| TO DO |
|
|
bottom of garage door on both sides are bent up. |
|
|
|
| UPGRADES |
| --- |
|
| CRITICAL PATH |
| --- |
|
| TO DO - COMPLETED OR DELETED |
|
|
Design Appt. January 6 at 4:00 PM |
|
|
|
|
Closet needed 3/14 |
|
|
|
|
Cabinet crown moulding needed |
Unknown arrival date |
|
|
|
Rate lock expires June 18 |
|
|
|
|
LVT in bonus room. Correct? |
|
|
|
|
Hallway bath counters not on (everywhere else is) |
Just need right side splash 6/2 |
|
|
|
Shelving ready to install and shower door ready to be installed. Painter will let Ron know when they are complete so all can be installed. |
Partially complete 6/19 |
|
|
|
Corner of patio broken 6/6 |
caulking |
|
|
|
Fence location |
|
|
|
|
Where are keys? |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
Colors for baths correct? 6/19 |
I think need BN (not black) bathroom fixtures-switching out 6/23 |
|
|
|
Green siding at peak ok? 6/19 |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
attic cover |
|
|
|
|
hallway light fixture-covers? |
|
|
|
|
CODED LOCKBOX 1414 |
|
|
|
|
Needs dishwasher 6/23 |
|
|
|
|
Weather stripping needed at front door 6/26 |
|
|
|
|
Staining steps 6/26 |
|
|
|
|
Bedroom light/exterior light need installed 6/26 |
|
|
|
|
Brush nickel hinges completed upstairs second floor first floor black knobs and hinges |
|
|
|
|
Cable cover |
|
|
|
|
Bottom of hall shower |
Tom will find one in the trailer - overflow drain cover |
|
|
|
weather stripping needed at front door |
|
|
|
|
weather stripping needed at garage dooe |
|
|
|
|
re-clean after painters are compketly done |
|
|
|
|
re-clean after the painters are done |
jill will clean once painters are finnishd. |
|
|
|
top board on the first set of steps has a screw head and a screw hole that needs filled in. |
Maher is aware of this. There’s a few holes 7/11 |
|
|
|
need a biscuit in the basement bonus room closet |
tom will get |
|
|
|
hinges on the garage door going into home are nickel and the need to be black (already ordered) |
Tom or Jill |
|
|
|
theres a gap behind the master bathroom toilet that needs caulked |
Maher is aware of this. |
|
|
|
needs caulk around the inside of the shower walls |
maher will take care of this |
|
|
|
paint touch up/repainting is needed throughout home. |
|
|
|
|
paint frame around the front door! |
|
|
|
|
Adjust bedroom closet doors where they rub |
trim |
|
|
|
Caulk shoe mold in front of utile shower |
|
|
|
|
Replace cabinet door above refrigerator |
On order- hope to install next week |
|
|
|
Inside garage lends patched/painted |
Majer |
|
|
|
Bottom of the aluminum wrap on both sides of the garage door is bent at the bottom |
Davenport |
|
|
|
Patio cracks |
Pavers? Tom & Kate will discuss. |
|
|
|
Tom is getting a quote for pavers |
|
|
|
|
Kitchen ceiling repair from bathroom leak |
|
|
|
|
Bathroom shower door repair |
|
|
|
| UPGRADES - COMPLETED |
| |
|
Finished Bonus Room and Bathroom ($9500 included in amendment)
|
|
| |
|
8 lb carpet pad ($250 included in amendment)
|
|
| |
|
utile shower with pan ($2800 included in amendment)
|
|
| |
|
Semi Frameless shower door ($1400 included in amendment)
|
|
| |
|
Cabinet Crown Moulding ($included in amendment)
|
|
| |
|
closet in the bonus room ($400 included in amendment)
|
|
|
| CRITICAL PATH - COMPLETED |
| -- |
-- |
Ratified Contract? (0) 07.27.2025 |
|
|
| -- |
-- |
$2500 Deposit Received (0) 07.27.2025 |
|
|
| -- |
-- |
Association Packet Requested (0) 07.27.2025 |
|
|
| -- |
-- |
Association Packet Received (0) 02.09.2026 |
|
|
| -- |
-- |
Selections Meeting (0) 07.27.2025 |
|
|
| -- |
-- |
Selections Sheet Signed (0) 07.27.2025 |
|
|
| -- |
-- |
Amendment for Upgrades (B,S,L,T,BCP) (0) 07.27.2025 |
|
|
| -- |
-- |
Deposit For Upgrades Received (0) 07.27.2025 |
|
|
| -- |
-- |
Building Permit (30) * |
|
|
| -- |
-- |
Order Roof & Floor Trusses (1) |
|
|
| -- |
-- |
Order Windows & Doors (0) |
BN hinges |
|
| -- |
-- |
Stake Out Home (1) |
|
|
| -- |
-- |
Excavate (2) |
|
|
| -- |
-- |
Inspection (Footers) (1) |
|
|
| -- |
-- |
Inspection (Concrete Wall) (1) 07.27.2025 |
|
|
| -- |
-- |
Pour Footers (1) * |
|
|
| -- |
-- |
Set Forms (2) |
|
|
| -- |
-- |
Pour Foundation Walls (1) |
|
|
| -- |
-- |
Plumb Slab (2) |
in process 1/16 |
|
| -- |
-- |
Inspection (Plumbing Under Slab) (1) |
|
|
| -- |
-- |
Inspection (Conduit Under Slab) (1) 07.27.2025 |
|
|
| -- |
-- |
Prepare Slab (1) |
|
|
| -- |
-- |
Inspection (Slab) (1) |
|
|
| -- |
-- |
Inspection (Drain Tile) (0) 07.27.2025 |
|
|
| -- |
-- |
Pour Slab (1) * |
|
|
| -- |
-- |
Settlement Agent Confirmed (0) 07.27.2025 |
|
|
| -- |
-- |
Framing I (9) |
|
|
| -- |
-- |
Order Steps (0) |
|
|
| -- |
-- |
Order Tubs / Showers (0) |
|
|
| -- |
-- |
Framing II (8) |
|
|
| -- |
-- |
Framing III (8) * |
|
|
| -- |
-- |
Verify Window & Roof Structure (0) 07.27.2025 |
|
|
| -- |
-- |
Install Stairs (0) * |
|
|
| -- |
-- |
Windows & Doors (0) * |
BN hinges |
|
| -- |
-- |
House Number and Status in Window (0) |
|
|
| -- |
-- |
Roofing (0) * |
|
|
| -- |
-- |
Order Cabinets (0) |
|
|
| -- |
-- |
Order Appliances (0) |
SS Standard |
|
| -- |
-- |
Deck (0) |
|
|
| -- |
-- |
Gutters (0) |
|
|
| -- |
-- |
Driveway (0) * |
D/w framed 5/22 |
|
| -- |
-- |
Patio (0) 07.27.2025 |
|
|
| -- |
-- |
Privacy Divider / Fence (0) * |
|
|
| -- |
-- |
Sod / Seed / Landscaping (0) |
|
|
| -- |
-- |
HVAC Rough In (4) |
|
|
| -- |
-- |
Rough In Microwave Vent (0) 07.27.2025 |
|
|
| -- |
-- |
Plumbing Rough In (4) |
In process 3/24 |
|
| -- |
-- |
Electric Rough In (4) |
|
|
| -- |
-- |
Inspection (Rough In HVAC) (1) |
3/30 |
|
| -- |
-- |
Inspection (Rough In Plumbing) (1) 07.27.2025 |
|
|
| -- |
-- |
Inspection (Rough In Electric) (1) 07.27.2025 |
|
|
| -- |
-- |
Inspection (Framing) (1) * 07.27.2025 |
|
|
| -- |
-- |
Inspection (Deck Piers) (0) 07.27.2025 |
|
|
| -- |
-- |
Exterior Vinyl (0) * |
Starting install Wed, Jun 16 |
|
| -- |
-- |
Exterior Stone (0) 07.27.2025 |
|
|
| -- |
-- |
Insulation (2) * |
|
|
| -- |
-- |
Inspection (Insulation) (1) |
|
|
| -- |
-- |
Inspection (Electric Service) (0) |
|
|
| -- |
-- |
Set Electric Meter (0) * 07.27.2025 |
|
|
| -- |
-- |
Inspection (Main Sewer Line) (0) |
|
|
| -- |
-- |
Inspection (Main Water Line) (0) 07.27.2025 |
|
|
| -- |
-- |
Order Interior Doors & Trim (0) |
Black hinges |
|
| -- |
-- |
Drywall (Hang) (4) * |
Stocked 4/7 |
|
| -- |
-- |
Loan Approval (0) 07.27.2025 |
|
|
| -- |
-- |
Deed Preparation (0) 07.27.2025 |
|
|
| -- |
-- |
Drywall (Tape, Block, Skim, Sand) (6) * |
Looks like just needs final sanding 4/17 |
|
| -- |
-- |
Paint 1 (1) |
All complete except basement bonus/bath 5/1 |
|
| -- |
-- |
Garage Door (0) |
|
|
| -- |
-- |
House Numbers (0) |
|
|
| -- |
-- |
Mailbox (0) 07.27.2025 |
|
|
| -- |
-- |
Cabinet Installation (2) * |
|
|
| -- |
-- |
Granite Installation (1) * |
6/23-kk |
|
| -- |
-- |
Interior Trim - Install (3) * |
In. Process 5/15 |
|
| -- |
-- |
Order Plumbing / Lighting Fixtures (0) |
|
|
| -- |
-- |
Interior Trim - Paint (1) 07.27.2025 |
|
|
| -- |
-- |
Luxury Vinyl Plank (3) * |
In process 5/31 |
|
| -- |
-- |
Luxury Vinyl Tile (0) |
|
|
| -- |
-- |
Paint 2 (3) |
working on it now- 6/14/21- KK |
|
| -- |
-- |
Cover Floors (0) |
|
|
| -- |
-- |
Deliver Plumbing / Lighting Fixtures (0) |
BN Plumbing and BN Lighting |
|
| -- |
-- |
Shoe Moulding (0) |
|
|
| -- |
-- |
Shelving, Door Knobs, Fire Extinguisher (1) * |
In process 6/26 |
|
| -- |
-- |
Install Coded Lockbox (add extra keys) (0) |
|
|
| -- |
-- |
Pay Water / Sewer Taps (0) |
|
|
| -- |
-- |
Set Water Meter (1) * |
|
|
| -- |
-- |
Electric Trim Out (3) * |
Brushed Nickel Lighting-in process. Still needs quite a bit finished 6/23 |
|
| -- |
-- |
Ceiling Fans (0) 07.27.2025 |
|
|
| -- |
-- |
HVAC Trim Out (1) * |
Furnace set 6/6-needs trim out 6/19 |
|
| -- |
-- |
Blower Door Test (1) 07.27.2025 |
|
|
| -- |
-- |
Plumbing Trim Out (2) * |
Standard BN Plumbing-working on today 6/23 |
|
| -- |
-- |
Install Appliances (0) * |
6/25 |
|
| -- |
-- |
Paint 3 (2) * |
|
|
| -- |
-- |
Carpet (2) |
In process 6/16 |
|
| -- |
-- |
Appraiser Confirms Construction Completion (0) |
|
|
| -- |
-- |
Inspection (Final HVAC) (0) 07.27.2025 |
|
|
| -- |
-- |
Inspection (Final Plumbing) (0) 07.27.2025 |
|
|
| -- |
-- |
Inspection (Final Electric) (0) 07.27.2025 |
|
|
| -- |
-- |
Inspection (Final Building) (4) * |
Mon, Jun 28 |
|
| -- |
-- |
Pre Walk Through (0) |
|
|
| -- |
-- |
Stain Hardwood Stairs (1) * 07.27.2025 |
|
|
| -- |
-- |
Cleaning (1) |
In process 6/30 |
|
| -- |
-- |
Certificate of Occupancy (1) * |
|
|
| -- |
-- |
C.O. to Lender (0) |
|
|
| -- |
-- |
Schedule Closing (0) |
|
|
| -- |
-- |
Buyer Walk Through (1) * |
|
|
| -- |
-- |
Payment for Upgrades (0) |
|
|
| -- |
-- |
Keys to Settlement Agent (0) |
|
|
| -- |
-- |
Review Settlement Statement (0) |
|
|
| -- |
-- |
Jerry Signs Closing Documents (0) |
|
|
| -- |
-- |
Request Trash Tote From POA Manager (0) |
|
|
| -- |
-- |
Closing (1) |
Likely 7/13/2021; |
|
| -- |
-- |
Remove Coded Lockbox (0) |
|
|