Carpet stained? |
Eric called again. I called as well. Waiting on return call 11/5 GWB |
|
-- |
-- |
Stacey 252-202-3753 |
|
|
Thu |
Nov 28 |
Ratified Contract? (0) |
|
|
Thu |
Nov 28 |
$2500 Deposit Received (0) |
|
|
Thu |
Nov 28 |
Association Packet Requested (0) |
|
|
Thu |
Nov 28 |
Association Packet Received (0) |
|
|
Thu |
Nov 28 |
Selections Meeting (0) |
|
|
Thu |
Nov 28 |
Selections Sheet Signed (0) |
|
|
Thu |
Nov 28 |
Amendment for Upgrades (B,S,L,T,BCP) (0) |
|
|
Thu |
Nov 28 |
Deposit For Upgrades Received (0) |
|
|
Thu |
Nov 28 |
Inspection (Concrete Wall) (1) |
|
|
Fri |
Nov 29 |
Inspection (Conduit Under Slab) (1) |
|
|
Mon |
Dec 2 |
Inspection (Drain Tile) (0) |
|
|
Mon |
Dec 2 |
Settlement Agent Confirmed (0) |
|
|
Mon |
Dec 2 |
Verify Window & Roof Structure (0) |
|
|
Mon |
Dec 2 |
Patio (0) |
|
|
Mon |
Dec 2 |
Rough In Microwave Vent (0) |
|
|
Mon |
Dec 2 |
Inspection (Rough In Plumbing) (1) |
|
|
Tue |
Dec 3 |
Inspection (Rough In Electric) (1) |
|
|
Wed |
Dec 4 |
Inspection (Deck Piers) (0) |
|
|
Wed |
Dec 4 |
Inspection (Framing) (1) |
|
|
Thu |
Dec 5 |
Exterior Stone (0) |
|
|
Thu |
Dec 5 |
Set Electric Meter (0) |
|
|
Thu |
Dec 5 |
Inspection (Main Water Line) (0) |
|
|
Thu |
Dec 5 |
Loan Approval (0) |
|
|
Thu |
Dec 5 |
Deed Preparation (0) |
|
|
Thu |
Dec 5 |
Mailbox (0) |
|
|
Thu |
Dec 5 |
Interior Trim - Paint (1) |
|
|
Fri |
Dec 6 |
Ceiling Fans (0) |
|
|
Fri |
Dec 6 |
Blower Door Test (1) |
|
|
Mon |
Dec 9 |
Inspection (Final HVAC) (1) |
|
|
Tue |
Dec 10 |
Inspection (Final Plumbing) (1) |
|
|
Wed |
Dec 11 |
Inspection (Final Electric) (1) |
|
|
Thu |
Dec 12 |
Stain Hardwood Stairs (1) |
|
|
Fri |
Dec 13 |
Request Trash Tote From POA Manager (0) |
|
|
|
-- |
-- |
Bone Vinyl Siding, Red Front Door |
|
|
-- |
-- |
Needs tub basement |
|
|
-- |
-- |
Needs crown molding 7/31 |
|
|
-- |
-- |
Cabinet hardware |
Missing pulls coming on Wed, Sep 18 |
|
-- |
-- |
Step transition strip needed on top step to LR 8/21 |
Leaning on wall in foyer 9/4 |
|
-- |
-- |
Basement vanity top not installed/other 2 are installed |
|
|
-- |
-- |
CODED LOCKBOX 4949 |
|
|
-- |
-- |
CODED LOCKBOX 4949 |
|
|
-- |
-- |
|
|
|
-- |
-- |
Fire extinguisher |
|
|
-- |
-- |
Cabinet dents/scratches |
One drawer that needs replacing |
|
-- |
-- |
Scratch in dishwasher |
CJ is checking it out |
|
-- |
-- |
Range repair |
Whirlpool on Sept 25 between 8A and 9A |
|
-- |
-- |
Stain steps |
|
|
-- |
-- |
Batteries for smoke detectors |
|
|
-- |
-- |
Drywall patch in 1/2 bath needed |
|
|
-- |
-- |
Walk Through - Mon, Oct 30 @ 12:00 PM |
|
|
-- |
-- |
Walk Through - Mon, Sep 30 @ 12:00 PM |
|
|
-- |
-- |
Where’s the key? |
|
|
-- |
-- |
|
|
|
-- |
-- |
Stain steps? |
|
|
-- |
-- |
Door handles kitchen cabinets |
Just one missing now |
|
-- |
-- |
Fix trim at top of stairs |
Tom |
|
-- |
-- |
Adjust closet doors |
|
|
-- |
-- |
Grill register for under sink |
|
|
-- |
-- |
Pressure wash siding |
|
|
-- |
-- |
Paint front door |
|
|
-- |
-- |
Plugs in patio door |
Tom |
|
-- |
-- |
Wash garage floor |
|
|
-- |
-- |
Install screens |
|
|
-- |
-- |
Pressure wash siding |
Tom |
|
-- |
-- |
|
|
|
-- |
-- |
Touch up caulk at kitchen countertop |
marked with painters tape |
|
-- |
-- |
Closed! |
|
|
-- |
-- |
Replace grantie countertop |
Jan 8th |
|
-- |
-- |
Unhook kitchen plumbing |
Morning of Jan 8th |
|
-- |
-- |
Drain pipe issue |
Tom talked to roger to bury drain pipe going away from house GWB |
|
-- |
-- |
Water in basement |
Greg to inspect |
|
-- |
-- |
Building Permit (30) |
|
|
-- |
-- |
Order Roof & Floor Trusses (1) |
|
|
-- |
-- |
Order Windows & Doors (0) |
|
|
-- |
-- |
Stake Out Home (1) |
|
|
-- |
-- |
Excavate (2) |
|
|
-- |
-- |
Inspection (Footers) (1) |
|
|
-- |
-- |
Pour Footers (1) |
|
|
-- |
-- |
Set Forms (2) |
|
|
-- |
-- |
Pour Foundation Walls (1) |
|
|
-- |
-- |
Plumb Slab (2) |
|
|
-- |
-- |
Inspection (Plumbing Under Slab) (1) |
|
|
-- |
-- |
Prepare Slab (1) |
|
|
-- |
-- |
Inspection (Slab) (1) |
|
|
-- |
-- |
Pour Slab (1) * |
|
|
-- |
-- |
Framing I (9) |
Starting April 1 |
|
-- |
-- |
Order Steps (0) |
|
|
-- |
-- |
Order Tubs / Showers (0) |
|
|
-- |
-- |
Framing II (8) |
|
|
-- |
-- |
Framing III (8) * |
|
|
-- |
-- |
Install Stairs (0) |
|
|
-- |
-- |
Windows & Doors (0) |
|
|
-- |
-- |
House Number and Status in Window (0) |
|
|
-- |
-- |
Roofing (0) |
|
|
-- |
-- |
Order Cabinets (0) |
|
|
-- |
-- |
Order Appliances (0) |
|
|
-- |
-- |
Deck (0) |
|
|
-- |
-- |
Gutters (0) |
|
|
-- |
-- |
Driveway (0) |
Patio done 7/31 |
|
-- |
-- |
Privacy Divider / Fence (0) |
$2100 allowance |
|
-- |
-- |
Sod / Seed / Landscaping (0) |
Wednesday |
|
-- |
-- |
HVAC Rough In (4) |
Working on it 6/1 |
|
-- |
-- |
Inspection (Rough In HVAC) (1) |
Mon, Jun 17 |
|
-- |
-- |
Plumbing Rough In (4) |
6/5 in progress |
|
-- |
-- |
Electric Rough In (4) |
6/10 in progress |
|
-- |
-- |
Exterior Vinyl (0) * |
|
|
-- |
-- |
Insulation (2) |
Wed, Jun 19- started |
|
-- |
-- |
Inspection (Insulation) (1) |
Fri, Jun 21 |
|
-- |
-- |
Inspection (Electric Service) (0) |
|
|
-- |
-- |
Inspection (Main Sewer Line) (0) |
|
|
-- |
-- |
Order Interior Doors & Trim (0) |
|
|
-- |
-- |
Drywall (Hang) (4) * |
Hanging as of June 27 |
|
-- |
-- |
Drywall (Tape, Block, Skim, Sand) (6) * |
Ongoing 7/13 |
|
-- |
-- |
Paint 1 (1) |
|
|
-- |
-- |
Garage Door (0) |
|
|
-- |
-- |
House Numbers (0) |
|
|
-- |
-- |
Cabinet Installation (2) * |
Kitchen installed/need hardware |
|
-- |
-- |
Granite Installation (1) * |
|
|
-- |
-- |
Interior Trim - Install (3) |
Finishing the trim week of 7/29 |
|
-- |
-- |
Order Plumbing / Lighting Fixtures (0) |
|
|
-- |
-- |
Luxury Vinyl Plank (3) * |
|
|
-- |
-- |
Luxury Vinyl Tile (0) |
Installed. Needs grout 8/10 |
|
-- |
-- |
Paint 2 (3) |
Not done 9/4 |
|
-- |
-- |
Cover Floors (1) |
|
|
-- |
-- |
Deliver Plumbing / Lighting Fixtures (0) |
|
|
-- |
-- |
Shoe Moulding (0) |
Done except foyer 9/4 |
|
-- |
-- |
Shelving, Door Knobs, Fire Extinguisher (0) |
Done 9/4. Needs fire extinguisher |
|
-- |
-- |
Install Coded Lockbox (add extra keys) (0) |
|
|
-- |
-- |
Pay Water / Sewer Taps (0) |
|
|
-- |
-- |
Set Water Meter (0) |
|
|
-- |
-- |
Electric Trim Out (3) |
In process 9/14 |
|
-- |
-- |
HVAC Trim Out (1) |
Set 8/7 |
|
-- |
-- |
Plumbing Trim Out (2) |
In process 9/14 |
|
-- |
-- |
Install Appliances (0) * |
All except stove |
|
-- |
-- |
Paint 3 (2) * |
|
|
-- |
-- |
Carpet (2) |
Going in 8/28 |
|
-- |
-- |
Appraiser Confirms Construction Completion (0) |
October 9 at 11:00 AM |
|
-- |
-- |
Inspection (Final Building) (2) * |
|
|
-- |
-- |
Pre Walk Through (0) |
|
|
-- |
-- |
Cleaning (1) |
In process 9/25 |
|
-- |
-- |
Certificate of Occupancy (1) * |
|
|
-- |
-- |
C.O. to Lender (0) |
|
|
-- |
-- |
Schedule Closing (0) |
Mon, Oct 14 at 11:00 AM |
|
-- |
-- |
Buyer Walk Through (1) |
First walk through completed- realtor walking back through with buyer Tuesday afternoon 10/8 |
|
-- |
-- |
Payment for Upgrades (0) |
|
|
-- |
-- |
Keys to Settlement Agent (0) |
|
|
-- |
-- |
Review Settlement Statement (0) |
|
|
-- |
-- |
Jerry Signs Closing Documents (0) |
|
|
-- |
-- |
Closing (1) |
West View Title |
|
-- |
-- |
Remove Coded Lockbox (0) |
|
|