| Tue | Nov 4 | Ratified Contract? (0) | ||
| Tue | Nov 4 | $2500 Deposit Received (0) | ||
| Tue | Nov 4 | Association Packet Requested (0) | ||
| Tue | Nov 4 | Association Packet Received (0) | ||
| Tue | Nov 4 | Selections Meeting (0) | ||
| Tue | Nov 4 | Selections Sheet Signed (0) | ||
| Tue | Nov 4 | Amendment for Upgrades (B,S,L,T,BCP) (0) | ||
| Tue | Nov 4 | Deposit For Upgrades Received (0) | ||
| Tue | Nov 4 | Inspection (Concrete Wall) (1) | ||
| Wed | Nov 5 | Inspection (Conduit Under Slab) (1) | ||
| Thu | Nov 6 | Inspection (Drain Tile) (0) | ||
| Thu | Nov 6 | Settlement Agent Confirmed (0) | ||
| Thu | Nov 6 | Verify Window & Roof Structure (0) | ||
| Thu | Nov 6 | Patio (0) | ||
| Thu | Nov 6 | Rough In Microwave Vent (0) | ||
| Thu | Nov 6 | Inspection (Rough In Plumbing) (1) | ||
| Fri | Nov 7 | Inspection (Rough In Electric) (1) | ||
| Mon | Nov 10 | Inspection (Framing) (1) * | ||
| Tue | Nov 11 | Inspection (Deck Piers) (0) | ||
| Tue | Nov 11 | Exterior Stone (0) | ||
| Tue | Nov 11 | Set Electric Meter (0) * | ||
| Tue | Nov 11 | Inspection (Main Water Line) (0) | ||
| Tue | Nov 11 | Loan Approval (0) | ||
| Tue | Nov 11 | Deed Preparation (0) | ||
| Tue | Nov 11 | Mailbox (0) | ||
| Tue | Nov 11 | Interior Trim - Paint (1) | ||
| Wed | Nov 12 | Ceiling Fans (0) | ||
| Wed | Nov 12 | Blower Door Test (1) | ||
| Thu | Nov 13 | Inspection (Final HVAC) (1) | ||
| Fri | Nov 14 | Inspection (Final Plumbing) (1) | ||
| Mon | Nov 17 | Inspection (Final Electric) (1) | ||
| Tue | Nov 18 | Stain Hardwood Stairs (1) * | ||
| -- | -- | Kate - Buyer Needs To Make Selections | ||
| -- | -- | Basement window needs installed 1/23 | ||
| -- | -- | |||
| -- | -- | LR & MB ceiling fans | ||
| -- | -- | CODED LOCKBOX 0909 | ||
| -- | -- | Refrigerator - May 5 | ||
| -- | -- | Exterior light fixture | ||
| -- | -- | 1/2 bath mirror | Ron | |
| -- | -- | Switch plate cover needed basement hallway & outdoor receptacle | Tom | |
| -- | -- | Blemish in MB cabinet door | Jill | |
| -- | -- | Home Inspection - May 11th at 9AM | Mike Donitzen | |
| -- | -- | Outdoor outlet | ||
| -- | -- | Cabinet trim | Trim guy | |
| -- | -- | Holes in patio door | Plugs needed | |
| -- | -- | Radon Test May 7 - 11 | Do not leave doors open | |
| -- | -- | Dampness in corner of basement. Rock solve the issue? | ||
| -- | -- | Missing HVAC cover LR | ||
| -- | -- | Finish shelving in MBcloset | Ron | |
| -- | -- | Quarter round | ||
| -- | -- | Shower Door | 5/7 or 5/10 | |
| -- | -- | Cut off house wrap at back of townhouse at bottom of siding | ||
| -- | -- | Protruding nail in kitchen flooring | Eric | |
| -- | -- | Caulk at shower/floor | ||
| -- | -- | Digital deadbolt | Ron | |
| -- | -- | Seam in shingles between townhouses | Tom will tell Joel | |
| -- | -- | loose transition at top of stairs | Removed 5/19 | |
| -- | -- | Loose shower door | Ron | |
| -- | -- | Touch up ceiling paint on main level | ||
| -- | -- | Add siding at back stoop | ||
| -- | -- | Paint wall in master bedroom closet | ||
| -- | -- | CODED LOCKBOX 0620 | ||
| -- | -- | Building Permit (30) * | ||
| CREDIT- for missing window in upstairs bedroom | ||||
| $2550 increase in contract price per amendment | ||||
| -- | -- | Order Roof & Floor Trusses (1) | ||
| -- | -- | Order Windows & Doors (0) | ||
| -- | -- | Stake Out Home (1) | ||
| -- | -- | Excavate (2) | ||
| -- | -- | Inspection (Footers) (1) | ||
| -- | -- | Pour Footers (1) * | ||
| -- | -- | Set Forms (2) | ||
| -- | -- | Pour Foundation Walls (1) | ||
| -- | -- | Plumb Slab (2) | in process 12/9 | |
| -- | -- | Inspection (Plumbing Under Slab) (1) | ||
| -- | -- | Prepare Slab (1) | ||
| -- | -- | Inspection (Slab) (1) | ||
| -- | -- | Pour Slab (1) * | ||
| -- | -- | Framing I (9) | ||
| -- | -- | Order Steps (0) | ||
| -- | -- | Order Tubs / Showers (0) | ||
| -- | -- | Framing II (8) | ||
| -- | -- | Framing III (8) * | ||
| -- | -- | Install Stairs (0) * | ||
| -- | -- | Windows & Doors (0) * | in process 1/16 | |
| -- | -- | House Number and Status in Window (0) | ||
| -- | -- | Roofing (0) * | in process 2/6 | |
| -- | -- | Order Cabinets (0) | ||
| Painted Kitchen Cabinetry | ||||
| -- | -- | Order Appliances (0) | SS with French Fridge | |
| French Model Fridge | ||||
| -- | -- | Deck (0) | ||
| -- | -- | Gutters (0) | ||
| -- | -- | Driveway (0) * | ||
| -- | -- | Privacy Divider / Fence (0) * | In process 4/21 | |
| -- | -- | Sod / Seed / Landscaping (0) | ||
| -- | -- | HVAC Rough In (4) | in process 2/10 | |
| -- | -- | Plumbing Rough In (4) | In process 2/10 | |
| -- | -- | Electric Rough In (4) | ||
| -- | -- | Inspection (Rough In HVAC) (1) | Mon, 2/15 | |
| -- | -- | Exterior Vinyl (0) * | ||
| -- | -- | Insulation (2) * | ||
| -- | -- | Inspection (Insulation) (1) | Mon, Feb 22 | |
| -- | -- | Inspection (Electric Service) (0) | ||
| -- | -- | Inspection (Main Sewer Line) (0) | ||
| -- | -- | Order Interior Doors & Trim (0) | BN Hinges | |
| -- | -- | Drywall (Hang) (4) * | ||
| -- | -- | Drywall (Tape, Block, Skim, Sand) (6) * | finished 3/9 | |
| -- | -- | Paint 1 (1) | ||
| -- | -- | Garage Door (0) | ||
| -- | -- | House Numbers (0) | ||
| -- | -- | Cabinet Installation (2) * | Week of Mar 8 | |
| -- | -- | Granite Installation (1) * | by Tuesday, 3/30 | |
| -- | -- | Interior Trim - Install (3) * | Completed. Needs painting. 3/28 | |
| -- | -- | Order Plumbing / Lighting Fixtures (0) | ||
| -- | -- | Luxury Vinyl Plank (3) * | In process 4/14 | |
| -- | -- | Luxury Vinyl Tile (0) | ||
| -- | -- | Paint 2 (3) | In process 4/14 | |
| -- | -- | Cover Floors (1) | ||
| -- | -- | Deliver Plumbing / Lighting Fixtures (0) | BN lighting is in and installed | |
| -- | -- | Shoe Moulding (0) | Lots on site here in garage 4/25 | |
| -- | -- | Shelving, Door Knobs, Fire Extinguisher (0) * | In process 4/28. Needs MB closet completed. | |
| Semi Frameless Shower Door in Master Bathroom | ||||
| -- | -- | Install Coded Lockbox (add extra keys) (0) | ||
| -- | -- | Pay Water / Sewer Taps (0) | ||
| -- | -- | Set Water Meter (0) * | ||
| -- | -- | Electric Trim Out (3) * | Brushed Nickel Lighting | |
| -- | -- | HVAC Trim Out (1) * | ||
| -- | -- | Plumbing Trim Out (2) * | Standard Brushed Nickel | |
| -- | -- | Install Appliances (0) * | DW - installed 5/14, Range installed 5/14; | |
| -- | -- | Paint 3 (2) * | ||
| -- | -- | Carpet (2) | Supplies on site 4/25 | |
| -- | -- | Appraiser Confirms Construction Completion (0) | ||
| -- | -- | Inspection (Final Building) (2) * | 5/6 | |
| -- | -- | Pre Walk Through (0) | ||
| -- | -- | Cleaning (1) | ||
| -- | -- | Certificate of Occupancy (1) * | ||
| -- | -- | C.O. to Lender (0) | ||
| -- | -- | Schedule Closing (0) | ||
| -- | -- | Buyer Walk Through (1) * | Wednesday 19th at 12:00 PM | |
| -- | -- | Payment for Upgrades (0) | ||
| -- | -- | Keys to Settlement Agent (0) | ||
| -- | -- | Review Settlement Statement (0) | ||
| -- | -- | Jerry Signs Closing Documents (0) | ||
| -- | -- | Request Trash Tote From POA Manager (0) | ||
| -- | -- | Closing (1) | 5/12 at 9:00 AM | |
| -- | -- | Remove Coded Lockbox (0) | ||