-- |
Interior Trim - Install (3) * 10.21.2025 |
|
|
-- |
-- |
Order Plumbing / Lighting Fixtures (0) 10.21.2025 |
|
|
-- |
-- |
Interior Trim - Paint (1) 10.21.2025 |
|
|
-- |
-- |
Luxury Vinyl Plank (3) * 10.21.2025 |
|
|
-- |
-- |
Luxury Vinyl Tile (0) 10.21.2025 |
|
|
-- |
-- |
Paint 2 (3) 10.21.2025 |
|
|
-- |
-- |
Cover Floors (1) 10.21.2025 |
|
|
-- |
-- |
Deliver Plumbing / Lighting Fixtures (0) 10.21.2025 |
|
|
-- |
-- |
Shoe Moulding (0) 10.21.2025 |
|
|
-- |
-- |
Shelving, Door Knobs, Fire Extinguisher (0) * 10.21.2025 |
|
|
-- |
-- |
Install Coded Lockbox (add extra keys) (0) 10.21.2025 |
|
|
-- |
-- |
Pay Water / Sewer Taps (0) 10.21.2025 |
|
|
-- |
-- |
Set Water Meter (0) * 10.21.2025 |
|
|
-- |
-- |
Electric Trim Out (3) * 10.21.2025 |
|
|
-- |
-- |
Ceiling Fans (0) 10.21.2025 |
|
|
-- |
-- |
HVAC Trim Out (1) * 10.21.2025 |
|
|
-- |
-- |
Blower Door Test (1) 10.21.2025 |
|
|
-- |
-- |
Plumbing Trim Out (2) * 10.21.2025 |
|
|
-- |
-- |
Install Appliances (0) * 10.21.2025 |
|
|
-- |
-- |
Paint 3 (2) * 10.21.2025 |
|
|
-- |
-- |
Carpet (2) 10.21.2025 |
|
|
-- |
-- |
Appraiser Confirms Construction Completion (0) 10.21.2025 |
|
|
-- |
-- |
Inspection (Final HVAC) (1) 10.21.2025 |
|
|
-- |
-- |
Inspection (Final Plumbing) (1) 10.21.2025 |
|
|
-- |
-- |
Inspection (Final Electric) (1) 10.21.2025 |
|
|
-- |
-- |
Inspection (Final Building) (2) * 10.21.2025 |
|
|
-- |
-- |
Pre Walk Through (0) 10.21.2025 |
|
|
-- |
-- |
Stain Hardwood Stairs (1) * 10.21.2025 |
|
|
-- |
-- |
Cleaning (1) 10.21.2025 |
|
|
-- |
-- |
Certificate of Occupancy (1) * 10.21.2025 |
|
|
-- |
-- |
C.O. to Lender (0) 10.21.2025 |
|
|
-- |
-- |
Schedule Closing (0) 10.21.2025 |
|
|
-- |
-- |
Buyer Walk Through (1) * 10.21.2025 |
|
|
-- |
-- |
Payment for Upgrades (0) 10.21.2025 |
|
|
-- |
-- |
Keys to Settlement Agent (0) 10.21.2025 |
|
|
-- |
-- |
Review Settlement Statement (0) 10.21.2025 |
|
|
-- |
-- |
Jerry Signs Closing Documents (0) 10.21.2025 |
|
|
-- |
-- |
Request Trash Tote From POA Manager (0) 10.21.2025 |
|
|
-- |
-- |
Closing (1) 10.21.2025 |
|
|
-- |
-- |
Remove Coded Lockbox (0) 10.21.2025 |
|
|