CONGERS - 3  ::  2823 Belgian Drive
[ BUILD: 20210000318 ]      
CRITICAL PATH   |   INSPECTIONS   |   FLOOR PLANS   |   SELECTIONS   |   SPECS   |   CHANGES   |   NHS
view photo archive
 
--   --   Missing window screens
Tue    Nov 4      Inspection (Concrete Wall) (1)      
Wed    Nov 5      Inspection (Conduit Under Slab) (1)      
Thu    Nov 6      Inspection (Drain Tile) (0)      
Thu    Nov 6      Verify Window & Roof Structure (0)      
Thu    Nov 6      Patio (0)      
Thu    Nov 6      Rough In Microwave Vent (0)      
Thu    Nov 6      Inspection (Rough In Plumbing) (1)      
Fri    Nov 7      Inspection (Rough In Electric) (1)      
Mon    Nov 10      Inspection (Framing) (1) *       
Tue    Nov 11      Inspection (Deck Piers) (0)      
Tue    Nov 11      Exterior Stone (0)      
Tue    Nov 11      Set Electric Meter (0) *       
Tue    Nov 11      Inspection (Main Water Line) (0)      
Tue    Nov 11      Order Plumbing / Lighting Fixtures (0)      
Tue    Nov 11      Interior Trim - Paint (1)      
Wed    Nov 12      Ceiling Fans (0)      
Wed    Nov 12      Blower Door Test (1)      
Thu    Nov 13      Inspection (Final HVAC) (1)      
Fri    Nov 14      Inspection (Final Plumbing) (1)      
Mon    Nov 17      Inspection (Final Electric) (1)      
Tue    Nov 18      Stain Hardwood Stairs (1) *       
--   --   Adding Oak treads Temporary steps will be installed until oak treads come in the next three weeks
--   --   Still waiting on buyer to sign selection sheet. Reached out to Ryan Roberts yet once again.
--   --   Temporary pine steps to be installed until I try to come in three weeks
--   --   Temporary pine steps to be Installed until oak treads arrive in three weeks.
--   --   Drywall correct in MB shower?
--   --   Drywall repairs surrounding shower
--   --   Replace back of k island? Granite? Granite in. Need back of cabinet 9/18
--   --   Replace cabinet w scratch Kate will bring it to the townhouse
--   --   Rock almost completed
--   --   Garage door 10/2
--   --   Paint 3 master bath
--   --   CODED LOCKBOX 3333
--   --   Upstairs bath trim/flooring gap Completed except master bath behind toilet
--   --   Loose shoe molding
--   --   MB shelving Kate will follow up, 10/14
--   --   Dent in fridge Lisa will order new door
--   --   Patch holes at stairs Jill will have painters patch
--   --   Splash blocks Tom
--   --   Exterior light broken? On floor of basement.
--   --   Dentedstove in garage CJ will remove
--   --   Touch up paint
--   --   Paint exterior door frame Painter
--   --   Master bathroom: Toilet has movement at floor. Have a plumber remove toilet, replacewax ring/seal and re-secure toilet.
--   --   Wire is missing a romex connector where entering outlet box for low voltage wiring panel. Have an electrician repair.
--   --   One outlet in the kitchen is within 6 feet of sink and not GFCI protected. Have an electrician repair.
--   --   Sheathing is not cut out enough for proper amount of upper ventilation in attic. Have aroofer cut out sheathing for a 4" gap or add other ventilation like a thermostatically controlled vent fan or passive vents.
--   --   Install a new HVAC filter.
--   --   Flashing is not installed over garage door trim. Install Z flashing as needed. Kick out flashing is not installed at ends of step flashing on side bump out. Have a roofer install kick out flashing to insure water does not leak behind siding. Z flashing is not installed where stone meets trim board at front of home. Install flashingor apply flexible sealant to insure water cannot leak behind stone.
--   --   Front door weather stripping has a gap at bottom latch side. Adjust door and/or weatherstripping.
--   --   Right bedroom: Door latch does not catch jamb plate. Repair so that door can be locked.
--   --   Left bedroom: Door rubs carpet when opened. Cut off 1/2" from bottom of door.
--   --   Rear dining room door latch does not lock. Repair or replace door latch/lock as needed.
--   --   Powder room: Exhaust fan cover is not tight against ceiling. Secure as needed.
--   --   Master bathroom: One piece of flooring has separated behind toilet. Re-install flooring where needed.
--   --   Splash block is not installed under gutter downspout at side of heat pump. Install a splashblock to divert water from foundation. In process 10/27
--   --   Metal wrap has a small gap on trim block for front porch roof support. Apply sealantwhere needed. Tom
--   --   Garage handles
--   --   Install correct garage door On order
--   --   Paint touch up in small left bedroom Painter
--   --   Clean paint from underneath deck door
--   --   Install z-flashing at bump out Tom
-- -- Ratified Contract? (0)  12.28.2021    
-- -- $2500 Deposit Received (0)  12.28.2021    
-- -- Association Packet Requested (0)  12.28.2021    
-- -- Association Packet Received (0)  12.28.2021    
-- -- Selections Meeting (0)  12.28.2021    
-- -- Selections Sheet Signed (0)  12.28.2021    
-- -- Amendment for Upgrades (B,S,L,T,BCP) (0)  12.28.2021    
-- -- Deposit For Upgrades Received (0)  12.28.2021    
-- -- Building Permit (30) *       
    Buyer requesting to add oak treads.  
    Glass Shower Door  
    UTile Shower in Master  
    Amendment from $281,900 to $287,700  
-- -- Order Roof & Floor Trusses (1)      
-- -- Order Windows & Doors (0)      
-- -- Stake Out Home (1)      
-- -- Excavate (2)      
-- -- Inspection (Footers) (1)      
-- -- Pour Footers (1) *       
-- -- Set Forms (2)       in process 3/24
-- -- Pour Foundation Walls (1)      
-- -- Plumb Slab (2)      
-- -- Inspection (Plumbing Under Slab) (1)      
-- -- Prepare Slab (1)      
-- -- Inspection (Slab) (1)      
-- -- Pour Slab (1) *       
-- -- Settlement Agent Confirmed (0)  12.28.2021    
-- -- Framing I (9)      
-- -- Order Steps (0)      
-- -- Order Tubs / Showers (0)      
-- -- Framing II (8)      
-- -- Framing III (8) *       
-- -- Install Stairs (0) *       
-- -- Windows & Doors (0) *       
-- -- House Number and Status in Window (0)  08.25.2021    
-- -- Roofing (0) *       
-- -- Order Cabinets (0)  08.23.2021    
-- -- Order Appliances (0)  08.23.2021     SS Standard
-- -- Deck (0)  09.29.2021    
-- -- Gutters (0)  10.16.2021    
-- -- Driveway (0) *   10.23.2021     Apron needed
-- -- Privacy Divider / Fence (0) *   09.29.2021    
-- -- Sod / Seed / Landscaping (0)  10.30.2021    
-- -- HVAC Rough In (4)       in process 6/23
-- -- Plumbing Rough In (4)      
-- -- Electric Rough In (4)      
-- -- Inspection (Rough In HVAC) (1)      
-- -- Exterior Vinyl (0) *   09.26.2021     in process 9/15
-- -- Insulation (2) *       
-- -- Inspection (Insulation) (1)      
-- -- Inspection (Electric Service) (0)  09.23.2021    
-- -- Inspection (Main Sewer Line) (0)  09.29.2021    
-- -- Order Interior Doors & Trim (0)  08.21.2021     BN Hinges
-- -- Drywall (Hang) (4) *        In process 7/24
-- -- Loan Approval (0)  12.28.2021    
-- -- Deed Preparation (0)  12.28.2021    
-- -- Drywall (Tape, Block, Skim, Sand) (6) *        In process 7/28
-- -- Paint 1 (1)      
-- -- Garage Door (0)  10.14.2021    
-- -- House Numbers (0)  10.02.2021    
-- -- Mailbox (0)  12.28.2021    
-- -- Cabinet Installation (2) *   08.23.2021     8/19
-- -- Granite Installation (1) *   09.11.2021     9/10
-- -- Interior Trim - Install (3) *   09.08.2021     Needs painting 9/6
-- -- Luxury Vinyl Plank (3) *   09.29.2021     In process 9/26. Powder bath few spots in kitchen need completed.
-- -- Luxury Vinyl Tile (0)  09.29.2021     In process 9/26
-- -- Paint 2 (3)  10.02.2021     Powder bath needs painting
-- -- Cover Floors (1)  10.14.2021    
-- -- Deliver Plumbing / Lighting Fixtures (0)  10.02.2021     Plumbing on site 9/26
-- -- Shoe Moulding (0)  10.10.2021     In process 10/6
-- -- Shelving, Door Knobs, Fire Extinguisher (0) *   10.13.2021     BN Levers and BN Bathroom accessories. In process10/10
-- -- Install Coded Lockbox (add extra keys) (0)  10.06.2021    
-- -- Pay Water / Sewer Taps (0)  09.23.2021    
-- -- Set Water Meter (0) *   10.07.2021    
-- -- Electric Trim Out (3) *   10.16.2021     BN Lighting. In process 10/13
-- -- HVAC Trim Out (1) *   10.02.2021     In process
-- -- Plumbing Trim Out (2) *   10.13.2021     In process 9/29
-- -- Install Appliances (0) *   10.14.2021     SS Standard
-- -- Paint 3 (2) *   10.06.2021     Completed except Master bath
-- -- Carpet (2)  10.10.2021     In process 10/6
-- -- Appraiser Confirms Construction Completion (0)  10.25.2021    
-- -- Inspection (Final Building) (2) *   10.25.2021     Fri, 10/22
-- -- Pre Walk Through (0)  10.18.2021     Wednesday, 10/20
-- -- Cleaning (1)  10.23.2021    
-- -- Certificate of Occupancy (1) *   10.25.2021    
-- -- C.O. to Lender (0)  10.25.2021    
-- -- Schedule Closing (0)  11.02.2021    
-- -- Buyer Walk Through (1) *   10.27.2021     Monday, 10/25 at 12:30 PM
-- -- Payment for Upgrades (0)  11.01.2021    
-- -- Keys to Settlement Agent (0)  10.28.2021    
-- -- Review Settlement Statement (0)  11.04.2021    
-- -- Jerry Signs Closing Documents (0)  11.04.2021    
-- -- Request Trash Tote From POA Manager (0)  11.02.2021    
-- -- Closing (1)  11.08.2021     Nov 4, 1:00 PM
-- -- Remove Coded Lockbox (0)  11.07.2021