ADDR
- 127  :: 
CRITICAL PATH   |   INSPECTIONS   |   FLOOR PLANS   |   SELECTIONS   |   SPECS   |   CHANGES   |   NHS
view photo archive
 
--   --   Test Ned will do this
Tue    Dec 16      Ratified Contract? (0)      
Tue    Dec 16      $2500 Deposit Received (0)      
Tue    Dec 16      Association Packet Requested (0)      
Tue    Dec 16      Association Packet Received (0)      
Tue    Dec 16      Selections Meeting (0)      
Tue    Dec 16      Selections Sheet Signed (0)      
Tue    Dec 16      Amendment for Upgrades (B,S,L,T,BCP) (0)      
Tue    Dec 16      Deposit For Upgrades Received (0)      
Tue    Dec 16      Building Permit (30) *        Fred will do this
Tue    Jan 27      Order Roof & Floor Trusses (1)       mindy will do this
Wed    Jan 28      Order Windows & Doors (0)       Tom will do this
Wed    Jan 28      Stake Out Home (1)      
Thu    Jan 29      Excavate (2)      
Mon    Feb 2      Inspection (Footers) (1)       test
Tue    Feb 3      Inspection (Concrete Wall) (1)      
Wed    Feb 4      Pour Footers (1) *       
Thu    Feb 5      Set Forms (2)      
Mon    Feb 9      Pour Foundation Walls (1)       test
Tue    Feb 10      Plumb Slab (2)      
Thu    Feb 12      Inspection (Conduit Under Slab) (1)      
Fri    Feb 13      Prepare Slab (1)      
Mon    Feb 16      Inspection (Slab) (1)       test
Tue    Feb 17      Inspection (Drain Tile) (0)      
Tue    Feb 17      Pour Slab (1) *       
Wed    Feb 18      Settlement Agent Confirmed (0)      
Wed    Feb 18      Order Tubs / Showers (0)      
Wed    Feb 18      Framing II (8)      
Mon    Mar 2      Framing III (8) *       
Thu    Mar 12      Verify Window & Roof Structure (0)      
Thu    Mar 12      Install Stairs (0) *       
Thu    Mar 12      Windows & Doors (0) *        test
Thu    Mar 12      House Number and Status in Window (0)      
Thu    Mar 12      Roofing (0) *       
Thu    Mar 12      Order Cabinets (0)      
Thu    Mar 12      Order Appliances (0)      
Thu    Mar 12      Gutters (0)      
Thu    Mar 12      Driveway (0) *       
Thu    Mar 12      Patio (0)      
Thu    Mar 12      Privacy Divider / Fence (0) *       
Thu    Mar 12      Sod / Seed / Landscaping (0)      
Thu    Mar 12      Rough In Microwave Vent (0)      
Thu    Mar 12      Electric Rough In (4)      
Wed    Mar 18      Inspection (Rough In HVAC) (1)      
Thu    Mar 19      Inspection (Rough In Plumbing) (1)      
Fri    Mar 20      Inspection (Rough In Electric) (1)      
Mon    Mar 23      Inspection (Framing) (1) *       
Tue    Mar 24      Inspection (Deck Piers) (0)      
Tue    Mar 24      Exterior Vinyl (0) *       
Tue    Mar 24      Exterior Stone (0)      
Tue    Mar 24      Insulation (2) *       
Thu    Mar 26      Inspection (Insulation) (1)      
Fri    Mar 27      Inspection (Electric Service) (0)      
Fri    Mar 27      Set Electric Meter (0) *       
Fri    Mar 27      Inspection (Main Sewer Line) (0)      
Fri    Mar 27      Inspection (Main Water Line) (0)      
Fri    Mar 27      Order Interior Doors & Trim (0)      
Fri    Mar 27      Drywall (Hang) (4) *       
Thu    Apr 2      Loan Approval (0)      
Thu    Apr 2      Deed Preparation (0)      
Thu    Apr 2      Drywall (Tape, Block, Skim, Sand) (6) *       
Fri    Apr 10      Paint 1 (1)      
Mon    Apr 13      Garage Door (0)      
Mon    Apr 13      House Numbers (0)      
Mon    Apr 13      Mailbox (0)      
Mon    Apr 13      Cabinet Installation (2) *       
Wed    Apr 15      Granite Installation (1) *       
Thu    Apr 16      Interior Trim - Install (3) *       
Tue    Apr 21      Order Plumbing / Lighting Fixtures (0)      
Tue    Apr 21      Interior Trim - Paint (1)      
Wed    Apr 22      Luxury Vinyl Plank (3) *       
Mon    Apr 27      Luxury Vinyl Tile (0)      
Mon    Apr 27      Paint 2 (3)      
Thu    Apr 30      Cover Floors (1)      
Fri    May 1      Deliver Plumbing / Lighting Fixtures (0)      
Fri    May 1      Shoe Moulding (0)      
Fri    May 1      Shelving, Door Knobs, Fire Extinguisher (0) *       
Fri    May 1      Install Coded Lockbox (add extra keys) (0)      
Fri    May 1      Pay Water / Sewer Taps (0)      
Fri    May 1      Set Water Meter (0) *       
Fri    May 1      Electric Trim Out (3) *       
Wed    May 6      Ceiling Fans (0)      
Wed    May 6      HVAC Trim Out (1) *       
Thu    May 7      Blower Door Test (1)      
Fri    May 8      Plumbing Trim Out (2) *       
Tue    May 12      Install Appliances (0) *       
Tue    May 12      Paint 3 (2) *       
Thu    May 14      Carpet (2)      
Mon    May 18      Appraiser Confirms Construction Completion (0)      
Mon    May 18      Inspection (Final HVAC) (1)      
Tue    May 19      Inspection (Final Plumbing) (1)      
Wed    May 20      Inspection (Final Electric) (1)      
Thu    May 21      Pre Walk Through (0)      
Thu    May 21      Stain Hardwood Stairs (1) *       
Fri    May 22      Cleaning (1)      
Mon    May 25      Certificate of Occupancy (1) *       
Tue    May 26      C.O. to Lender (0)      
Tue    May 26      Schedule Closing (0)      
Tue    May 26      Buyer Walk Through (1) *       
Wed    May 27      Payment for Upgrades (0)      
Wed    May 27      Keys to Settlement Agent (0)      
Wed    May 27      Review Settlement Statement (0)      
Wed    May 27      Jerry Signs Closing Documents (0)      
Wed    May 27      Request Trash Tote From POA Manager (0)      
Wed    May 27      Closing (1)      
Thu    May 28      Remove Coded Lockbox (0)      
-- -- Inspection (Plumbing Under Slab) (1)      
-- -- Framing I (9)      
-- -- Order Steps (0)      
-- -- Deck (0)      
-- -- HVAC Rough In (4)      
-- -- Plumbing Rough In (4)      
-- -- Inspection (Final Building) (2) *