ADDR
- 49  ::  2224 Deyerle Avenue
[ BUILD: 1812-0088 ]      
CRITICAL PATH   |   INSPECTIONS   |   FLOOR PLANS   |   SELECTIONS   |   SPECS   |   CHANGES   |   NHS
view photo archive
 
--   --   Carpet stained? Eric called again. I called as well. Waiting on return call 11/5 GWB
--   --   Stacey 252-202-3753
Tue    Dec 16      Ratified Contract? (0)      
Tue    Dec 16      $2500 Deposit Received (0)      
Tue    Dec 16      Association Packet Requested (0)      
Tue    Dec 16      Association Packet Received (0)      
Tue    Dec 16      Selections Meeting (0)      
Tue    Dec 16      Selections Sheet Signed (0)      
Tue    Dec 16      Amendment for Upgrades (B,S,L,T,BCP) (0)      
Tue    Dec 16      Deposit For Upgrades Received (0)      
Tue    Dec 16      Inspection (Concrete Wall) (1)      
Wed    Dec 17      Inspection (Conduit Under Slab) (1)      
Thu    Dec 18      Inspection (Drain Tile) (0)      
Thu    Dec 18      Settlement Agent Confirmed (0)      
Thu    Dec 18      Verify Window & Roof Structure (0)      
Thu    Dec 18      Patio (0)      
Thu    Dec 18      Rough In Microwave Vent (0)      
Thu    Dec 18      Inspection (Rough In Plumbing) (1)      
Fri    Dec 19      Inspection (Rough In Electric) (1)      
Mon    Dec 22      Inspection (Framing) (1) *       
Tue    Dec 23      Inspection (Deck Piers) (0)      
Tue    Dec 23      Exterior Stone (0)      
Tue    Dec 23      Set Electric Meter (0) *       
Tue    Dec 23      Inspection (Main Water Line) (0)      
Tue    Dec 23      Loan Approval (0)      
Tue    Dec 23      Deed Preparation (0)      
Tue    Dec 23      Mailbox (0)      
Tue    Dec 23      Interior Trim - Paint (1)      
Wed    Dec 24      Ceiling Fans (0)      
Wed    Dec 24      Blower Door Test (1)      
Thu    Dec 25      Inspection (Final HVAC) (1)      
Fri    Dec 26      Inspection (Final Plumbing) (1)      
Mon    Dec 29      Inspection (Final Electric) (1)      
Tue    Dec 30      Stain Hardwood Stairs (1) *       
Wed    Dec 31      Request Trash Tote From POA Manager (0)      
--   --   Bone Vinyl Siding, Red Front Door
--   --   Needs tub basement
--   --   Needs crown molding 7/31
--   --   Cabinet hardware Missing pulls coming on Wed, Sep 18
--   --   Step transition strip needed on top step to LR 8/21 Leaning on wall in foyer 9/4
--   --   Basement vanity top not installed/other 2 are installed
--   --   CODED LOCKBOX 4949
--   --   CODED LOCKBOX 4949
--   --  
--   --   Fire extinguisher
--   --   Cabinet dents/scratches One drawer that needs replacing
--   --   Scratch in dishwasher CJ is checking it out
--   --   Range repair Whirlpool on Sept 25 between 8A and 9A
--   --   Stain steps
--   --   Batteries for smoke detectors
--   --   Drywall patch in 1/2 bath needed
--   --   Walk Through - Mon, Oct 30 @ 12:00 PM
--   --   Walk Through - Mon, Sep 30 @ 12:00 PM
--   --   Where’s the key?
--   --  
--   --   Stain steps?
--   --   Door handles kitchen cabinets Just one missing now
--   --   Fix trim at top of stairs Tom
--   --   Adjust closet doors
--   --   Grill register for under sink
--   --   Pressure wash siding
--   --   Paint front door
--   --   Plugs in patio door Tom
--   --   Wash garage floor
--   --   Install screens
--   --   Pressure wash siding Tom
--   --  
--   --   Touch up caulk at kitchen countertop marked with painters tape
--   --   Closed!
--   --   Replace grantie countertop Jan 8th
--   --   Unhook kitchen plumbing Morning of Jan 8th
--   --   Drain pipe issue Tom talked to roger to bury drain pipe going away from house GWB
--   --   Water in basement Greg to inspect
-- -- Building Permit (30) *       
    Kitchen Tile Backsplash (allowance)  
    Crown Molding on Main Level  
    CREDIT- Removal of French style refrigerator from contract  
-- -- Order Roof & Floor Trusses (1)      
-- -- Order Windows & Doors (0)      
-- -- Stake Out Home (1)      
-- -- Excavate (2)      
-- -- Inspection (Footers) (1)      
-- -- Pour Footers (1) *       
-- -- Set Forms (2)      
-- -- Pour Foundation Walls (1)      
-- -- Plumb Slab (2)      
-- -- Inspection (Plumbing Under Slab) (1)      
-- -- Prepare Slab (1)      
-- -- Inspection (Slab) (1)      
-- -- Pour Slab (1) *       
-- -- Framing I (9)       Starting April 1
-- -- Order Steps (0)      
-- -- Order Tubs / Showers (0)      
-- -- Framing II (8)      
-- -- Framing III (8) *       
    Full finished basement with full bathroom  
-- -- Install Stairs (0) *       
-- -- Windows & Doors (0) *       
-- -- House Number and Status in Window (0)      
-- -- Roofing (0) *       
-- -- Order Cabinets (0)      
    Double Waste Basket in Island  
    Upgraded kitchen hardware  
-- -- Order Appliances (0)      
-- -- Deck (0)      
-- -- Gutters (0)      
-- -- Driveway (0) *        Patio done 7/31
-- -- Privacy Divider / Fence (0) *        $2100 allowance
    Fence (Allowance)  
-- -- Sod / Seed / Landscaping (0)       Wednesday
-- -- HVAC Rough In (4)       Working on it 6/1
-- -- Plumbing Rough In (4)       6/5 in progress
-- -- Electric Rough In (4)       6/10 in progress
-- -- Inspection (Rough In HVAC) (1)       Mon, Jun 17
-- -- Exterior Vinyl (0) *       
-- -- Insulation (2) *        Wed, Jun 19- started
-- -- Inspection (Insulation) (1)       Fri, Jun 21
-- -- Inspection (Electric Service) (0)      
-- -- Inspection (Main Sewer Line) (0)      
-- -- Order Interior Doors & Trim (0)      
-- -- Drywall (Hang) (4) *        Hanging as of June 27
-- -- Drywall (Tape, Block, Skim, Sand) (6) *        Ongoing 7/13
-- -- Paint 1 (1)      
-- -- Garage Door (0)      
-- -- House Numbers (0)      
-- -- Cabinet Installation (2) *        Kitchen installed/need hardware
-- -- Granite Installation (1) *       
-- -- Interior Trim - Install (3) *        Finishing the trim week of 7/29
-- -- Order Plumbing / Lighting Fixtures (0)      
-- -- Luxury Vinyl Plank (3) *       
-- -- Luxury Vinyl Tile (0)       Installed. Needs grout 8/10
-- -- Paint 2 (3)       Not done 9/4
-- -- Cover Floors (1)      
-- -- Deliver Plumbing / Lighting Fixtures (0)      
-- -- Shoe Moulding (0)       Done except foyer 9/4
-- -- Shelving, Door Knobs, Fire Extinguisher (0) *        Done 9/4. Needs fire extinguisher
    Peephole in front door  
-- -- Install Coded Lockbox (add extra keys) (0)      
-- -- Pay Water / Sewer Taps (0)      
-- -- Set Water Meter (0) *       
-- -- Electric Trim Out (3) *        In process 9/14
-- -- HVAC Trim Out (1) *        Set 8/7
-- -- Plumbing Trim Out (2) *        In process 9/14
-- -- Install Appliances (0) *        All except stove
    Whirlpool Stainless Steel Kitchen Appliances  
    French Door Style Refrigerator  
-- -- Paint 3 (2) *       
-- -- Carpet (2)       Going in 8/28
    Upgraded carpet padding on upper level  
-- -- Appraiser Confirms Construction Completion (0)       October 9 at 11:00 AM
-- -- Inspection (Final Building) (2) *       
-- -- Pre Walk Through (0)      
-- -- Cleaning (1)       In process 9/25
-- -- Certificate of Occupancy (1) *       
-- -- C.O. to Lender (0)      
-- -- Schedule Closing (0)       Mon, Oct 14 at 11:00 AM
-- -- Buyer Walk Through (1) *        First walk through completed- realtor walking back through with buyer Tuesday afternoon 10/8
-- -- Payment for Upgrades (0)      
-- -- Keys to Settlement Agent (0)      
-- -- Review Settlement Statement (0)      
-- -- Jerry Signs Closing Documents (0)      
-- -- Closing (1)       West View Title
-- -- Remove Coded Lockbox (0)