1 28 33 37 45 46 47 48 71 52 70 69 67 53 54 55 56 59 58 57 66 65 64 60 61 62 63 ADDR
CONGERS-2 - 4  ::  1316 Palomino Trail
[ BUILD: 20210001840 ]      
CRITICAL PATH   |   INSPECTIONS   |   FLOOR PLANS   |   SELECTIONS   |   SPECS   |   CHANGES   |   NHS
view photo archive
 
--   --   Fix basement plumbing rough in
--   --   Wrong flooring plank? Or just odd one? 5/1
--   --   Closet frame drywall repair
--   --   Cover upstairs flooring
--   --   CODED LOCKBOX 4444
--   --   Microwave plug in? 5/15 Tom
--   --   Kitchen needs electric trim out 5/15 Electrician
--   --   Caulk or fill in between Granite and fridge panel? Painter
--   --   Cover glass top range Jill
--   --   Caulk between granite in wall Painter
--   --   So screw holes in French doors in front door with covers Jill
--   --   Caulk back of fridge panel and wall Painter
--   --   Finish electric trim out
--   --   Paint touch up Painter. In process 5/25
--   --   Caulk around pedestal sink Painter
--   --   Tighten all plumbing fixture escutcheons Plumber
--   --   Finish HVAC trim out HVAC
--   --   Hole to be filled under escutcheon at showerhead and hall bathroom Painter
--   --   Caulk in side splashes at cultured marble in bathrooms Painter
--   --   Adjust closet doors Jill
--   --   Install screens Jill. Most are in.
--   --   Drywall repair closet-up bedroom Drywaller
--   --   Attic access cover Painter
--   --   Garage trim
--   --   Adjust HVAC drain a little?
--   --   Read gutter extension 5/30
--   --   Final stain on steps needed 6/1 ???
--   --   Replace HVAC vent up hallway 6/1 Jill or Tom will call Clem
--   --   Paint front door
--   --   Sand garage spot
--   --   Paint access cover
--   --   Caulk in gap on upstairs set of steps Painter
--   --   Ceiling blemish 6/8 Painter
--   --   Extend drain pipes in the mechanical closet to drain Tom will tell plumber
--   --   Address receptacle in garage Painter
--   --   Address glue residue at the transition at stairs and landing Denny
--   --   Clean toilet powder bathroom overspray
--   --   Final clean the floors and surfaces After painting
--   --   Add additional brackets on handrails Monday, 6/13/2022
--   --   Add additional brackets on handrails
--   --   Paint touch up Painter
--   --   Caulk in kitchen by refrigerator
--   --   Caulk at top stair on main level, both sides Painter
--   --   Silicon (caulk?) around kitchen island
--   --   Clean main level
--   --   Clean inside island cabinet and entire main level Jill
--   --   Silicon caulk between island and countertop
--   --   Patio door deadbolt does not lock Tom
--   --   Staircase going from main level to bedroom level missing trim under each step Kate will talk to Mattias
--   --   Caulk at top stair on landing area going to bedroom Painter
--   --   Landing floor not even with staircase on bedroom level and transition strip is crooked Denny
--   --   Vanity in master bathroom is not straight Tom will talk to installer, Kate will talk to Kimberly
--   --   Sand and paint at corners of tray ceiling in master bedroom Painter
--   --   Flooring issue in the kitchen Sagging - Eric is working on scheduling and supplies. Scheduled for 3/14 and 3/15
-- -- Ratified Contract? (0)  11.21.2021    
-- -- $2500 Deposit Received (0)  11.21.2021    
-- -- Association Packet Requested (0)  11.21.2021    
-- -- Association Packet Received (0)  11.21.2021    
-- -- Selections Meeting (0)  11.22.2021    
-- -- Selections Sheet Signed (0)  11.22.2021    
-- -- Amendment for Upgrades (B,S,L,T,BCP) (0)  12.01.2021     Waiting on Jerry to sign, 11/30/2021
-- -- Deposit For Upgrades Received (0)  11.30.2021     $1,531.25
-- -- Building Permit (30)  11.11.2021    
-- -- Order Roof & Floor Trusses (1)  11.11.2021    
-- -- Order Windows & Doors (0)  11.11.2021    
-- -- Stake Out Home (1)  11.11.2021    
-- -- Excavate (2)  11.11.2021    
-- -- Inspection (Footers) (1)  11.11.2021    
-- -- Inspection (Concrete Wall) (1)  11.14.2022    
-- -- Pour Footers (1)  11.11.2021    
-- -- Set Forms (2)  11.29.2021    
-- -- Pour Foundation Walls (1)  11.29.2021    
-- -- Plumb Slab (2)  12.02.2021    
-- -- Inspection (Plumbing Under Slab) (1)  12.14.2021    
-- -- Inspection (Conduit Under Slab) (1)  11.14.2022    
-- -- Prepare Slab (1)  12.06.2021    
-- -- Inspection (Slab) (1)  12.14.2021    
-- -- Inspection (Drain Tile) (0)  11.14.2022    
-- -- Pour Slab (1)  12.06.2021    
-- -- Settlement Agent Confirmed (0)  02.02.2022    
-- -- Framing I (9)  12.20.2021    
-- -- Order Steps (0)  12.20.2021    
-- -- Order Tubs / Showers (0)  12.09.2021    
-- -- Framing II (8)  12.27.2021    
-- -- Framing III (8)  01.24.2022    
-- -- Verify Window & Roof Structure (0)  02.01.2024    
-- -- Install Stairs (0)  01.17.2022    
-- -- Windows & Doors (0)  01.27.2022    
-- -- House Number and Status in Window (0)  02.28.2022    
-- -- Roofing (0)  02.14.2022    
-- -- Order Cabinets (0)  01.31.2022    
-- -- Order Appliances (0)  02.24.2022     Standard SS
-- -- Deck (0)  02.28.2022     n/a
-- -- Gutters (0)  05.05.2022    
-- -- Driveway (0)  05.30.2022     Expanded Driveway,
-- -- Patio (0)  11.14.2022    
-- -- Privacy Divider / Fence (0)  05.11.2022    
-- -- Sod / Seed / Landscaping (0)  06.08.2022    
-- -- HVAC Rough In (4)  02.10.2022     in process 2/5
-- -- Inspection (Rough In HVAC) (1)  03.07.2022    
-- -- Rough In Microwave Vent (0)  02.01.2024    
-- -- Plumbing Rough In (4)  02.27.2022     in process 2/16
-- -- Inspection (Rough In Plumbing) (1)  11.14.2022    
-- -- Electric Rough In (4)  03.02.2022     in process 2/27. Almost complete.
-- -- Inspection (Rough In Electric) (1)  11.14.2022    
-- -- Inspection (Deck Piers) (0)  11.14.2022    
-- -- Inspection (Framing) (1)  11.14.2022    
-- -- Exterior Vinyl (0)  05.05.2022    
-- -- Exterior Stone (0)  04.14.2022    
-- -- Insulation (2)  03.09.2022    
-- -- Inspection (Insulation) (1)  03.17.2022    
-- -- Inspection (Electric Service) (0)  05.12.2022    
-- -- Set Electric Meter (0)  04.11.2023    
-- -- Inspection (Main Sewer Line) (0)  01.31.2022    
-- -- Inspection (Main Water Line) (0)  11.14.2022    
-- -- Order Interior Doors & Trim (0)  03.10.2022    
-- -- Drywall (Hang) (4)  03.17.2022     Stocked 3/12
-- -- Loan Approval (0)  04.26.2022    
-- -- Deed Preparation (0)  04.13.2022    
-- -- Drywall (Tape, Block, Skim, Sand) (6)  03.23.2022     Needs final sanding 3/23
-- -- Paint 1 (1)  03.27.2022    
-- -- Garage Door (0)  06.05.2022    
-- -- House Numbers (0)  05.07.2022    
-- -- Mailbox (0)  06.02.2022    
-- -- Cabinet Installation (2)  04.07.2022     Installation April 6
-- -- Granite Installation (1)  04.18.2022    
-- -- Interior Trim - Install (3)  04.07.2022     Almost complete 3/30
-- -- Order Plumbing / Lighting Fixtures (0)  02.01.2024    
-- -- Interior Trim - Paint (1)  11.14.2022    
-- -- Luxury Vinyl Plank (3)  04.27.2022     In process 4/24
-- -- Luxury Vinyl Tile (0)  04.24.2022    
-- -- Paint 2 (3)  04.18.2022    
-- -- Cover Floors (1)  05.01.2022    
-- -- Deliver Plumbing / Lighting Fixtures (0)  05.11.2022    
-- -- Shoe Moulding (0)  05.04.2022     In process 5/1
-- -- Shelving, Door Knobs, Fire Extinguisher (0)  05.07.2022     In process 5/4
-- -- Install Coded Lockbox (add extra keys) (0)  05.11.2022    
-- -- Pay Water / Sewer Taps (0)  03.31.2022    
-- -- Set Water Meter (0)  05.12.2022    
-- -- Electric Trim Out (3)  05.15.2022     Black lighting. In process 5/11
-- -- Ceiling Fans (0)  05.11.2022     Living Room
-- -- HVAC Trim Out (1)  05.01.2022     In process. Heat Pump needs hooked up & thermostat set 4/24
-- -- Blower Door Test (1)  02.01.2024    
-- -- Plumbing Trim Out (2)  05.07.2022     Black Standard
-- -- Install Appliances (0)  05.11.2022     Standard SS. On site.
-- -- Paint 3 (2)  05.04.2022    
-- -- Carpet (2)  04.26.2022    
-- -- Appraiser Confirms Construction Completion (0)  06.08.2022    
-- -- Inspection (Final HVAC) (1)  11.14.2022    
-- -- Inspection (Final Plumbing) (1)  11.14.2022    
-- -- Inspection (Final Electric) (1)  11.14.2022    
-- -- Inspection (Final Building) (2)  06.02.2022    
-- -- Pre Walk Through (0)  06.02.2022    
-- -- Stain Hardwood Stairs (1)  06.06.2022     Up set primed 5/25
-- -- Cleaning (1)  06.08.2022    
-- -- Certificate of Occupancy (1)  06.08.2022    
-- -- C.O. to Lender (0)  06.08.2022    
-- -- Schedule Closing (0)  06.09.2022    
-- -- Buyer Walk Through (1)  06.09.2022    
-- -- Payment for Upgrades (0)  06.08.2022    
-- -- Keys to Settlement Agent (0)  06.07.2022    
-- -- Review Settlement Statement (0)  06.08.2022    
-- -- Jerry Signs Closing Documents (0)  06.11.2022     Thursday, June 9, 1:30 PM
-- -- Request Trash Tote From POA Manager (0)  06.11.2022    
-- -- Closing (1)  06.11.2022     Sara at West View Title
-- -- Remove Coded Lockbox (0)  06.30.2022