37 ADDR
CONGERS-2 - 129  ::  1321 Palomino Trail
[ BUILD: 20210001832 ]      
CRITICAL PATH   |   INSPECTIONS   |   FLOOR PLANS   |   SELECTIONS   |   SPECS   |   CHANGES   |   NHS
view photo archive
 
TO DO
Front bedroom window needed
Insulate tubs
Side splash needed for hall vanity? needs caulking
Retaining Wall around back patio
Siding falling 5/30
CODED LOCKBOX 0129
Attic cover Painter
Fix shelving after carpet installation
Blemish in ceiling (drywall repair)
Outside electric needs done 132-129
Touch up paint Painter
Finish main level electric trim out
Basement window needs trimmed Trimmed now just needs tape trimmed - Jill
Driveway, Tues, June 21
Patches around kitchen pendant lights Painter-needs to be painted? Patch appears done.
Trim closet door master bedroom closet - Edgar
Powder bath bulbs Jill
Closet handle up bedroom Joe
Shingle sticking out on front side of roof Tom
Mailbox numbers needed Jill
Door plugs Jill
Insulation on carpet upstairs landing Jill or Eric
Sand concrete repair Tom
sand and paint around dining light
Secure bottom square of post to deck at house Tom
remove red cover from alarm Jill
paint and caulk shoe at front door
tray ceiling drywall corners
cut vent into master bath floor Jill
place attic access cover Needs painting/insulation clean up 7/13
Cut down master closet door Jill will coordinate
fix crack in hall bath tub
Fix broken trim t base of French doors
Power wash back
Fix sheetrock above HVAC Drywaller
Paint touch up
Clean master closet floor Jill
Is HVAC tube in basement supposed to be hooked up?
Fix dips in concrete Tom will coordinate
UPGRADES
---
CRITICAL PATH
    Association Packet Received (0)  11.21.2021    
Tue    Feb 3      Building Permit (30) *   11.11.2021    
Tue    Mar 17      Pour Foundation Walls (1)  12.09.2021    
Wed    Mar 18      Plumb Slab (2)  12.13.2021    
Fri    Mar 20      Inspection (Plumbing Under Slab) (1)  12.20.2021    
    Verify Window & Roof Structure (0)      
    Install Stairs (0) *   02.24.2022    
    House Number and Status in Window (0)  02.28.2022    
    Order Cabinets (0)  01.31.2022    
    Rough In Microwave Vent (0)      
Mon    Mar 23      Insulation (2) *   03.30.2022     3/25 or 3/26
    Inspection (Electric Service) (0)  06.02.2022    
    Garage Door (0)  04.04.2022    
    Order Plumbing / Lighting Fixtures (0)      
    Deliver Plumbing / Lighting Fixtures (0)  06.05.2022    
Wed    Mar 25      Shelving, Door Knobs, Fire Extinguisher (1) *   06.12.2022     Almost complete 6/8
Thu    Mar 26      Set Water Meter (1) *   06.09.2022    
Fri    Mar 27      Blower Door Test (1)      
    Appraiser Confirms Construction Completion (0)  07.06.2022     Mon, July 4
Mon    Mar 30      Cleaning (1)  07.10.2022     Thurs, Jul 7
    C.O. to Lender (0)  07.07.2022    
TO DO - COMPLETED OR DELETED
Paint foundation Painter- after sod goes down
remove trash and cement from backyard
UPGRADES - COMPLETED
    Expanded Deck 12x18  
    Expanded Patio 10x10  
    Painted White Kitchen Cabinetry  
    Painted carpet grade steps (buyer to provide color to match flooring)  
    Amendment to increase price by $5,000  
CRITICAL PATH - COMPLETED
-- -- Ratified Contract? (0)  11.21.2021    
-- -- $2500 Deposit Received (0)  11.21.2021    
-- -- Association Packet Requested (0)  11.21.2021    
-- -- Selections Meeting (0)  01.04.2022    
-- -- Selections Sheet Signed (0)  01.26.2022     1/4/2022: sent to Nina for buyer signatures
-- -- Amendment for Upgrades (B,S,L,T,BCP) (0)  02.10.2022     1/26/2022: sent to Nina for buyer signatures
-- -- Deposit For Upgrades Received (0)  01.26.2022     n/a
-- -- Order Roof & Floor Trusses (1)  11.11.2021    
-- -- Order Windows & Doors (0)  04.25.2022    
-- -- Stake Out Home (1)  11.08.2021    
-- -- Excavate (2)  11.29.2021    
-- -- Inspection (Footers) (1)  11.29.2021    
-- -- Inspection (Concrete Wall) (1)  02.14.2023    
-- -- Pour Footers (1) *   11.29.2021    
-- -- Set Forms (2)  12.06.2021     in process 12/1
-- -- Inspection (Conduit Under Slab) (1)  02.14.2023    
-- -- Prepare Slab (1)  12.20.2021    
-- -- Inspection (Slab) (1)  12.20.2021    
-- -- Inspection (Drain Tile) (0)  02.14.2023    
-- -- Pour Slab (1) *   12.20.2021    
-- -- Settlement Agent Confirmed (0)  04.13.2022    
-- -- Framing I (9)  01.03.2022    
-- -- Order Steps (0)  12.20.2021    
-- -- Order Tubs / Showers (0)  12.09.2021    
-- -- Framing II (8)  01.17.2022    
-- -- Framing III (8) *   02.03.2022    
-- -- Windows & Doors (0) *   03.13.2022    
-- -- Roofing (0) *   02.14.2022    
-- -- Order Appliances (0)  02.24.2022     Standard
-- -- Deck (0)  04.25.2022     in process-expanded deck
-- -- Gutters (0)  05.02.2022    
-- -- Driveway (0) *   06.27.2022     Expanded Patio 10x10 - Tuesday, June 21
-- -- Patio (0)  02.14.2023    
-- -- Privacy Divider / Fence (0) *   04.25.2022    
-- -- Sod / Seed / Landscaping (0)  06.29.2022    
-- -- HVAC Rough In (4)  02.24.2022     in process 2/16
-- -- Plumbing Rough In (4)  03.23.2022     in process 3/12
-- -- Electric Rough In (4)  03.23.2022     In process 3/19
-- -- Inspection (Rough In HVAC) (1)  03.24.2022    
-- -- Inspection (Rough In Plumbing) (1)  02.14.2023    
-- -- Inspection (Rough In Electric) (1)  02.14.2023    
-- -- Inspection (Framing) (1) *   02.14.2023    
-- -- Inspection (Deck Piers) (0)  02.14.2023    
-- -- Exterior Vinyl (0) *   04.18.2022    
-- -- Exterior Stone (0)  04.14.2022    
-- -- Inspection (Insulation) (1)  03.31.2022    
-- -- Set Electric Meter (0) *   04.11.2023    
-- -- Inspection (Main Sewer Line) (0)  04.14.2022    
-- -- Inspection (Main Water Line) (0)  02.14.2023    
-- -- Order Interior Doors & Trim (0)  03.10.2022    
-- -- Drywall (Hang) (4) *   04.10.2022    
-- -- Loan Approval (0)  06.30.2022    
-- -- Deed Preparation (0)  04.13.2022    
-- -- Drywall (Tape, Block, Skim, Sand) (6) *   04.18.2022     In process 4/13
-- -- Paint 1 (1)  04.18.2022    
-- -- House Numbers (0)  06.29.2022    
-- -- Mailbox (0)  07.03.2022    
-- -- Cabinet Installation (2) *   04.18.2022     4/14
-- -- Granite Installation (1) *   05.07.2022     5/6
-- -- Interior Trim - Install (3) *   05.11.2022     5/7 needs painting
-- -- Interior Trim - Paint (1)  02.14.2023    
-- -- Luxury Vinyl Plank (3) *   05.30.2022    
-- -- Luxury Vinyl Tile (0)  06.01.2022     Hall bath left 5/30
-- -- Paint 2 (3)  05.25.2022    
-- -- Cover Floors (0)  06.29.2022    
-- -- Shoe Moulding (0)  06.08.2022     On site 6/5
-- -- Install Coded Lockbox (add extra keys) (0)  06.05.2022    
-- -- Pay Water / Sewer Taps (0)  05.19.2022    
-- -- Electric Trim Out (3) *   06.18.2022     Black Lighting. In process 6/12. Kitchen needs completed.
-- -- Ceiling Fans (0)  05.16.2022    
-- -- HVAC Trim Out (1) *   06.15.2022     Furnace set 6/1
-- -- Plumbing Trim Out (2) *   06.05.2022     Black Standard
-- -- Install Appliances (0) *   06.08.2022    
-- -- Paint 3 (2) *   06.12.2022    
-- -- Carpet (2)  06.25.2022    
-- -- Inspection (Final HVAC) (0)  02.14.2023    
-- -- Inspection (Final Plumbing) (0)  02.14.2023    
-- -- Inspection (Final Electric) (0)  02.14.2023    
-- -- Inspection (Final Building) (4) *   07.05.2022     Fri, July 1
-- -- Pre Walk Through (0)  07.05.2022    
-- -- Stain Hardwood Stairs (1) *   06.29.2022    
-- -- Certificate of Occupancy (1) *   07.06.2022    
-- -- Schedule Closing (0)  07.07.2022     Tue, June 12
-- -- Buyer Walk Through (1) *   07.13.2022     Mon, July 11 confirmed for 2:00 PM
-- -- Payment for Upgrades (0)  06.30.2022    
-- -- Keys to Settlement Agent (0)  06.28.2022    
-- -- Review Settlement Statement (0)  07.08.2022    
-- -- Jerry Signs Closing Documents (0)  06.30.2022     Wednesday, June 29, 1:00 PM
-- -- Request Trash Tote From POA Manager (0)  06.28.2022    
-- -- Closing (1)  07.13.2022     Brittany @ West View Title (June 12)
-- -- Remove Coded Lockbox (0)  08.29.2022