CRITICAL PATH   |   INSPECTIONS   |   FLOOR PLANS   |   SELECTIONS   |   SPECS   |   CHANGES   |   NHS
view photo archive
 
--   --   Test Ned will do this
Thu    Nov 28      Ratified Contract? (0)      
Thu    Nov 28      $2500 Deposit Received (0)      
Thu    Nov 28      Association Packet Requested (0)      
Thu    Nov 28      Association Packet Received (0)      
Thu    Nov 28      Selections Meeting (0)      
Thu    Nov 28      Selections Sheet Signed (0)      
Thu    Nov 28      Amendment for Upgrades (B,S,L,T,BCP) (0)      
Thu    Nov 28      Deposit For Upgrades Received (0)      
Thu    Nov 28      Building Permit (30)       Fred will do this
Thu    Jan 9      Order Roof & Floor Trusses (1)       mindy will do this
Fri    Jan 10      Order Windows & Doors (0)       Tom will do this
Fri    Jan 10      Stake Out Home (1)      
Mon    Jan 13      Excavate (2)      
Wed    Jan 15      Inspection (Footers) (1)       test
Thu    Jan 16      Inspection (Concrete Wall) (1)      
Fri    Jan 17      Pour Footers (1)      
Mon    Jan 20      Set Forms (2)      
Wed    Jan 22      Pour Foundation Walls (1)       test
Thu    Jan 23      Plumb Slab (2)      
Mon    Jan 27      Inspection (Conduit Under Slab) (1)      
Tue    Jan 28      Prepare Slab (1)      
Wed    Jan 29      Inspection (Slab) (1)       test
Thu    Jan 30      Inspection (Drain Tile) (0)      
Thu    Jan 30      Pour Slab (1) *       
Fri    Jan 31      Settlement Agent Confirmed (0)      
Fri    Jan 31      Order Tubs / Showers (0)      
Fri    Jan 31      Framing II (8)      
Wed    Feb 12      Framing III (8) *       
Mon    Feb 24      Verify Window & Roof Structure (0)      
Mon    Feb 24      Install Stairs (0)      
Mon    Feb 24      Windows & Doors (0)       test
Mon    Feb 24      House Number and Status in Window (0)      
Mon    Feb 24      Roofing (0)      
Mon    Feb 24      Order Cabinets (0)      
Mon    Feb 24      Order Appliances (0)      
Mon    Feb 24      Gutters (0)      
Mon    Feb 24      Driveway (0)      
Mon    Feb 24      Patio (0)      
Mon    Feb 24      Privacy Divider / Fence (0)      
Mon    Feb 24      Sod / Seed / Landscaping (0)      
Mon    Feb 24      Inspection (Rough In HVAC) (1)      
Tue    Feb 25      Rough In Microwave Vent (0)      
Tue    Feb 25      Inspection (Rough In Plumbing) (1)      
Wed    Feb 26      Electric Rough In (4)      
Tue    Mar 4      Inspection (Rough In Electric) (1)      
Wed    Mar 5      Inspection (Deck Piers) (0)      
Wed    Mar 5      Inspection (Framing) (1)      
Thu    Mar 6      Exterior Vinyl (0) *       
Thu    Mar 6      Exterior Stone (0)      
Thu    Mar 6      Insulation (2)      
Mon    Mar 10      Inspection (Insulation) (1)      
Tue    Mar 11      Inspection (Electric Service) (0)      
Tue    Mar 11      Set Electric Meter (0)      
Tue    Mar 11      Inspection (Main Sewer Line) (0)      
Tue    Mar 11      Inspection (Main Water Line) (0)      
Tue    Mar 11      Order Interior Doors & Trim (0)      
Tue    Mar 11      Drywall (Hang) (4) *       
Mon    Mar 17      Loan Approval (0)      
Mon    Mar 17      Deed Preparation (0)      
Mon    Mar 17      Drywall (Tape, Block, Skim, Sand) (6) *       
Tue    Mar 25      Paint 1 (1)      
Wed    Mar 26      Garage Door (0)      
Wed    Mar 26      House Numbers (0)      
Wed    Mar 26      Mailbox (0)      
Wed    Mar 26      Cabinet Installation (2) *       
Fri    Mar 28      Granite Installation (1) *       
Mon    Mar 31      Interior Trim - Install (3)      
Thu    Apr 3      Order Plumbing / Lighting Fixtures (0)      
Thu    Apr 3      Interior Trim - Paint (1)      
Fri    Apr 4      Luxury Vinyl Plank (3) *       
Wed    Apr 9      Luxury Vinyl Tile (0)      
Wed    Apr 9      Paint 2 (3)      
Mon    Apr 14      Cover Floors (1)      
Tue    Apr 15      Deliver Plumbing / Lighting Fixtures (0)      
Tue    Apr 15      Shoe Moulding (0)      
Tue    Apr 15      Shelving, Door Knobs, Fire Extinguisher (0)      
Tue    Apr 15      Install Coded Lockbox (add extra keys) (0)      
Tue    Apr 15      Pay Water / Sewer Taps (0)      
Tue    Apr 15      Set Water Meter (0)      
Tue    Apr 15      Electric Trim Out (3)      
Fri    Apr 18      Ceiling Fans (0)      
Fri    Apr 18      HVAC Trim Out (1)      
Mon    Apr 21      Blower Door Test (1)      
Tue    Apr 22      Plumbing Trim Out (2)      
Thu    Apr 24      Install Appliances (0) *       
Thu    Apr 24      Paint 3 (2) *       
Mon    Apr 28      Carpet (2)      
Wed    Apr 30      Appraiser Confirms Construction Completion (0)      
Wed    Apr 30      Inspection (Final HVAC) (1)      
Thu    May 1      Inspection (Final Plumbing) (1)      
Fri    May 2      Inspection (Final Electric) (1)      
Mon    May 5      Pre Walk Through (0)      
Mon    May 5      Stain Hardwood Stairs (1)      
Tue    May 6      Cleaning (1)      
Wed    May 7      Certificate of Occupancy (1) *       
Thu    May 8      C.O. to Lender (0)      
Thu    May 8      Schedule Closing (0)      
Thu    May 8      Buyer Walk Through (1)      
Fri    May 9      Payment for Upgrades (0)      
Fri    May 9      Keys to Settlement Agent (0)      
Fri    May 9      Review Settlement Statement (0)      
Fri    May 9      Jerry Signs Closing Documents (0)      
Fri    May 9      Request Trash Tote From POA Manager (0)      
Fri    May 9      Closing (1)      
Mon    May 12      Remove Coded Lockbox (0)      
-- -- Inspection (Plumbing Under Slab) (1)      
-- -- Framing I (9)      
-- -- Order Steps (0)      
-- -- Deck (0)      
-- -- HVAC Rough In (4)      
-- -- Plumbing Rough In (4)      
-- -- Inspection (Final Building) (2) *