- 49  ::  2224 Deyerle Avenue
[ BUILD: 1812-0088 ]      
CRITICAL PATH   |   INSPECTIONS   |   FLOOR PLANS   |   SELECTIONS   |   SPECS   |   CHANGES   |   NHS
view photo archive
 
--   --   Carpet stained? Eric called again. I called as well. Waiting on return call 11/5 GWB
--   --   Stacey 252-202-3753
Thu    Nov 28      Ratified Contract? (0)      
Thu    Nov 28      $2500 Deposit Received (0)      
Thu    Nov 28      Association Packet Requested (0)      
Thu    Nov 28      Association Packet Received (0)      
Thu    Nov 28      Selections Meeting (0)      
Thu    Nov 28      Selections Sheet Signed (0)      
Thu    Nov 28      Amendment for Upgrades (B,S,L,T,BCP) (0)      
Thu    Nov 28      Deposit For Upgrades Received (0)      
Thu    Nov 28      Inspection (Concrete Wall) (1)      
Fri    Nov 29      Inspection (Conduit Under Slab) (1)      
Mon    Dec 2      Inspection (Drain Tile) (0)      
Mon    Dec 2      Settlement Agent Confirmed (0)      
Mon    Dec 2      Verify Window & Roof Structure (0)      
Mon    Dec 2      Patio (0)      
Mon    Dec 2      Rough In Microwave Vent (0)      
Mon    Dec 2      Inspection (Rough In Plumbing) (1)      
Tue    Dec 3      Inspection (Rough In Electric) (1)      
Wed    Dec 4      Inspection (Deck Piers) (0)      
Wed    Dec 4      Inspection (Framing) (1)      
Thu    Dec 5      Exterior Stone (0)      
Thu    Dec 5      Set Electric Meter (0)      
Thu    Dec 5      Inspection (Main Water Line) (0)      
Thu    Dec 5      Loan Approval (0)      
Thu    Dec 5      Deed Preparation (0)      
Thu    Dec 5      Mailbox (0)      
Thu    Dec 5      Interior Trim - Paint (1)      
Fri    Dec 6      Ceiling Fans (0)      
Fri    Dec 6      Blower Door Test (1)      
Mon    Dec 9      Inspection (Final HVAC) (1)      
Tue    Dec 10      Inspection (Final Plumbing) (1)      
Wed    Dec 11      Inspection (Final Electric) (1)      
Thu    Dec 12      Stain Hardwood Stairs (1)      
Fri    Dec 13      Request Trash Tote From POA Manager (0)      
--   --   Bone Vinyl Siding, Red Front Door
--   --   Needs tub basement
--   --   Needs crown molding 7/31
--   --   Cabinet hardware Missing pulls coming on Wed, Sep 18
--   --   Step transition strip needed on top step to LR 8/21 Leaning on wall in foyer 9/4
--   --   Basement vanity top not installed/other 2 are installed
--   --   CODED LOCKBOX 4949
--   --   CODED LOCKBOX 4949
--   --  
--   --   Fire extinguisher
--   --   Cabinet dents/scratches One drawer that needs replacing
--   --   Scratch in dishwasher CJ is checking it out
--   --   Range repair Whirlpool on Sept 25 between 8A and 9A
--   --   Stain steps
--   --   Batteries for smoke detectors
--   --   Drywall patch in 1/2 bath needed
--   --   Walk Through - Mon, Oct 30 @ 12:00 PM
--   --   Walk Through - Mon, Sep 30 @ 12:00 PM
--   --   Where’s the key?
--   --  
--   --   Stain steps?
--   --   Door handles kitchen cabinets Just one missing now
--   --   Fix trim at top of stairs Tom
--   --   Adjust closet doors
--   --   Grill register for under sink
--   --   Pressure wash siding
--   --   Paint front door
--   --   Plugs in patio door Tom
--   --   Wash garage floor
--   --   Install screens
--   --   Pressure wash siding Tom
--   --  
--   --   Touch up caulk at kitchen countertop marked with painters tape
--   --   Closed!
--   --   Replace grantie countertop Jan 8th
--   --   Unhook kitchen plumbing Morning of Jan 8th
--   --   Drain pipe issue Tom talked to roger to bury drain pipe going away from house GWB
--   --   Water in basement Greg to inspect
-- -- Building Permit (30)      
-- -- Order Roof & Floor Trusses (1)      
-- -- Order Windows & Doors (0)      
-- -- Stake Out Home (1)      
-- -- Excavate (2)      
-- -- Inspection (Footers) (1)      
-- -- Pour Footers (1)      
-- -- Set Forms (2)      
-- -- Pour Foundation Walls (1)      
-- -- Plumb Slab (2)      
-- -- Inspection (Plumbing Under Slab) (1)      
-- -- Prepare Slab (1)      
-- -- Inspection (Slab) (1)      
-- -- Pour Slab (1) *       
-- -- Framing I (9)       Starting April 1
-- -- Order Steps (0)      
-- -- Order Tubs / Showers (0)      
-- -- Framing II (8)      
-- -- Framing III (8) *       
-- -- Install Stairs (0)      
-- -- Windows & Doors (0)      
-- -- House Number and Status in Window (0)      
-- -- Roofing (0)      
-- -- Order Cabinets (0)      
-- -- Order Appliances (0)      
-- -- Deck (0)      
-- -- Gutters (0)      
-- -- Driveway (0)       Patio done 7/31
-- -- Privacy Divider / Fence (0)       $2100 allowance
-- -- Sod / Seed / Landscaping (0)       Wednesday
-- -- HVAC Rough In (4)       Working on it 6/1
-- -- Inspection (Rough In HVAC) (1)       Mon, Jun 17
-- -- Plumbing Rough In (4)       6/5 in progress
-- -- Electric Rough In (4)       6/10 in progress
-- -- Exterior Vinyl (0) *       
-- -- Insulation (2)       Wed, Jun 19- started
-- -- Inspection (Insulation) (1)       Fri, Jun 21
-- -- Inspection (Electric Service) (0)      
-- -- Inspection (Main Sewer Line) (0)      
-- -- Order Interior Doors & Trim (0)      
-- -- Drywall (Hang) (4) *        Hanging as of June 27
-- -- Drywall (Tape, Block, Skim, Sand) (6) *        Ongoing 7/13
-- -- Paint 1 (1)      
-- -- Garage Door (0)      
-- -- House Numbers (0)      
-- -- Cabinet Installation (2) *        Kitchen installed/need hardware
-- -- Granite Installation (1) *       
-- -- Interior Trim - Install (3)       Finishing the trim week of 7/29
-- -- Order Plumbing / Lighting Fixtures (0)      
-- -- Luxury Vinyl Plank (3) *       
-- -- Luxury Vinyl Tile (0)       Installed. Needs grout 8/10
-- -- Paint 2 (3)       Not done 9/4
-- -- Cover Floors (1)      
-- -- Deliver Plumbing / Lighting Fixtures (0)      
-- -- Shoe Moulding (0)       Done except foyer 9/4
-- -- Shelving, Door Knobs, Fire Extinguisher (0)       Done 9/4. Needs fire extinguisher
-- -- Install Coded Lockbox (add extra keys) (0)      
-- -- Pay Water / Sewer Taps (0)      
-- -- Set Water Meter (0)      
-- -- Electric Trim Out (3)       In process 9/14
-- -- HVAC Trim Out (1)       Set 8/7
-- -- Plumbing Trim Out (2)       In process 9/14
-- -- Install Appliances (0) *        All except stove
-- -- Paint 3 (2) *       
-- -- Carpet (2)       Going in 8/28
-- -- Appraiser Confirms Construction Completion (0)       October 9 at 11:00 AM
-- -- Inspection (Final Building) (2) *       
-- -- Pre Walk Through (0)      
-- -- Cleaning (1)       In process 9/25
-- -- Certificate of Occupancy (1) *       
-- -- C.O. to Lender (0)      
-- -- Schedule Closing (0)       Mon, Oct 14 at 11:00 AM
-- -- Buyer Walk Through (1)       First walk through completed- realtor walking back through with buyer Tuesday afternoon 10/8
-- -- Payment for Upgrades (0)      
-- -- Keys to Settlement Agent (0)      
-- -- Review Settlement Statement (0)      
-- -- Jerry Signs Closing Documents (0)      
-- -- Closing (1)       West View Title
-- -- Remove Coded Lockbox (0)