CONGERS-2 - 4  ::  1316 Palomino Trail
[ BUILD: 20210001840 ]      
CRITICAL PATH   |   INSPECTIONS   |   FLOOR PLANS   |   SELECTIONS   |   SPECS   |   CHANGES   |   NHS
view photo archive
 
TO DO
---
UPGRADES
---
CRITICAL PATH
---
TO DO - COMPLETED OR DELETED
Fix basement plumbing rough in
Wrong flooring plank? Or just odd one? 5/1
Closet frame drywall repair
Cover upstairs flooring
CODED LOCKBOX 4444
Microwave plug in? 5/15 Tom
Kitchen needs electric trim out 5/15 Electrician
Caulk or fill in between Granite and fridge panel? Painter
Cover glass top range Jill
Caulk between granite in wall Painter
So screw holes in French doors in front door with covers Jill
Caulk back of fridge panel and wall Painter
Finish electric trim out
Paint touch up Painter. In process 5/25
Caulk around pedestal sink Painter
Tighten all plumbing fixture escutcheons Plumber
Finish HVAC trim out HVAC
Hole to be filled under escutcheon at showerhead and hall bathroom Painter
Caulk in side splashes at cultured marble in bathrooms Painter
Adjust closet doors Jill
Install screens Jill. Most are in.
Drywall repair closet-up bedroom Drywaller
Attic access cover Painter
Garage trim
Adjust HVAC drain a little?
Read gutter extension 5/30
Final stain on steps needed 6/1 ???
Replace HVAC vent up hallway 6/1 Jill or Tom will call Clem
Paint front door
Sand garage spot
Paint access cover
Caulk in gap on upstairs set of steps Painter
Ceiling blemish 6/8 Painter
Extend drain pipes in the mechanical closet to drain Tom will tell plumber
Address receptacle in garage Painter
Address glue residue at the transition at stairs and landing Denny
Clean toilet powder bathroom overspray
Final clean the floors and surfaces After painting
Add additional brackets on handrails Monday, 6/13/2022
Add additional brackets on handrails
Paint touch up Painter
Caulk in kitchen by refrigerator
Caulk at top stair on main level, both sides Painter
Silicon (caulk?) around kitchen island
Clean main level
Clean inside island cabinet and entire main level Jill
Silicon caulk between island and countertop
Patio door deadbolt does not lock Tom
Staircase going from main level to bedroom level missing trim under each step Kate will talk to Mattias
Caulk at top stair on landing area going to bedroom Painter
Landing floor not even with staircase on bedroom level and transition strip is crooked Denny
Vanity in master bathroom is not straight Tom will talk to installer, Kate will talk to Kimberly
Sand and paint at corners of tray ceiling in master bedroom Painter
Flooring issue in the kitchen Sagging - Eric is working on scheduling and supplies. Scheduled for 3/14 and 3/15
UPGRADES - COMPLETED
    Expanded Driveway  
    LVP Upstairs  
    Pull out trays ( four) in 18  
    Pull out trays Base 33  
    Painted steps to bedroom level  
    double trash can  
    Living Room ceiling fan  
    Amendment to increase price by $6,125  
CRITICAL PATH - COMPLETED
-- -- Ratified Contract? (0)  11.21.2021    
-- -- $2500 Deposit Received (0)  11.21.2021    
-- -- Association Packet Requested (0)  11.21.2021    
-- -- Association Packet Received (0)  11.21.2021    
-- -- Selections Meeting (0)  11.22.2021    
-- -- Selections Sheet Signed (0)  11.22.2021    
-- -- Amendment for Upgrades (B,S,L,T,BCP) (0)  12.01.2021     Waiting on Jerry to sign, 11/30/2021
-- -- Deposit For Upgrades Received (0)  11.30.2021     $1,531.25
-- -- Building Permit (30) *   11.11.2021    
-- -- Order Roof & Floor Trusses (1)  11.11.2021    
-- -- Order Windows & Doors (0)  11.11.2021    
-- -- Stake Out Home (1)  11.11.2021    
-- -- Excavate (2)  11.11.2021    
-- -- Inspection (Footers) (1)  11.11.2021    
-- -- Inspection (Concrete Wall) (1)  11.14.2022    
-- -- Pour Footers (1) *   11.11.2021    
-- -- Set Forms (2)  11.29.2021    
-- -- Pour Foundation Walls (1)  11.29.2021    
-- -- Plumb Slab (2)  12.02.2021    
-- -- Inspection (Plumbing Under Slab) (1)  12.14.2021    
-- -- Inspection (Conduit Under Slab) (1)  11.14.2022    
-- -- Prepare Slab (1)  12.06.2021    
-- -- Inspection (Slab) (1)  12.14.2021    
-- -- Inspection (Drain Tile) (0)  11.14.2022    
-- -- Pour Slab (1) *   12.06.2021    
-- -- Settlement Agent Confirmed (0)  02.02.2022    
-- -- Framing I (9)  12.20.2021    
-- -- Order Steps (0)  12.20.2021    
-- -- Order Tubs / Showers (0)  12.09.2021    
-- -- Framing II (8)  12.27.2021    
-- -- Framing III (8) *   01.24.2022    
-- -- Verify Window & Roof Structure (0)  02.01.2024    
-- -- Install Stairs (0) *   01.17.2022    
-- -- Windows & Doors (0) *   01.27.2022    
-- -- House Number and Status in Window (0)  02.28.2022    
-- -- Roofing (0) *   02.14.2022    
-- -- Order Cabinets (0)  01.31.2022    
-- -- Order Appliances (0)  02.24.2022     Standard SS
-- -- Deck (0)  02.28.2022     n/a
-- -- Gutters (0)  05.05.2022    
-- -- Driveway (0) *   05.30.2022     Expanded Driveway,
-- -- Patio (0)  11.14.2022    
-- -- Privacy Divider / Fence (0) *   05.11.2022    
-- -- Sod / Seed / Landscaping (0)  06.08.2022    
-- -- HVAC Rough In (4)  02.10.2022     in process 2/5
-- -- Rough In Microwave Vent (0)  02.01.2024    
-- -- Plumbing Rough In (4)  02.27.2022     in process 2/16
-- -- Electric Rough In (4)  03.02.2022     in process 2/27. Almost complete.
-- -- Inspection (Rough In HVAC) (1)  03.07.2022    
-- -- Inspection (Rough In Plumbing) (1)  11.14.2022    
-- -- Inspection (Rough In Electric) (1)  11.14.2022    
-- -- Inspection (Framing) (1) *   11.14.2022    
-- -- Inspection (Deck Piers) (0)  11.14.2022    
-- -- Exterior Vinyl (0) *   05.05.2022    
-- -- Exterior Stone (0)  04.14.2022    
-- -- Insulation (2) *   03.09.2022    
-- -- Inspection (Insulation) (1)  03.17.2022    
-- -- Inspection (Electric Service) (0)  05.12.2022    
-- -- Set Electric Meter (0) *   04.11.2023    
-- -- Inspection (Main Sewer Line) (0)  01.31.2022    
-- -- Inspection (Main Water Line) (0)  11.14.2022    
-- -- Order Interior Doors & Trim (0)  03.10.2022    
-- -- Drywall (Hang) (4) *   03.17.2022     Stocked 3/12
-- -- Loan Approval (0)  04.26.2022    
-- -- Deed Preparation (0)  04.13.2022    
-- -- Drywall (Tape, Block, Skim, Sand) (6) *   03.23.2022     Needs final sanding 3/23
-- -- Paint 1 (1)  03.27.2022    
-- -- Garage Door (0)  06.05.2022    
-- -- House Numbers (0)  05.07.2022    
-- -- Mailbox (0)  06.02.2022    
-- -- Cabinet Installation (2) *   04.07.2022     Installation April 6
-- -- Granite Installation (1) *   04.18.2022    
-- -- Interior Trim - Install (3) *   04.07.2022     Almost complete 3/30
-- -- Order Plumbing / Lighting Fixtures (0)  02.01.2024    
-- -- Interior Trim - Paint (1)  11.14.2022    
-- -- Luxury Vinyl Plank (3) *   04.27.2022     In process 4/24
-- -- Luxury Vinyl Tile (0)  04.24.2022    
-- -- Paint 2 (3)  04.18.2022    
-- -- Cover Floors (0)  05.01.2022    
-- -- Deliver Plumbing / Lighting Fixtures (0)  05.11.2022    
-- -- Shoe Moulding (0)  05.04.2022     In process 5/1
-- -- Shelving, Door Knobs, Fire Extinguisher (1) *   05.07.2022     In process 5/4
-- -- Install Coded Lockbox (add extra keys) (0)  05.11.2022    
-- -- Pay Water / Sewer Taps (0)  03.31.2022    
-- -- Set Water Meter (1) *   05.12.2022    
-- -- Electric Trim Out (3) *   05.15.2022     Black lighting. In process 5/11
-- -- Ceiling Fans (0)  05.11.2022     Living Room
-- -- HVAC Trim Out (1) *   05.01.2022     In process. Heat Pump needs hooked up & thermostat set 4/24
-- -- Blower Door Test (1)  02.01.2024    
-- -- Plumbing Trim Out (2) *   05.07.2022     Black Standard
-- -- Install Appliances (0) *   05.11.2022     Standard SS. On site.
-- -- Paint 3 (2) *   05.04.2022    
-- -- Carpet (2)  04.26.2022    
-- -- Appraiser Confirms Construction Completion (0)  06.08.2022    
-- -- Inspection (Final HVAC) (0)  11.14.2022    
-- -- Inspection (Final Plumbing) (0)  11.14.2022    
-- -- Inspection (Final Electric) (0)  11.14.2022    
-- -- Inspection (Final Building) (4) *   06.02.2022    
-- -- Pre Walk Through (0)  06.02.2022    
-- -- Stain Hardwood Stairs (1) *   06.06.2022     Up set primed 5/25
-- -- Cleaning (1)  06.08.2022    
-- -- Certificate of Occupancy (1) *   06.08.2022    
-- -- C.O. to Lender (0)  06.08.2022    
-- -- Schedule Closing (0)  06.09.2022    
-- -- Buyer Walk Through (1) *   06.09.2022    
-- -- Payment for Upgrades (0)  06.08.2022    
-- -- Keys to Settlement Agent (0)  06.07.2022    
-- -- Review Settlement Statement (0)  06.08.2022    
-- -- Jerry Signs Closing Documents (0)  06.11.2022     Thursday, June 9, 1:30 PM
-- -- Request Trash Tote From POA Manager (0)  06.11.2022    
-- -- Closing (1)  06.11.2022     Sara at West View Title
-- -- Remove Coded Lockbox (0)  06.30.2022