CONGERS - 14  ::  2854 Belgian Drive
[ BUILD: 20200001995 ]      
CRITICAL PATH   |   INSPECTIONS   |   FLOOR PLANS   |   SELECTIONS   |   SPECS   |   CHANGES   |   NHS
view photo archive
 
TO DO
---
UPGRADES
---
CRITICAL PATH
---
TO DO - COMPLETED OR DELETED
Design Appt. January 6 at 4:00 PM
Closet needed 3/14
Cabinet crown moulding needed Unknown arrival date
Rate lock expires June 18
LVT in bonus room. Correct?
Hallway bath counters not on (everywhere else is) Just need right side splash 6/2
Shelving ready to install and shower door ready to be installed. Painter will let Ron know when they are complete so all can be installed. Partially complete 6/19
Corner of patio broken 6/6 caulking
Fence location
Where are keys?
Colors for baths correct? 6/19 I think need BN (not black) bathroom fixtures-switching out 6/23
Green siding at peak ok? 6/19
attic cover
hallway light fixture-covers?
CODED LOCKBOX 1414
Needs dishwasher 6/23
Weather stripping needed at front door 6/26
Staining steps 6/26
Bedroom light/exterior light need installed 6/26
Brush nickel hinges completed upstairs second floor first floor black knobs and hinges
Cable cover
Bottom of hall shower Tom will find one in the trailer - overflow drain cover
weather stripping needed at front door
weather stripping needed at garage dooe
re-clean after painters are compketly done
re-clean after the painters are done jill will clean once painters are finnishd.
top board on the first set of steps has a screw head and a screw hole that needs filled in. Maher is aware of this. There’s a few holes 7/11
need a biscuit in the basement bonus room closet tom will get
hinges on the garage door going into home are nickel and the need to be black (already ordered) Tom or Jill
bottom of garage door on both sides are bent up.
theres a gap behind the master bathroom toilet that needs caulked Maher is aware of this.
needs caulk around the inside of the shower walls maher will take care of this
paint touch up/repainting is needed throughout home.
paint frame around the front door!
Adjust bedroom closet doors where they rub trim
Caulk shoe mold in front of utile shower
Replace cabinet door above refrigerator On order- hope to install next week
Inside garage lends patched/painted Majer
Bottom of the aluminum wrap on both sides of the garage door is bent at the bottom Davenport
Patio cracks Pavers? Tom & Kate will discuss.
Tom is getting a quote for pavers
Kitchen ceiling repair from bathroom leak
Bathroom shower door repair
UPGRADES - COMPLETED
    Finished Bonus Room and Bathroom ($9500 included in amendment)  
    8 lb carpet pad ($250 included in amendment)  
    utile shower with pan ($2800 included in amendment)  
    Semi Frameless shower door ($1400 included in amendment)  
    Cabinet Crown Moulding ($included in amendment)  
    closet in the bonus room ($400 included in amendment)  
CRITICAL PATH - COMPLETED
-- -- Ratified Contract? (0)  07.27.2025    
-- -- $2500 Deposit Received (0)  07.27.2025    
-- -- Association Packet Requested (0)  07.27.2025    
-- -- Association Packet Received (0)  07.27.2025    
-- -- Selections Meeting (0)  07.27.2025    
-- -- Selections Sheet Signed (0)  07.27.2025    
-- -- Amendment for Upgrades (B,S,L,T,BCP) (0)  07.27.2025    
-- -- Deposit For Upgrades Received (0)  07.27.2025    
-- -- Building Permit (30) *       
-- -- Order Roof & Floor Trusses (1)      
-- -- Order Windows & Doors (0)       BN hinges
-- -- Stake Out Home (1)      
-- -- Excavate (2)      
-- -- Inspection (Footers) (1)      
-- -- Inspection (Concrete Wall) (1)  07.27.2025    
-- -- Pour Footers (1) *       
-- -- Set Forms (2)      
-- -- Pour Foundation Walls (1)      
-- -- Plumb Slab (2)       in process 1/16
-- -- Inspection (Plumbing Under Slab) (1)      
-- -- Inspection (Conduit Under Slab) (1)  07.27.2025    
-- -- Prepare Slab (1)      
-- -- Inspection (Slab) (1)      
-- -- Inspection (Drain Tile) (0)  07.27.2025    
-- -- Pour Slab (1) *       
-- -- Settlement Agent Confirmed (0)  07.27.2025    
-- -- Framing I (9)      
-- -- Order Steps (0)      
-- -- Order Tubs / Showers (0)      
-- -- Framing II (8)      
-- -- Framing III (8) *       
-- -- Verify Window & Roof Structure (0)  07.27.2025    
-- -- Install Stairs (0) *       
-- -- Windows & Doors (0) *        BN hinges
-- -- House Number and Status in Window (0)      
-- -- Roofing (0) *       
-- -- Order Cabinets (0)      
-- -- Order Appliances (0)       SS Standard
-- -- Deck (0)      
-- -- Gutters (0)      
-- -- Driveway (0) *        D/w framed 5/22
-- -- Patio (0)  07.27.2025    
-- -- Privacy Divider / Fence (0) *       
-- -- Sod / Seed / Landscaping (0)      
-- -- HVAC Rough In (4)      
-- -- Rough In Microwave Vent (0)  07.27.2025    
-- -- Plumbing Rough In (4)       In process 3/24
-- -- Electric Rough In (4)      
-- -- Inspection (Rough In HVAC) (1)       3/30
-- -- Inspection (Rough In Plumbing) (1)  07.27.2025    
-- -- Inspection (Rough In Electric) (1)  07.27.2025    
-- -- Inspection (Framing) (1) *   07.27.2025    
-- -- Inspection (Deck Piers) (0)  07.27.2025    
-- -- Exterior Vinyl (0) *        Starting install Wed, Jun 16
-- -- Exterior Stone (0)  07.27.2025    
-- -- Insulation (2) *       
-- -- Inspection (Insulation) (1)      
-- -- Inspection (Electric Service) (0)      
-- -- Set Electric Meter (0) *   07.27.2025    
-- -- Inspection (Main Sewer Line) (0)      
-- -- Inspection (Main Water Line) (0)  07.27.2025    
-- -- Order Interior Doors & Trim (0)       Black hinges
-- -- Drywall (Hang) (4) *        Stocked 4/7
-- -- Loan Approval (0)  07.27.2025    
-- -- Deed Preparation (0)  07.27.2025    
-- -- Drywall (Tape, Block, Skim, Sand) (6) *        Looks like just needs final sanding 4/17
-- -- Paint 1 (1)       All complete except basement bonus/bath 5/1
-- -- Garage Door (0)      
-- -- House Numbers (0)      
-- -- Mailbox (0)  07.27.2025    
-- -- Cabinet Installation (2) *       
-- -- Granite Installation (1) *        6/23-kk
-- -- Interior Trim - Install (3) *        In. Process 5/15
-- -- Order Plumbing / Lighting Fixtures (0)      
-- -- Interior Trim - Paint (1)  07.27.2025    
-- -- Luxury Vinyl Plank (3) *        In process 5/31
-- -- Luxury Vinyl Tile (0)      
-- -- Paint 2 (3)       working on it now- 6/14/21- KK
-- -- Cover Floors (0)      
-- -- Deliver Plumbing / Lighting Fixtures (0)       BN Plumbing and BN Lighting
-- -- Shoe Moulding (0)      
-- -- Shelving, Door Knobs, Fire Extinguisher (1) *        In process 6/26
-- -- Install Coded Lockbox (add extra keys) (0)      
-- -- Pay Water / Sewer Taps (0)      
-- -- Set Water Meter (1) *       
-- -- Electric Trim Out (3) *        Brushed Nickel Lighting-in process. Still needs quite a bit finished 6/23
-- -- Ceiling Fans (0)  07.27.2025    
-- -- HVAC Trim Out (1) *        Furnace set 6/6-needs trim out 6/19
-- -- Blower Door Test (1)  07.27.2025    
-- -- Plumbing Trim Out (2) *        Standard BN Plumbing-working on today 6/23
-- -- Install Appliances (0) *        6/25
-- -- Paint 3 (2) *       
-- -- Carpet (2)       In process 6/16
-- -- Appraiser Confirms Construction Completion (0)      
-- -- Inspection (Final HVAC) (0)  07.27.2025    
-- -- Inspection (Final Plumbing) (0)  07.27.2025    
-- -- Inspection (Final Electric) (0)  07.27.2025    
-- -- Inspection (Final Building) (4) *        Mon, Jun 28
-- -- Pre Walk Through (0)      
-- -- Stain Hardwood Stairs (1) *   07.27.2025    
-- -- Cleaning (1)       In process 6/30
-- -- Certificate of Occupancy (1) *       
-- -- C.O. to Lender (0)      
-- -- Schedule Closing (0)      
-- -- Buyer Walk Through (1) *       
-- -- Payment for Upgrades (0)      
-- -- Keys to Settlement Agent (0)      
-- -- Review Settlement Statement (0)      
-- -- Jerry Signs Closing Documents (0)      
-- -- Request Trash Tote From POA Manager (0)      
-- -- Closing (1)       Likely 7/13/2021;
-- -- Remove Coded Lockbox (0)