--   --   Kitchen corner cabinet door
--   --   Caulk kitchen corner cabinet
--   --   Patch master bathroom bath tub Waiting on new repair material
--   --   Sand and paint kitchen window trim
Tue    Apr 29      Ratified Contract? (0)      
Tue    Apr 29      $2500 Deposit Received (0)      
Tue    Apr 29      Association Packet Requested (0)      
Tue    Apr 29      Association Packet Received (0)      
Tue    Apr 29      Selections Meeting (0)      
Tue    Apr 29      Selections Sheet Signed (0)      
Tue    Apr 29      Amendment for Upgrades (B,S,L,T,BCP) (0)      
Tue    Apr 29      Deposit For Upgrades Received (0)      
Tue    Apr 29      Inspection (Concrete Wall) (1)      
Wed    Apr 30      Inspection (Conduit Under Slab) (1)      
Thu    May 1      Inspection (Drain Tile) (0)      
Thu    May 1      Settlement Agent Confirmed (0)      
Thu    May 1      Verify Window & Roof Structure (0)      
Thu    May 1      Order Appliances (0)      
Thu    May 1      Patio (0)      
Thu    May 1      Rough In Microwave Vent (0)      
Thu    May 1      Inspection (Rough In Plumbing) (1)      
Fri    May 2      Inspection (Rough In Electric) (1)      
Mon    May 5      Inspection (Deck Piers) (0)      
Mon    May 5      Inspection (Framing) (1) *       
Tue    May 6      Exterior Stone (0)      
Tue    May 6      Set Electric Meter (0) *       
Tue    May 6      Inspection (Main Water Line) (0)      
Tue    May 6      Loan Approval (0)      
Tue    May 6      Deed Preparation (0)      
Tue    May 6      Mailbox (0)      
Tue    May 6      Interior Trim - Paint (1)      
Wed    May 7      Ceiling Fans (0)      
Wed    May 7      Blower Door Test (1)      
Thu    May 8      Inspection (Final HVAC) (1)      
Fri    May 9      Inspection (Final Plumbing) (1)      
Mon    May 12      Inspection (Final Electric) (1)      
Tue    May 13      Stain Hardwood Stairs (1)      
Wed    May 14      Request Trash Tote From POA Manager (0)      
--   --   TWO MASTER SUITES See floor plans
--   --   Country Beige-GOLD DOOR
--   --   Is basement finished? Framing and electric are in???
--   --   Mold on green board (more than normal-pic)
--   --   Are the walls and plumbing in the right spot in the basement? See pics 4/14
--   --   Water leak at back right corner of basement? Damp all along back edge/corners
--   --   No 2 nd door leading to 2nd master suite. Correct?
--   --   Crown molding needed 5/19
--   --  
--   --  
--   --  
--   --  
--   --  
--   --   Bathroom cabinets Toe kick-still missing 6/22
--   --   Kate update buyer in timing after Thursday ops meeting
--   --   Drywall repair master bath Joe Meally- TOM TO COMMUNCIATE
--   --   Basement dripping water from wall into puddle, see pic 7/3
--   --   CODED LOCKBOX 6666
--   --   Install upper 9 inch cabinet door Kitchen Kyle Litten Monday/Tuesday July 6-7
--   --   Install ceiling fan
--   --   Install handrail JB
--   --   Caulk in front of all tubs and showers JB
--   --   Paint touch up laundry room Maher
--   --   Adjust cabinet doors in master bath. First cabinet doors to be adjusted Kyle Litten Monday/Tuesday July 6-7
--   --   Drywall patch right side vanity light in master bathroom Joe Meally- TOM TO COMMUNCIATE
--   --   Master bath shower floor drain needed Tom
--   --   Install dining chandelier Harry- to arrive Tuesday/Wednesday
--   --   PVC board underneath patio door JB
--   --   Kate update buyer on timing beginning of the week
--   --   Add screw covers to patio doors JB or painter
--   --   Install screens JBj patio door 7/29
--   --   Tighten up for switch receptacle in kitchen JB
--   --   Install shoe in front of patio door JB
--   --   Install low-voltage covers Tom/Harry?
--   --   Caulk toilet and pedestal sink All but half bath
--   --   Clean up back yard (7/7) Tom/JB
--   --   Drain spout outside 7/7 Tom/JB
--   --   Island cabinet door wont shut
--   --   Touch up paint throughout
--   --   Insulation in basement
--   --   MB light issue 7/20
--   --   MB closet fix shelf
--   --   Tub repair
--   --   Fan in master bathroom
-- -- Building Permit (30)      
-- -- Order Roof & Floor Trusses (1)      
-- -- Order Windows & Doors (0)      
-- -- Stake Out Home (1)      
-- -- Excavate (2)      
-- -- Inspection (Footers) (1)      
-- -- Pour Footers (1) *       
-- -- Set Forms (2)      
-- -- Pour Foundation Walls (1)      
-- -- Plumb Slab (2)      
-- -- Inspection (Plumbing Under Slab) (1)      
-- -- Prepare Slab (1)      
-- -- Inspection (Slab) (1)      
-- -- Pour Slab (1) *       
-- -- Framing I (9)      
-- -- Order Steps (0)      
-- -- Order Tubs / Showers (0)      
-- -- Framing II (8)      
-- -- Framing III (8) *       
-- -- Install Stairs (0)      
-- -- Windows & Doors (0) *       
-- -- House Number and Status in Window (0)      
-- -- Roofing (0) *       
-- -- Order Cabinets (0)       Kate will check with Kimberly
-- -- Deck (0)      
-- -- Gutters (0)      
-- -- Driveway (0) *       
-- -- Privacy Divider / Fence (0)      
-- -- Sod / Seed / Landscaping (0)      
-- -- HVAC Rough In (4)       Soon as of Mar 14
-- -- Inspection (Rough In HVAC) (1)       Mon, Apr 8
-- -- Plumbing Rough In (4)       Starting soon as of Apr 1
-- -- Electric Rough In (4)      
-- -- Exterior Vinyl (0) *       
-- -- Insulation (2) *        Tues, Apr 9
-- -- Inspection (Insulation) (1)      
-- -- Inspection (Electric Service) (0)      
-- -- Inspection (Main Sewer Line) (0)      
-- -- Order Interior Doors & Trim (0)      
-- -- Drywall (Hang) (4) *        Starting Apr 15
-- -- Drywall (Tape, Block, Skim, Sand) (6) *        Should be done Monday
-- -- Paint 1 (1)       Ready for paint on April 30
-- -- Garage Door (0) *       
-- -- House Numbers (0)       Only Mailbox needed- Tom to set this week.
-- -- Cabinet Installation (2) *       
-- -- Granite Installation (1) *       
-- -- Interior Trim - Install (3) *        Starting May 13
-- -- Order Plumbing / Lighting Fixtures (0)       Waiting on some lighting fixtures
-- -- Luxury Vinyl Plank (3) *       
-- -- Luxury Vinyl Tile (0)       Started as of May 13
-- -- Paint 2 (3)       In process 5/22
-- -- Cover Floors (1)      
-- -- Deliver Plumbing / Lighting Fixtures (0)      
-- -- Shoe Moulding (0)       On site
-- -- Shelving, Door Knobs, Fire Extinguisher (0) *        finishing week of 7/1
-- -- Install Coded Lockbox (add extra keys) (0)      
-- -- Pay Water / Sewer Taps (0)       ASAP
-- -- Set Water Meter (0) *        Hopefully by Tuesday 7/9
-- -- Electric Trim Out (3)       All but dining chandelier & closet lights in bedrooms
-- -- HVAC Trim Out (1)      
-- -- Plumbing Trim Out (2)       Waiting on plumber
-- -- Install Appliances (0) *       
-- -- Paint 3 (2) *       
-- -- Carpet (2)      
-- -- Appraiser Confirms Construction Completion (0)      
-- -- Inspection (Final Building) (2) *       
-- -- Pre Walk Through (0)      
-- -- Cleaning (1)       July 25
-- -- Certificate of Occupancy (1) *       
-- -- C.O. to Lender (0)      
-- -- Schedule Closing (0)      
-- -- Buyer Walk Through (1)       Completed by Tom
-- -- Payment for Upgrades (0)       $1,800
-- -- Keys to Settlement Agent (0)      
-- -- Review Settlement Statement (0)      
-- -- Jerry Signs Closing Documents (0)       West View Title - Anna
-- -- Closing (1)       This week of 7/29
-- -- Remove Coded Lockbox (0)