1 87 73 ADDR
CONGERS-2 - 129  ::  1321 Palomino Trail
[ BUILD: 20210001832 ]      
CRITICAL PATH   |   INSPECTIONS   |   FLOOR PLANS   |   SELECTIONS   |   SPECS   |   CHANGES   |   NHS
view photo archive
 
--   --   Front bedroom window needed
--   --   Insulate tubs
--   --   Side splash needed for hall vanity? needs caulking
--   --   Retaining Wall around back patio
--   --   Siding falling 5/30
--   --   CODED LOCKBOX 0129
--   --   Attic cover Painter
--   --   Fix shelving after carpet installation
--   --   Blemish in ceiling (drywall repair)
--   --   Outside electric needs done 132-129
--   --   Touch up paint Painter
--   --   Finish main level electric trim out
--   --   Basement window needs trimmed Trimmed now just needs tape trimmed - Jill
--   --   Driveway, Tues, June 21
--   --   Patches around kitchen pendant lights Painter-needs to be painted? Patch appears done.
--   --   Trim closet door master bedroom closet - Edgar
--   --   Powder bath bulbs Jill
--   --   Closet handle up bedroom Joe
--   --   Shingle sticking out on front side of roof Tom
--   --   Mailbox numbers needed Jill
--   --   Door plugs Jill
--   --   Insulation on carpet upstairs landing Jill or Eric
--   --   Sand concrete repair Tom
--   --   sand and paint around dining light
--   --   Secure bottom square of post to deck at house Tom
--   --   remove red cover from alarm Jill
--   --   paint and caulk shoe at front door
--   --   tray ceiling drywall corners
--   --   cut vent into master bath floor Jill
--   --   place attic access cover Needs painting/insulation clean up 7/13
--   --   Cut down master closet door Jill will coordinate
--   --   fix crack in hall bath tub
--   --   Fix broken trim t base of French doors
--   --   Power wash back
--   --   Fix sheetrock above HVAC Drywaller
--   --   Paint touch up
--   --   Clean master closet floor Jill
--   --   Is HVAC tube in basement supposed to be hooked up?
--   --   Fix dips in concrete Tom will coordinate
Tue    Jul 1      Association Packet Received (0)  11.21.2021    
Tue    Jul 1      Building Permit (30)  11.11.2021    
Tue    Aug 12      Pour Foundation Walls (1)  12.09.2021    
Wed    Aug 13      Plumb Slab (2)  12.13.2021    
Fri    Aug 15      Inspection (Plumbing Under Slab) (1)  12.20.2021    
Mon    Aug 18      Verify Window & Roof Structure (0)      
Mon    Aug 18      Install Stairs (0)  02.24.2022    
Mon    Aug 18      House Number and Status in Window (0)  02.28.2022    
Mon    Aug 18      Order Cabinets (0)  01.31.2022    
    Painted White Kitchen Cabinetry  
Mon    Aug 18      Rough In Microwave Vent (0)      
Mon    Aug 18      Insulation (2) *   03.30.2022     3/25 or 3/26
Wed    Aug 20      Inspection (Electric Service) (0)  06.02.2022    
Wed    Aug 20      Garage Door (0) *   04.04.2022    
Wed    Aug 20      Order Plumbing / Lighting Fixtures (0)      
Wed    Aug 20      Deliver Plumbing / Lighting Fixtures (0)  06.05.2022    
Wed    Aug 20      Shelving, Door Knobs, Fire Extinguisher (0) *   06.12.2022     Almost complete 6/8
Wed    Aug 20      Set Water Meter (0) *   06.09.2022    
Wed    Aug 20      Blower Door Test (1)      
Thu    Aug 21      Appraiser Confirms Construction Completion (0)  07.06.2022     Mon, July 4
Thu    Aug 21      Cleaning (1)  07.10.2022     Thurs, Jul 7
Fri    Aug 22      C.O. to Lender (0)  07.07.2022    
--   --   Paint foundation Painter- after sod goes down
--   --   remove trash and cement from backyard
-- -- Ratified Contract? (0)  11.21.2021    
    Amendment to increase price by $5,000  
-- -- $2500 Deposit Received (0)  11.21.2021    
-- -- Association Packet Requested (0)  11.21.2021    
-- -- Selections Meeting (0)  01.04.2022    
-- -- Selections Sheet Signed (0)  01.26.2022     1/4/2022: sent to Nina for buyer signatures
-- -- Amendment for Upgrades (B,S,L,T,BCP) (0)  02.10.2022     1/26/2022: sent to Nina for buyer signatures
-- -- Deposit For Upgrades Received (0)  01.26.2022     n/a
-- -- Order Roof & Floor Trusses (1)  11.11.2021    
-- -- Order Windows & Doors (0)  04.25.2022    
-- -- Stake Out Home (1)  11.08.2021    
-- -- Excavate (2)  11.29.2021    
-- -- Inspection (Footers) (1)  11.29.2021    
-- -- Inspection (Concrete Wall) (1)  02.14.2023    
-- -- Pour Footers (1) *   11.29.2021    
-- -- Set Forms (2)  12.06.2021     in process 12/1
-- -- Inspection (Conduit Under Slab) (1)  02.14.2023    
-- -- Prepare Slab (1)  12.20.2021    
-- -- Inspection (Slab) (1)  12.20.2021    
-- -- Inspection (Drain Tile) (0)  02.14.2023    
-- -- Pour Slab (1) *   12.20.2021    
-- -- Settlement Agent Confirmed (0)  04.13.2022    
-- -- Framing I (9)  01.03.2022    
-- -- Order Steps (0)  12.20.2021    
-- -- Order Tubs / Showers (0)  12.09.2021    
-- -- Framing II (8)  01.17.2022    
-- -- Framing III (8) *   02.03.2022    
-- -- Windows & Doors (0) *   03.13.2022    
-- -- Roofing (0) *   02.14.2022    
-- -- Order Appliances (0)  02.24.2022     Standard
-- -- Deck (0)  04.25.2022     in process-expanded deck
    Expanded Deck 12x18  
-- -- Gutters (0)  05.02.2022    
-- -- Driveway (0) *   06.27.2022     Expanded Patio 10x10 - Tuesday, June 21
    Expanded Patio 10x10  
-- -- Patio (0)  02.14.2023    
-- -- Privacy Divider / Fence (0)  04.25.2022    
-- -- Sod / Seed / Landscaping (0)  06.29.2022    
-- -- HVAC Rough In (4)  02.24.2022     in process 2/16
-- -- Inspection (Rough In HVAC) (1)  03.24.2022    
-- -- Plumbing Rough In (4)  03.23.2022     in process 3/12
-- -- Inspection (Rough In Plumbing) (1)  02.14.2023    
-- -- Electric Rough In (4)  03.23.2022     In process 3/19
-- -- Inspection (Rough In Electric) (1)  02.14.2023    
-- -- Inspection (Deck Piers) (0)  02.14.2023    
-- -- Inspection (Framing) (1) *   02.14.2023    
-- -- Exterior Vinyl (0) *   04.18.2022    
-- -- Exterior Stone (0)  04.14.2022    
-- -- Inspection (Insulation) (1)  03.31.2022    
-- -- Set Electric Meter (0) *   04.11.2023    
-- -- Inspection (Main Sewer Line) (0)  04.14.2022    
-- -- Inspection (Main Water Line) (0)  02.14.2023    
-- -- Order Interior Doors & Trim (0)  03.10.2022    
-- -- Drywall (Hang) (4) *   04.10.2022    
-- -- Loan Approval (0)  06.30.2022    
-- -- Deed Preparation (0)  04.13.2022    
-- -- Drywall (Tape, Block, Skim, Sand) (6) *   04.18.2022     In process 4/13
-- -- Paint 1 (1)  04.18.2022    
-- -- House Numbers (0)  06.29.2022    
-- -- Mailbox (0)  07.03.2022    
-- -- Cabinet Installation (2) *   04.18.2022     4/14
-- -- Granite Installation (1) *   05.07.2022     5/6
-- -- Interior Trim - Install (3) *   05.11.2022     5/7 needs painting
-- -- Interior Trim - Paint (1)  02.14.2023    
-- -- Luxury Vinyl Plank (3) *   05.30.2022    
-- -- Luxury Vinyl Tile (0)  06.01.2022     Hall bath left 5/30
-- -- Paint 2 (3)  05.25.2022    
-- -- Cover Floors (1)  06.29.2022    
-- -- Shoe Moulding (0)  06.08.2022     On site 6/5
-- -- Install Coded Lockbox (add extra keys) (0)  06.05.2022    
-- -- Pay Water / Sewer Taps (0)  05.19.2022    
-- -- Electric Trim Out (3)  06.18.2022     Black Lighting. In process 6/12. Kitchen needs completed.
-- -- Ceiling Fans (0)  05.16.2022    
-- -- HVAC Trim Out (1)  06.15.2022     Furnace set 6/1
-- -- Plumbing Trim Out (2)  06.05.2022     Black Standard
-- -- Install Appliances (0) *   06.08.2022    
-- -- Paint 3 (2) *   06.12.2022    
    Painted carpet grade steps (buyer to provide color to match flooring)  
-- -- Carpet (2)  06.25.2022    
-- -- Inspection (Final HVAC) (1)  02.14.2023    
-- -- Inspection (Final Plumbing) (1)  02.14.2023    
-- -- Inspection (Final Electric) (1)  02.14.2023    
-- -- Inspection (Final Building) (2) *   07.05.2022     Fri, July 1
-- -- Pre Walk Through (0)  07.05.2022    
-- -- Stain Hardwood Stairs (1)  06.29.2022    
-- -- Certificate of Occupancy (1) *   07.06.2022    
-- -- Schedule Closing (0)  07.07.2022     Tue, June 12
-- -- Buyer Walk Through (1)  07.13.2022     Mon, July 11 confirmed for 2:00 PM
-- -- Payment for Upgrades (0)  06.30.2022    
-- -- Keys to Settlement Agent (0)  06.28.2022    
-- -- Review Settlement Statement (0)  07.08.2022    
-- -- Jerry Signs Closing Documents (0)  06.30.2022     Wednesday, June 29, 1:00 PM
-- -- Request Trash Tote From POA Manager (0)  06.28.2022    
-- -- Closing (1)  07.13.2022     Brittany @ West View Title (June 12)
-- -- Remove Coded Lockbox (0)  08.29.2022