- 64  ::  2237 Deyerle Avenue
[ BUILD: 1809-0052 ]      
CRITICAL PATH   |   INSPECTIONS   |   FLOOR PLANS   |   SELECTIONS   |   SPECS   |   CHANGES   |   NHS
view photo archive
 
--   --   Jayne = 540-421-5327
--   --   Leaking outdoor faucet/flooding basement
Tue    Dec 16      Ratified Contract? (0)      
Tue    Dec 16      $2500 Deposit Received (0)      
Tue    Dec 16      Association Packet Requested (0)      
Tue    Dec 16      Association Packet Received (0)      
Tue    Dec 16      Selections Meeting (0)      
Tue    Dec 16      Selections Sheet Signed (0)      
Tue    Dec 16      Amendment for Upgrades (B,S,L,T,BCP) (0)      
Tue    Dec 16      Deposit For Upgrades Received (0)      
Tue    Dec 16      Inspection (Concrete Wall) (1)      
Wed    Dec 17      Inspection (Conduit Under Slab) (1)      
Thu    Dec 18      Inspection (Drain Tile) (0)      
Thu    Dec 18      Settlement Agent Confirmed (0)      
Thu    Dec 18      Verify Window & Roof Structure (0)      
Thu    Dec 18      Order Appliances (0)      
Thu    Dec 18      Patio (0)      
Thu    Dec 18      Rough In Microwave Vent (0)      
Thu    Dec 18      Inspection (Rough In Plumbing) (1)      
Fri    Dec 19      Inspection (Rough In Electric) (1)      
Mon    Dec 22      Inspection (Framing) (1) *       
Tue    Dec 23      Inspection (Deck Piers) (0)      
Tue    Dec 23      Exterior Stone (0)      
Tue    Dec 23      Set Electric Meter (0) *       
Tue    Dec 23      Inspection (Main Water Line) (0)      
Tue    Dec 23      Loan Approval (0)      
Tue    Dec 23      Deed Preparation (0)      
Tue    Dec 23      Mailbox (0)      
Tue    Dec 23      Interior Trim - Paint (1)      
Wed    Dec 24      Ceiling Fans (0)      
Wed    Dec 24      Blower Door Test (1)      
Thu    Dec 25      Inspection (Final HVAC) (1)      
Fri    Dec 26      Inspection (Final Plumbing) (1)      
Mon    Dec 29      Inspection (Final Electric) (1)      
Tue    Dec 30      Stain Hardwood Stairs (1) *       
Wed    Dec 31      Request Trash Tote From POA Manager (0)      
Wed    Dec 31      Remove Coded Lockbox (0)      
--   --   Buyer would like to do a framing and electrical walk-through
--   --   Brick - Carters Grove
--   --   Carter’s Grove- Ivory Vinyl- GREEN DOOR
--   --   Hardwood steps
--   --   Lots of changes..needs updating
--   --   Pocket door to MB -correct? (Pic)
--   --   Tub liners needed
--   --   Mold behind insulation
--   --   Water coming through the foundation wall
--   --   Door to master closet needs to be flipped per critical path notes
--   --   Bathroom cabinets
--   --   Coded Lockbox 6464
--   --  
--   --   Basement paint 2 needed on non-accent walls
--   --   Dented back sliding door frame JB
--   --   Bathroom cabinet hardware needed
--   --   Bathroom countertops needed July 10-delivering as I left house
--   --   Basement leaking 7/3 And 7/17
--   --   Install 9 inch cabinet and crown molding and missing drawer in kitchen Kyle Litten Monday/Tuesday July 6-7
--   --   Patch wood floor and small pantry in kitchen JB
--   --   Ron to fix pantry shelving per buyer request To accommodate freezer Confirmed Monday 7/8
--   --   Change out the window sash in living room JB
--   --   Install window screens and patio door screen JB
--   --   Install PVC board under patio JB
--   --   Caulk in front of all tubs/showers JB
--   --   Caulk all toilet and pedestal sink JB
--   --   Adjust double doors in upstairs bedroom JB
--   --   Put insulation back up in basement JB
--   --   Fix leak around water line in basement JB
--   --   Fill around holes at water heater And furnace JB
--   --   Set toilet in basement bathroom and 3 faucets
--   --   Need vinyl flooring in closet under stairs in basement Eric- confirmed for this week.
--   --   Drain spout needed JB
--   --   Fridge needed 7/10 Not here 7/17
--   --   drywall holes in pantry to be patched
--   --   HVAC filter door broken Tom contacted Ronnie
--   --   Patch holes in master closet and laundry room
--   --   Patch hole in upper left corner of Hall tub shower
--   --   Install faucet in the upper bathroom
--   --   Set refrigerator
--   --   Pocket door adjustment pantry
--   --   Missing bulbs in various lights throughout the home
--   --   Electrical outlet needed behind range
--   --   Clean out basement
--   --   Finished basement bathroom toilet, vanity, light
--   --   Reattach insulation in basement
--   --   Clean out bonus room
--   --   Spray bleach behind insulation we are mold stains are still detected
--   --   Damage to molding around basement sliding glass door
--   --   Apply PVC to gap between block and brick at basement
--   --   Missing tabs/hinge on HVAC at filter replacement
--   --   Final paint
-- -- Building Permit (30) *       
    11x11 patio under deck  
    Added paint colors and paint coverage on darker colors  
-- -- Order Roof & Floor Trusses (1)      
-- -- Order Windows & Doors (0)      
-- -- Stake Out Home (1)      
-- -- Excavate (2)      
-- -- Inspection (Footers) (1)      
-- -- Pour Footers (1) *       
-- -- Set Forms (2)      
-- -- Pour Foundation Walls (1)      
-- -- Plumb Slab (2)      
-- -- Inspection (Plumbing Under Slab) (1)       Thurs, Nov 8
-- -- Prepare Slab (1)      
-- -- Inspection (Slab) (1)      
-- -- Pour Slab (1) *       
-- -- Framing I (9)      
-- -- Order Steps (0)      
-- -- Order Tubs / Showers (0)      
-- -- Framing II (8)      
-- -- Framing III (8) *       
    Additional closet in kitchen  
    Pocket door between kitchen and pantry  
    Pocket door to master bathroom, on opposite end of wall between bedroom and bathroom  
    Basement family room stairwell, Carpet, for recessed lights, wall outlets, cable drop  
    Basement full bathroom 4 foot shower, vanity, light/fan, mirror with lights  
-- -- Install Stairs (0) *        Awaiting hardwood treads
-- -- Windows & Doors (0) *       
-- -- House Number and Status in Window (0)      
-- -- Roofing (0) *       
-- -- Order Cabinets (0)      
-- -- Deck (0)      
-- -- Gutters (0)      
-- -- Driveway (0) *        pouring patio 7/2
-- -- Privacy Divider / Fence (0) *       
-- -- Sod / Seed / Landscaping (0)      
-- -- HVAC Rough In (4)      
-- -- Plumbing Rough In (4)       Has not started as of Apr 15 (Hall Mechanical)
    Plumbing for a wet bar on family room wall behind the shower (drain vent ties, hot and cold stub out)  
-- -- Electric Rough In (4)       Starting soon as of Apr 1
    Added Electrical- (dedicated iron outlet and freezer outlet)  
-- -- Inspection (Rough In HVAC) (1)       TBD
-- -- Exterior Vinyl (0) *        Vinyl starting week of June 3
-- -- Insulation (2) *        soon 4/18
-- -- Inspection (Insulation) (1)      
-- -- Inspection (Electric Service) (0)      
-- -- Inspection (Main Sewer Line) (0)       Need water lines
-- -- Order Interior Doors & Trim (0)      
-- -- Drywall (Hang) (4) *        Done but basement 5/4
-- -- Drywall (Tape, Block, Skim, Sand) (6) *        Finished by May 17
-- -- Paint 1 (1)       Tues, May 21
-- -- Garage Door (0)      
-- -- House Numbers (0)       only Mailbox needed- Tom install this week.
-- -- Cabinet Installation (2) *        Kitchen done 5/29
    Mellamine Bathroom Cabinets (3)  
-- -- Granite Installation (1) *       
-- -- Interior Trim - Install (3) *       
    Crown molding on the main level- Contract  
-- -- Order Plumbing / Lighting Fixtures (0)      
-- -- Luxury Vinyl Plank (3) *       
-- -- Luxury Vinyl Tile (0)       Started as of June 10
-- -- Paint 2 (3)       Orange, Orange, Orange - anytime starting June 3
-- -- Cover Floors (1)      
-- -- Deliver Plumbing / Lighting Fixtures (0)      
-- -- Shoe Moulding (0)      
-- -- Shelving, Door Knobs, Fire Extinguisher (0) *        Mostly complete
-- -- Install Coded Lockbox (add extra keys) (0)      
-- -- Pay Water / Sewer Taps (0)      
-- -- Set Water Meter (0) *        Hopefully by Tuesday 7/9
-- -- Electric Trim Out (3) *        Should be done 7/18
-- -- HVAC Trim Out (1) *       
-- -- Plumbing Trim Out (2) *        Need 1 toilet and faucets
    Elongated Comfort Height Toilets (4)  
-- -- Install Appliances (0) *       
-- -- Paint 3 (2) *        Not done 7/10
-- -- Carpet (2)      
    Upgraded carpet and pad on stairs to basement  
-- -- Appraiser Confirms Construction Completion (0)      
-- -- Inspection (Final Building) (2) *        Monday, 7/22
-- -- Pre Walk Through (0)      
-- -- Cleaning (1)       Will begin as soon as we have water. Tom pelase confirm with Kate once complete so she can coordiante with cleaner
-- -- Certificate of Occupancy (1) *       
-- -- C.O. to Lender (0)      
-- -- Schedule Closing (0)       Will close ASAP. Tell Realtor when we have CO
-- -- Buyer Walk Through (1) *       
-- -- Payment for Upgrades (0)       Check for $5837 to be Given at closing. Has been communicated to both buyer and realtor.
-- -- Keys to Settlement Agent (0)      
-- -- Review Settlement Statement (0)      
-- -- Jerry Signs Closing Documents (0)       West View Title - Sara
-- -- Closing (1)