ADDR
CONGERS - 19  ::  2880 Belgian Drive
[ BUILD: 20200002171 ]      
CRITICAL PATH   |   INSPECTIONS   |   FLOOR PLANS   |   SELECTIONS   |   SPECS   |   CHANGES   |   NHS
view photo archive
 
TO DO
---
UPGRADES
---
    Ratified Contract? (0)      
    $2500 Deposit Received (0)      
    Association Packet Requested (0)      
    Association Packet Received (0)      
    Selections Meeting (0)      
    Selections Sheet Signed (0)      
    Amendment for Upgrades (B,S,L,T,BCP) (0)      
    Deposit For Upgrades Received (0)      
CRITICAL PATH
Tue    Feb 3      Inspection (Concrete Wall) (1)      
Wed    Feb 4      Inspection (Conduit Under Slab) (1)      
    Inspection (Drain Tile) (0)      
    Settlement Agent Confirmed (0)      
    Verify Window & Roof Structure (0)      
    Patio (0)      
    Rough In Microwave Vent (0)      
Thu    Feb 5      Inspection (Rough In Plumbing) (1)      
Fri    Feb 6      Inspection (Rough In Electric) (1)      
Mon    Feb 9      Inspection (Framing) (1) *       
    Inspection (Deck Piers) (0)      
    Exterior Stone (0)      
    Set Electric Meter (0) *       
    Inspection (Main Water Line) (0)      
    Loan Approval (0)      
    Deed Preparation (0)      
    Mailbox (0)      
    Order Plumbing / Lighting Fixtures (0)      
Tue    Feb 10      Interior Trim - Paint (1)      
    Ceiling Fans (0)      
Wed    Feb 11      Blower Door Test (1)      
    Inspection (Final HVAC) (0)      
    Inspection (Final Plumbing) (0)      
    Inspection (Final Electric) (0)      
Thu    Feb 12      Stain Hardwood Stairs (1) *       
TO DO - COMPLETED OR DELETED
Design Appointment Thursday January 28 at 11:00 AM
Door into basement has BN hinges
Basement vanity needed 6/23
Where’s hall bath door? Jill to follow up
Kitchen floor sloping down? Or cabinets? 7/11
Gap between countertops and cabinetry 7/28 Homeowner didn’t mention it
Need lots of lightbulbs Still a few missing 8/11
Air filter issue? (Hallway)
Drywall repairs near thermostat painter
Push stove into place 8/11
Attic cover
Garage door?
CODED LOCKBOX 1919
Basement toilet paper holder
Weatherstripping Painter
Missing 1 chandelier bulb Jill
Paint touch up Tues, Aug 17
Splash locks Put in place
Touch up paint Painter
Bed
Bed
Master bed closet shelving
transition strip at front door is loose and needs glued down Flooring guys
paint the bottom of front door underneath it. Painter
re clean cabinets in the kitchen Jill
theres a place in the powder room under the crown molding that needs painted Painter
caulk along back of the sink in the powder room Painter
clean the room under the stairs on the main level Jill
nail holes in crown molding in living room needs to be filled in Painter
bottom of crown molding in living room needs painted in a couple of spots Painter
fill in gaps on both sides of transition strip at the top of the stairs on the landing and the gaps at the top step transition strip also. Painter
crack in the wall beside the shower needs re caulked in the hallway bathroom on 3rd floor Painter
they want more caulk around the sink in the hall bath on 3rd floor Painter
garage still needs painted. Painter
missing screw in the top hand rail going up to the 3rd floor Jill
closet door in the small bedroom to the right needs painted behind the hinges Painter
Another coat of poly
Splash blocks need to be installed - Tom
UPGRADES - COMPLETED
    Bonus Room and Bath  
    Add closet to bonus room  
    Crown Moulding Main Level  
    LVP Bonus Room  
    LVP up hallway and bedrooms  
    Oak Stairs to bedroom level  
    Cabinet Crown Moulding  
    Painted Kitchen and Bath Cabinetry  
    Level III Quartz Kitchen Counters  
CRITICAL PATH - COMPLETED
-- -- Building Permit (30) *       
-- -- Order Roof & Floor Trusses (1)      
-- -- Order Windows & Doors (0)      
-- -- Stake Out Home (1)      
-- -- Excavate (2)      
-- -- Inspection (Footers) (1)      
-- -- Pour Footers (1) *       
-- -- Set Forms (2)      
-- -- Pour Foundation Walls (1)      
-- -- Plumb Slab (2)       in process 2/14
-- -- Inspection (Plumbing Under Slab) (1)      
-- -- Prepare Slab (1)      
-- -- Inspection (Slab) (1)      
-- -- Pour Slab (1) *       
-- -- Framing I (9)       in process 3/7
-- -- Order Steps (0)      
-- -- Order Tubs / Showers (0)      
-- -- Framing II (8)      
-- -- Framing III (8) *       
-- -- Install Stairs (0) *       
-- -- Windows & Doors (0) *       
-- -- House Number and Status in Window (0)      
-- -- Roofing (0) *       
-- -- Order Cabinets (0)      
-- -- Order Appliances (0)       SS Standard
-- -- Deck (0)      
-- -- Gutters (0)      
-- -- Driveway (0) *       
-- -- Privacy Divider / Fence (0) *   09.07.2021     Tom calling to set up install
-- -- Sod / Seed / Landscaping (0)      
-- -- HVAC Rough In (4)       In process 4/14
-- -- Plumbing Rough In (4)       In process 5/1
-- -- Electric Rough In (4)       In process 5/5
-- -- Inspection (Rough In HVAC) (1)      
-- -- Exterior Vinyl (0) *       
-- -- Insulation (2) *        In process 5/8
-- -- Inspection (Insulation) (1)      
-- -- Inspection (Electric Service) (0)      
-- -- Inspection (Main Sewer Line) (0)      
-- -- Order Interior Doors & Trim (0)       Black hinges
-- -- Drywall (Hang) (4) *        In process 5/12
-- -- Drywall (Tape, Block, Skim, Sand) (6) *        In process 5/19
-- -- Paint 1 (1)      
-- -- Garage Door (0)      
-- -- House Numbers (0)  08.30.2021    
-- -- Cabinet Installation (2) *        June 21
-- -- Granite Installation (1) *       
-- -- Interior Trim - Install (3) *        in process 6/23
-- -- Luxury Vinyl Plank (3) *        In process 6/30
-- -- Luxury Vinyl Tile (0)      
-- -- Paint 2 (3)       Jill 7/26
-- -- Cover Floors (0)      
-- -- Deliver Plumbing / Lighting Fixtures (0)       Black plumbing; black lighting
-- -- Shoe Moulding (0)      
-- -- Shelving, Door Knobs, Fire Extinguisher (1) *        Black levers and bathroom accessories; Bonus Bath
-- -- Install Coded Lockbox (add extra keys) (0)      
-- -- Pay Water / Sewer Taps (0)      
-- -- Set Water Meter (1) *       
-- -- Electric Trim Out (3) *        Black Lighting. In process 7/31. 90% complete.
-- -- HVAC Trim Out (1) *        Partially complete 8/11
-- -- Plumbing Trim Out (2) *        Black Plumbing- 8/3 starting
-- -- Install Appliances (0) *        installing 8/6. No dishwasher
-- -- Paint 3 (2) *       
-- -- Carpet (2)      
-- -- Appraiser Confirms Construction Completion (0)       Sandy Davis, Mon, 8/16
-- -- Inspection (Final Building) (4) *        Mon, Aug 16
-- -- Pre Walk Through (0)      
-- -- Cleaning (1)  08.21.2021     In process 8/18
-- -- Certificate of Occupancy (1) *   08.19.2021    
-- -- C.O. to Lender (0)  08.19.2021    
-- -- Schedule Closing (0)  08.26.2021    
-- -- Buyer Walk Through (1) *   08.21.2021     Fri, 8/20, 12PM
-- -- Payment for Upgrades (0)  08.23.2021     $257,900 + $16,554 = $274,454
-- -- Keys to Settlement Agent (0)  08.21.2021    
-- -- Review Settlement Statement (0)  08.24.2021    
-- -- Jerry Signs Closing Documents (0)  08.24.2021    
-- -- Request Trash Tote From POA Manager (0)  08.26.2021    
-- -- Closing (1)  08.26.2021    
-- -- Remove Coded Lockbox (0)  08.30.2021