RED FRONT DOOR |
|
|
Thu |
Nov 28 |
Ratified Contract? (0) |
|
|
Thu |
Nov 28 |
$2500 Deposit Received (0) |
|
|
Thu |
Nov 28 |
Association Packet Requested (0) |
|
|
Thu |
Nov 28 |
Association Packet Received (0) |
|
|
Thu |
Nov 28 |
Selections Meeting (0) |
|
|
Thu |
Nov 28 |
Selections Sheet Signed (0) |
|
|
Thu |
Nov 28 |
Amendment for Upgrades (B,S,L,T,BCP) (0) |
|
|
Thu |
Nov 28 |
Deposit For Upgrades Received (0) |
|
|
Thu |
Nov 28 |
Inspection (Concrete Wall) (1) |
|
|
Fri |
Nov 29 |
Inspection (Conduit Under Slab) (1) |
|
|
Mon |
Dec 2 |
Inspection (Drain Tile) (0) |
|
|
Mon |
Dec 2 |
Settlement Agent Confirmed (0) |
|
|
Mon |
Dec 2 |
Verify Window & Roof Structure (0) |
|
|
Mon |
Dec 2 |
Order Appliances (0) |
|
|
Mon |
Dec 2 |
Patio (0) |
|
|
Mon |
Dec 2 |
Rough In Microwave Vent (0) |
|
|
Mon |
Dec 2 |
Inspection (Rough In Plumbing) (1) |
|
|
Tue |
Dec 3 |
Inspection (Rough In Electric) (1) |
|
|
Wed |
Dec 4 |
Inspection (Deck Piers) (0) |
|
|
Wed |
Dec 4 |
Inspection (Framing) (1) |
|
|
Thu |
Dec 5 |
Exterior Stone (0) |
|
|
Thu |
Dec 5 |
Set Electric Meter (0) |
|
|
Thu |
Dec 5 |
Inspection (Main Water Line) (0) |
|
|
Thu |
Dec 5 |
Loan Approval (0) |
|
|
Thu |
Dec 5 |
Deed Preparation (0) |
|
|
Thu |
Dec 5 |
Mailbox (0) |
|
|
Thu |
Dec 5 |
Order Plumbing / Lighting Fixtures (0) |
|
|
Thu |
Dec 5 |
Interior Trim - Paint (1) |
|
|
Fri |
Dec 6 |
Ceiling Fans (0) |
|
|
Fri |
Dec 6 |
Blower Door Test (1) |
|
|
Mon |
Dec 9 |
Inspection (Final HVAC) (1) |
|
|
Tue |
Dec 10 |
Inspection (Final Plumbing) (1) |
|
|
Wed |
Dec 11 |
Inspection (Final Electric) (1) |
|
|
Thu |
Dec 12 |
Stain Hardwood Stairs (1) |
|
|
Fri |
Dec 13 |
Schedule Closing (0) |
|
|
Fri |
Dec 13 |
Keys to Settlement Agent (0) |
|
|
Fri |
Dec 13 |
Review Settlement Statement (0) |
|
|
Fri |
Dec 13 |
Jerry Signs Closing Documents (0) |
|
|
Fri |
Dec 13 |
Request Trash Tote From POA Manager (0) |
|
|
Fri |
Dec 13 |
Remove Coded Lockbox (0) |
|
|
|
-- |
-- |
Must be in home by Mar 31 |
|
|
-- |
-- |
Tom will inspect framing |
|
|
-- |
-- |
Missing basement shower |
Mon, Feb 5 |
|
-- |
-- |
Vinyl siding at front porch |
|
|
-- |
-- |
Basement vanity and top |
Still....waiting on installation date from Jeff |
|
-- |
-- |
Fill up the gas tank |
Tom |
|
-- |
-- |
Hook up furnace |
Clem |
|
-- |
-- |
Trim fixes |
|
|
-- |
-- |
Paint touch ups throughout and caulk |
|
|
-- |
-- |
Adjust screen door |
|
|
-- |
-- |
Pushback range |
|
|
-- |
-- |
Missing pin on downstairs closet door |
|
|
-- |
-- |
Replace front door weatherstripping |
|
|
-- |
-- |
Install window screens |
|
|
-- |
-- |
Transition strip at patio doors |
|
|
-- |
-- |
Repair boards with gashes, At landing and at bottom of stairs |
|
|
-- |
-- |
Missing receptacle cover upstairs bedroom |
|
|
-- |
-- |
Replace and cut trim laundry room |
|
|
-- |
-- |
Put cover on master closet fluorescent light |
|
|
-- |
-- |
Master shower tent repair, Color discoloration |
|
|
-- |
-- |
I just latch on upstairs bedroom closet doors |
|
|
-- |
-- |
Finish trim edge of the island |
|
|
-- |
-- |
CODED LOCKBOX --- 3674 |
|
|
-- |
-- |
Master shower hand |
|
|
-- |
-- |
Hand held shower heads |
add blocking - Kate will talk to Kara and Mindy |
|
-- |
-- |
Please sweep out and remove trash upstairs bedrooms before carpet |
|
|
-- |
-- |
Top two trim pieces to high in stairs, top of stairs and landing |
Osbaldo |
|
-- |
-- |
Stain steps |
Saturday + Sunday |
|
-- |
-- |
Install mirrors and vanity lights |
Greg |
|
-- |
-- |
CODED LOCKBOX --- 3476 |
|
|
-- |
-- |
Last coat of polyurethane |
Tuesday night |
|
-- |
-- |
Sod |
|
|
-- |
-- |
Towel rings |
Wednesday, Apr 18 |
|
-- |
-- |
Cover for water access green to match them all |
|
|
-- |
-- |
Missing screws breaker box |
Osbaldo |
|
-- |
-- |
Fix deadbolt basement door |
|
|
-- |
-- |
Transition strip for basement |
Stained to match |
|
-- |
-- |
Phil and fix nail holes at basement door exterior |
|
|
-- |
-- |
Paint touch ups throughout |
|
|
-- |
-- |
Missing trim piece on the landing |
|
|
-- |
-- |
Adjust door to deck |
|
|
-- |
-- |
Sand and paint and powder bath near light fixture |
Put globes on |
|
-- |
-- |
Finish installing gloves and like fixture in powder bath |
|
|
-- |
-- |
Sand and paint and add receptacle upstairs between bedrooms |
|
|
-- |
-- |
Adjust double closet doors |
|
|
-- |
-- |
Fix side splash in master bathroom |
|
|
-- |
-- |
Pocket door hardware |
Tom to purchase hardware and install today 4/23 |
|
-- |
-- |
Shoe mold In up hall bathroom |
|
|
-- |
-- |
Washer and dryer install |
|
|
-- |
-- |
Washer and dryer ASAP |
|
|
-- |
-- |
Add shower bars |
|
|
-- |
-- |
Sand and paint the door edges that feel rough |
|
|
-- |
-- |
Fix handrail going upstairs |
|
|
-- |
-- |
Master bath shoemold and laundry room trim |
|
|
-- |
-- |
Fix handrail going upstairs |
Osbaldo |
|
-- |
-- |
Shower bars |
|
|
-- |
-- |
Remove Lockbox 4.24 |
|
|
-- |
-- |
Second basement banister needs painting where it was sanded |
Need to be done today 4.23 |
|
-- |
-- |
Pocket Door hardware needs to be installed |
Needs to be done today 4.23 |
|
-- |
-- |
Light bulb for the outdoor light on the basement level is missing |
Need to be done today 4.23 |
|
-- |
-- |
Building Permit (30) |
|
|
-- |
-- |
Order Roof & Floor Trusses (1) |
|
|
-- |
-- |
Order Windows & Doors (0) |
|
|
-- |
-- |
Stake Out Home (1) |
|
|
-- |
-- |
Excavate (2) |
|
|
-- |
-- |
Inspection (Footers) (1) |
|
|
-- |
-- |
Pour Footers (1) |
|
|
-- |
-- |
Set Forms (2) |
|
|
-- |
-- |
Pour Foundation Walls (1) |
|
|
-- |
-- |
Plumb Slab (2) |
|
|
-- |
-- |
Inspection (Plumbing Under Slab) (1) |
|
|
-- |
-- |
Prepare Slab (1) |
|
|
-- |
-- |
Inspection (Slab) (1) |
|
|
-- |
-- |
Pour Slab (1) * |
|
|
-- |
-- |
Framing I (9) |
Framing to begin this week 10/16 |
|
-- |
-- |
Order Steps (0) |
|
|
-- |
-- |
Order Tubs / Showers (0) |
|
|
-- |
-- |
Framing II (8) |
|
|
-- |
-- |
Framing III (8) * |
|
|
-- |
-- |
Install Stairs (0) |
|
|
-- |
-- |
Windows & Doors (0) |
|
|
-- |
-- |
House Number and Status in Window (0) |
|
|
-- |
-- |
Roofing (0) |
|
|
-- |
-- |
Order Cabinets (0) |
|
|
-- |
-- |
Deck (0) |
|
|
-- |
-- |
Gutters (0) |
|
|
-- |
-- |
Driveway (0) |
|
|
-- |
-- |
Privacy Divider / Fence (0) |
|
|
-- |
-- |
Sod / Seed / Landscaping (0) |
Need sod in front |
|
-- |
-- |
HVAC Rough In (4) |
|
|
-- |
-- |
Inspection (Rough In HVAC) (1) |
|
|
-- |
-- |
Plumbing Rough In (4) |
Starting Mon, Jan 22 |
|
-- |
-- |
Electric Rough In (4) |
12/21 in process |
|
-- |
-- |
Exterior Vinyl (0) * |
2/22- siding nearly complete |
|
-- |
-- |
Insulation (2) |
Thu, Jan 25 |
|
-- |
-- |
Inspection (Insulation) (1) |
1/30 |
|
-- |
-- |
Inspection (Electric Service) (0) |
|
|
-- |
-- |
Inspection (Main Sewer Line) (0) |
|
|
-- |
-- |
Order Interior Doors & Trim (0) |
Kate will check with Mitch |
|
-- |
-- |
Drywall (Hang) (4) * |
Starting Mon, Feb 12 |
|
-- |
-- |
Drywall (Tape, Block, Skim, Sand) (6) * |
2/22 taped |
|
-- |
-- |
Paint 1 (1) |
Hopefully Monday 2/26 |
|
-- |
-- |
Garage Door (0) |
|
|
-- |
-- |
House Numbers (0) |
|
|
-- |
-- |
Cabinet Installation (2) * |
3/5 nearly complete |
|
-- |
-- |
Granite Installation (1) * |
|
|
-- |
-- |
Interior Trim - Install (3) |
Starting Monday 3/12 - Carlin Platt |
|
-- |
-- |
Luxury Vinyl Plank (3) * |
|
|
-- |
-- |
Luxury Vinyl Tile (0) |
Nearly complete |
|
-- |
-- |
Paint 2 (3) |
In process now |
|
-- |
-- |
Cover Floors (1) |
|
|
-- |
-- |
Deliver Plumbing / Lighting Fixtures (0) |
|
|
-- |
-- |
Shoe Moulding (0) |
|
|
-- |
-- |
Shelving, Door Knobs, Fire Extinguisher (0) |
Greg - Friday, April 13 |
|
-- |
-- |
Install Coded Lockbox (add extra keys) (0) |
|
|
-- |
-- |
Pay Water / Sewer Taps (0) |
Mindy will tell Nicolette |
|
-- |
-- |
Set Water Meter (0) |
|
|
-- |
-- |
Electric Trim Out (3) |
nearly complete- Waiting for mirrors to be set |
|
-- |
-- |
HVAC Trim Out (1) |
|
|
-- |
-- |
Plumbing Trim Out (2) |
Starting Mon, April 2 |
|
-- |
-- |
Install Appliances (0) * |
Mon, Apr 9 |
|
-- |
-- |
Paint 3 (2) * |
After Carpet |
|
-- |
-- |
Carpet (2) |
Mon 4/9 |
|
-- |
-- |
Appraiser Confirms Construction Completion (0) |
Marty Walters |
|
-- |
-- |
Inspection (Final Building) (2) * |
Afternoon of Monday, April 16 |
|
-- |
-- |
Pre Walk Through (0) |
|
|
-- |
-- |
Cleaning (1) |
Monday, April 16 |
|
-- |
-- |
Certificate of Occupancy (1) * |
|
|
-- |
-- |
C.O. to Lender (0) |
|
|
-- |
-- |
Buyer Walk Through (1) |
Tuesday, April 17, 9:15 AM |
|
-- |
-- |
Payment for Upgrades (0) |
$2,187 |
|
-- |
-- |
Closing (1) |
|
|