CONGERS - 3  ::  2823 Belgian Drive
[ BUILD: 20210000318 ]      
CRITICAL PATH   |   INSPECTIONS   |   FLOOR PLANS   |   SELECTIONS   |   SPECS   |   CHANGES   |   NHS
view photo archive
 
TO DO
UPGRADES
---
CRITICAL PATH
Tue    Feb 3      Inspection (Concrete Wall) (1)      
Wed    Feb 4      Inspection (Conduit Under Slab) (1)      
    Inspection (Drain Tile) (0)      
Thu    Feb 5      Inspection (Rough In Plumbing) (1)      
Fri    Feb 6      Inspection (Rough In Electric) (1)      
Mon    Feb 9      Inspection (Framing) (1) *       
    Inspection (Deck Piers) (0)      
    Inspection (Main Water Line) (0)      
    Inspection (Final HVAC) (0)      
    Inspection (Final Plumbing) (0)      
    Inspection (Final Electric) (0)      
TO DO - COMPLETED OR DELETED
UPGRADES - COMPLETED
    Buyer requesting to add oak treads.  
    Glass Shower Door  
    UTile Shower in Master  
    Amendment from $281,900 to $287,700  
CRITICAL PATH - COMPLETED
-- -- Inspection (Footers) (1)      
-- -- Inspection (Plumbing Under Slab) (1)      
-- -- Inspection (Slab) (1)      
-- -- Inspection (Rough In HVAC) (1)      
-- -- Inspection (Insulation) (1)      
-- -- Inspection (Electric Service) (0)  09.23.2021    
-- -- Inspection (Main Sewer Line) (0)  09.29.2021    
-- -- Inspection (Final Building) (4) *   10.25.2021     Fri, 10/22