CONGERS - 7  ::  2814 Belgian Drive
[ BUILD: 20200001985 ]      
CRITICAL PATH   |   INSPECTIONS   |   FLOOR PLANS   |   SELECTIONS   |   SPECS   |   CHANGES   |   NHS
view photo archive
 
TO DO
Stairway-Adding Concrete 2/23
UPGRADES
---
    Ratified Contract? (0)      
    $2500 Deposit Received (0)      
    Association Packet Requested (0)      
    Association Packet Received (0)      
    Selections Meeting (0)      
    Selections Sheet Signed (0)      
    Amendment for Upgrades (B,S,L,T,BCP) (0)      
    Deposit For Upgrades Received (0)      
CRITICAL PATH
Tue    Feb 3      Inspection (Concrete Wall) (1)      
Wed    Feb 4      Inspection (Conduit Under Slab) (1)      
    Inspection (Drain Tile) (0)      
    Settlement Agent Confirmed (0)      
    Verify Window & Roof Structure (0)      
    Patio (0)      
    Rough In Microwave Vent (0)      
Thu    Feb 5      Inspection (Rough In Plumbing) (1)      
Fri    Feb 6      Inspection (Rough In Electric) (1)      
Mon    Feb 9      Inspection (Framing) (1) *       
    Inspection (Deck Piers) (0)      
    Exterior Stone (0)      
    Set Electric Meter (0) *       
    Inspection (Main Water Line) (0)      
    Loan Approval (0)      
    Deed Preparation (0)      
    Mailbox (0)      
Tue    Feb 10      Interior Trim - Paint (1)      
    Ceiling Fans (0)      
Wed    Feb 11      Blower Door Test (1)      
    Inspection (Final HVAC) (0)      
    Inspection (Final Plumbing) (0)      
    Inspection (Final Electric) (0)      
Thu    Feb 12      Stain Hardwood Stairs (1) *       
TO DO - COMPLETED OR DELETED
Design appointment scheduled for Monday, January 4 at 1 PM
CONSIDERING BONUS ROOM AND BATH
Missing 1 window (side basement) 1/20
Kitchen plumbing? 2/14
Insulation to protect bathtubs? 2/14
Can the wall in the back of the closet under the stairs be removed?
No smaller door at back of the closet under the stairs
Appraiser, Monday, March 8 at 12PM
Wesley Woods, Appraiser, Monday, March 8 at 12PM
Kitchen cabinet hardware shoudl be brushed nickel
Kitchen cabinet hardware should be brushed nickel Kimberly has ordered and will install
Bathroom cabinet hardware should be black
Broken cabinet 3/14
Handrail on other side 3/21
Exterior garage doors 7-9? Hopefully by 3/26-interior garage doors needed 3/24
Trim needs paint 3/21 Taped/not painted 3/24
Broken exterior window trim 3/21 J channel - Tom
Installing tile in foyer - no is the answer, right?
No digital deadbolt installed 4/11 Ron is aware
CODED LOCKBOX 0707
Ceiling drywall repair (kitchen) And MB
Electrician-dining room light Missing a piece
1/2 bath mirror On site 4/25
Attic cover
Bottom piece of bathtub plumbing
Replace board from initial house number install? Tom will tell Davenport to replace the board
Railings
Electric outlet outside and switch plate cover needed on stairs And by front door
Cabinet trim needed 4/28
Transition strips?
Fill holes in patio door Plugs - Tom
Caulk in front of bathtubs Or shoe moulding
Paint front door
Stain steps
Outdoor outlet
Fence easement Jerry
Final paint needed on steps
Splash block Tom
Crack in hall tub Tom
Home Inspection - May 13 @ 9AM
Corner of concrete patio is broken. Cut off corner - Tom
Extend downspout away from house Tom
Garage-in subpanel the neutral bar and ground bar should be installed seperately with neutral bar floating and not bonded to the panel or ground bar. Bonding screw should be removed. Tom will talk to the electrician
Ceiling fans in LR and MB need remotes? How do you adjust fan speed? Tom will talk to the electrician
Recommend verifying function/condition of dishwasher/range
Verify floor condition is acceptable after removing floor coverings
Verify floor condition is acceptable after removing floor coverings
One ceiling fan that does not work electrician
Large unapproved screened porch Kate will send photos to Bernard
UPGRADES - COMPLETED
    Expanded Driveway  
    garage keypad  
    French Model Fridge  
    Digital Deadbolt  
    CREDIT for missing bedroom window  
CRITICAL PATH - COMPLETED
-- -- Building Permit (30) *   08.19.2021    
-- -- Order Roof & Floor Trusses (1)      
-- -- Order Windows & Doors (0)      
-- -- Stake Out Home (1)      
-- -- Excavate (2)      
-- -- Inspection (Footers) (1)      
-- -- Pour Footers (1) *       
-- -- Set Forms (2)       in process 12/2
-- -- Pour Foundation Walls (1)      
-- -- Plumb Slab (2)       in process 12/9
-- -- Inspection (Plumbing Under Slab) (1)      
-- -- Prepare Slab (1)      
-- -- Inspection (Slab) (1)      
-- -- Pour Slab (1) *       
-- -- Framing I (9)      
-- -- Order Steps (0)      
-- -- Order Tubs / Showers (0)      
-- -- Framing II (8)      
-- -- Framing III (8) *       
-- -- Install Stairs (0) *       
-- -- Windows & Doors (0) *        in process 1/16
-- -- House Number and Status in Window (0)      
-- -- Roofing (0) *   08.19.2021     in process 2/6
-- -- Order Cabinets (0)      
-- -- Order Appliances (0)       SS with French fridge
-- -- Deck (0)      
-- -- Gutters (0)       Hopefully by 3/26
-- -- Driveway (0) *        Patio done/driveway framed 4/11
-- -- Privacy Divider / Fence (0) *        Going in 4/21
-- -- Sod / Seed / Landscaping (0)      
-- -- HVAC Rough In (4)       in process 1/27
-- -- Plumbing Rough In (4)       in process 2/10
-- -- Electric Rough In (4)      
-- -- Inspection (Rough In HVAC) (1)      
-- -- Exterior Vinyl (0) *       
-- -- Insulation (2) *       
-- -- Inspection (Insulation) (1)  08.19.2021    
-- -- Inspection (Electric Service) (0)      
-- -- Inspection (Main Sewer Line) (0)      
-- -- Order Interior Doors & Trim (0)       BLACK Hinges; front door digital deadbolt
-- -- Drywall (Hang) (4) *        In process 2/17
-- -- Drywall (Tape, Block, Skim, Sand) (6) *        In process 2/24
-- -- Paint 1 (1)       Mon, Mar not yet 3/3. Windows/tubs are taped
-- -- Garage Door (0)      
-- -- House Numbers (0)       H/n done
-- -- Cabinet Installation (2) *        Week of Mar 8
-- -- Granite Installation (1) *        3/29
-- -- Interior Trim - Install (3) *        In process 3/17
-- -- Order Plumbing / Lighting Fixtures (0)      
-- -- Luxury Vinyl Plank (3) *        In process 4/7
-- -- Luxury Vinyl Tile (0)       In process 4/7
-- -- Paint 2 (3)       by Tuesday, 3/30
-- -- Cover Floors (0)      
-- -- Deliver Plumbing / Lighting Fixtures (0)       Brushed Nickel Lighting, Black Plumbing
-- -- Shoe Moulding (0)       In process 4/28
-- -- Shelving, Door Knobs, Fire Extinguisher (1) *        BLACK Levers & Bath Accessories. Almost done 4/25
-- -- Install Coded Lockbox (add extra keys) (0)      
-- -- Pay Water / Sewer Taps (0)      
-- -- Set Water Meter (1) *       
-- -- Electric Trim Out (3) *        Almost complete 4/11
-- -- HVAC Trim Out (1) *       
-- -- Plumbing Trim Out (2) *        In process 4/17. Need bath/shower faucets
-- -- Install Appliances (0) *        5/5 ( fridge) 5/6 DW, Range, OTR. Need range.DW 5/12
-- -- Paint 3 (2) *       
-- -- Carpet (2)       April 19 & 20
-- -- Appraiser Confirms Construction Completion (0)      
-- -- Inspection (Final Building) (4) *       
-- -- Pre Walk Through (0)      
-- -- Cleaning (1)       Started 5/8
-- -- Certificate of Occupancy (1) *       
-- -- C.O. to Lender (0)      
-- -- Schedule Closing (0)      
-- -- Buyer Walk Through (1) *       
-- -- Payment for Upgrades (0)       $2,000
-- -- Keys to Settlement Agent (0)      
-- -- Review Settlement Statement (0)      
-- -- Jerry Signs Closing Documents (0)       Tuesday, May 18th at 11:30 AM or 12:00 PM
-- -- Request Trash Tote From POA Manager (0)      
-- -- Closing (1)       West View Title
-- -- Remove Coded Lockbox (0)