Tue |
Jul 1 |
Verify Window & Roof Structure (0) |
|
|
Tue |
Jul 1 |
Rough In Microwave Vent (0) |
|
|
Tue |
Jul 1 |
Order Plumbing / Lighting Fixtures (0) |
|
|
Tue |
Jul 1 |
Blower Door Test (1) |
|
|
|
-- |
-- |
Set forms 12/26 |
|
|
-- |
-- |
Drywall garage hole? |
Needs sanding 5/30 |
|
-- |
-- |
Pedestal sink powder bath needs put together. |
|
|
-- |
-- |
Secure toe kick under cabinets/island in the kitchen |
|
|
-- |
-- |
Powder Bathroom outlet by sink- receptacle uneven out of wall |
Electrician |
|
-- |
-- |
Drywall corners tray ceiling |
Drywaller |
|
-- |
-- |
Drywall hole above escutcheon master toilet |
Drywaller |
|
-- |
-- |
Drywall hole- light switch top of first set of steps |
Drywaller |
|
-- |
-- |
Needs overall paint touch up 7/13 |
|
|
-- |
-- |
CODED LOCKBOX 7777 |
|
|
-- |
-- |
Gutter repairs |
Tom |
|
-- |
-- |
Paint front door trim |
Jill |
|
-- |
-- |
Clean out garage/bonus room |
before mondays walkthrough |
|
-- |
-- |
Hot water pipe needs extending |
Plumber |
|
-- |
-- |
Few bulbs missing |
Jill |
|
-- |
-- |
Mailbox numbers 6-10 |
|
|
-- |
-- |
|
|
|
-- |
-- |
Small spot kitchen ceiling 7/24 |
Needs sanding/painted - Painter |
|
-- |
-- |
Staining in master shower? |
And hall bath - Jill |
|
-- |
-- |
Raise dining chandelier |
Electrician |
|
-- |
-- |
New ski for notched out island panel |
|
|
-- |
-- |
Sand and paint drywall mud in kitchen ceiling above refrigerator |
Painter |
|
-- |
-- |
Paint around pendant lights in kitchen |
Painter |
|
-- |
-- |
Powder bath paint touchups and powder bath ceiling around Fan |
Painter |
|
-- |
-- |
Phil drywall hole above master bath toilet escutcheon |
Painter |
|
-- |
-- |
Laundry room fix drywall and caulk around dryer vent and paint touch up behind laundry room door |
Painter |
|
-- |
-- |
Caulk around the base of all toilets |
Painter |
|
-- |
-- |
Take screws out of attic access cover |
Jill |
|
-- |
-- |
Paint trim around attic access |
Painter |
|
-- |
-- |
New skin for notched out island panel |
Kate will ask Kimberly to order it (6-8 weeks) |
|
-- |
-- |
Smoke detector beeps |
Tom |
|
-- |
-- |
Siding issues outside |
siding - same issues at Lot 6 |
|
-- |
-- |
Ratified Contract? (0) 11.21.2021 |
|
|
|
|
Amendment to increase price by $4,400
|
|
-- |
-- |
$2500 Deposit Received (0) 11.21.2021 |
|
|
-- |
-- |
Association Packet Requested (0) 11.21.2021 |
|
|
-- |
-- |
Association Packet Received (0) 11.21.2021 |
|
|
-- |
-- |
Selections Meeting (0) 12.07.2021 |
|
|
-- |
-- |
Selections Sheet Signed (0) 12.09.2021 |
12/7/2021: Sent to Mattias for buyer signatures |
|
-- |
-- |
Amendment for Upgrades (B,S,L,T,BCP) (0) 12.17.2021 |
12/16/2021: sent to Jerry for signature |
|
-- |
-- |
Deposit For Upgrades Received (0) 12.16.2021 |
12/8/2021: waiting on deposit check from buyer |
|
-- |
-- |
Building Permit (30) 11.11.2021 |
|
|
-- |
-- |
Order Roof & Floor Trusses (1) 11.11.2021 |
|
|
-- |
-- |
Order Windows & Doors (0) 11.11.2021 |
|
|
-- |
-- |
Stake Out Home (1) 12.09.2021 |
|
|
-- |
-- |
Excavate (2) 12.09.2021 |
|
|
-- |
-- |
Inspection (Footers) (1) 12.14.2021 |
|
|
-- |
-- |
Inspection (Concrete Wall) (1) 02.14.2023 |
|
|
-- |
-- |
Pour Footers (1) * 12.14.2021 |
|
|
-- |
-- |
Set Forms (2) 01.03.2022 |
In process 12/26 |
|
-- |
-- |
Pour Foundation Walls (1) 01.03.2022 |
|
|
-- |
-- |
Plumb Slab (2) 01.17.2022 |
|
|
-- |
-- |
Inspection (Plumbing Under Slab) (1) 01.31.2022 |
|
|
-- |
-- |
Inspection (Conduit Under Slab) (1) 02.14.2023 |
|
|
-- |
-- |
Prepare Slab (1) 02.03.2022 |
|
|
-- |
-- |
Inspection (Slab) (1) 02.03.2022 |
|
|
-- |
-- |
Inspection (Drain Tile) (0) 02.14.2023 |
|
|
-- |
-- |
Pour Slab (1) * 02.10.2022 |
needs garage poured 2/2 |
|
-- |
-- |
Settlement Agent Confirmed (0) 04.27.2022 |
|
|
-- |
-- |
Framing I (9) 02.24.2022 |
|
|
-- |
-- |
Order Steps (0) 03.10.2022 |
|
|
-- |
-- |
Order Tubs / Showers (0) 03.30.2022 |
|
|
-- |
-- |
Framing II (8) 03.07.2022 |
|
|
-- |
-- |
Framing III (8) * 03.13.2022 |
|
|
-- |
-- |
Install Stairs (0) 03.10.2022 |
|
|
-- |
-- |
Windows & Doors (0) * 03.30.2022 |
|
|
-- |
-- |
House Number and Status in Window (0) 04.24.2022 |
|
|
-- |
-- |
Roofing (0) * 03.30.2022 |
|
|
-- |
-- |
Order Cabinets (0) 01.31.2022 |
|
|
-- |
-- |
Order Appliances (0) 05.16.2022 |
Standard |
|
-- |
-- |
Deck (0) 04.23.2022 |
n/a |
|
-- |
-- |
Gutters (0) 06.08.2022 |
|
|
-- |
-- |
Driveway (0) * 07.05.2022 |
Expanded Driveway |
|
|
|
Expanded Driveway
|
|
-- |
-- |
Patio (0) 02.14.2023 |
|
|
-- |
-- |
Privacy Divider / Fence (0) 07.05.2022 |
|
|
-- |
-- |
Sod / Seed / Landscaping (0) 07.14.2022 |
|
|
-- |
-- |
HVAC Rough In (4) 03.30.2022 |
|
|
-- |
-- |
Inspection (Rough In HVAC) (1) 04.20.2022 |
4/14 |
|
-- |
-- |
Plumbing Rough In (4) 04.07.2022 |
|
|
-- |
-- |
Inspection (Rough In Plumbing) (1) 02.14.2023 |
|
|
-- |
-- |
Electric Rough In (4) 04.14.2022 |
In process 4/13 |
|
-- |
-- |
Inspection (Rough In Electric) (1) 02.14.2023 |
|
|
-- |
-- |
Inspection (Deck Piers) (0) 02.14.2023 |
|
|
-- |
-- |
Inspection (Framing) (1) * 02.14.2023 |
|
|
-- |
-- |
Exterior Vinyl (0) * 06.05.2022 |
|
|
-- |
-- |
Exterior Stone (0) 04.14.2022 |
|
|
-- |
-- |
Insulation (2) * 04.20.2022 |
|
|
-- |
-- |
Inspection (Insulation) (1) 04.21.2022 |
|
|
-- |
-- |
Inspection (Electric Service) (0) 06.30.2022 |
|
|
-- |
-- |
Set Electric Meter (0) * 04.11.2023 |
|
|
-- |
-- |
Inspection (Main Sewer Line) (0) 05.12.2022 |
|
|
-- |
-- |
Inspection (Main Water Line) (0) 02.14.2023 |
|
|
-- |
-- |
Order Interior Doors & Trim (0) 05.02.2022 |
|
|
-- |
-- |
Drywall (Hang) (4) * 04.27.2022 |
In process. Almost complete 4/24 |
|
-- |
-- |
Loan Approval (0) 06.30.2022 |
|
|
-- |
-- |
Deed Preparation (0) 04.27.2022 |
|
|
-- |
-- |
Drywall (Tape, Block, Skim, Sand) (6) * 05.02.2022 |
In process 5/1 |
|
-- |
-- |
Paint 1 (1) 05.04.2022 |
|
|
-- |
-- |
Garage Door (0) * 06.29.2022 |
|
|
-- |
-- |
House Numbers (0) 07.11.2022 |
|
|
-- |
-- |
Mailbox (0) 07.17.2022 |
|
|
-- |
-- |
Cabinet Installation (2) * 05.08.2022 |
5/5 |
|
-- |
-- |
Granite Installation (1) * 05.15.2022 |
|
|
-- |
-- |
Interior Trim - Install (3) * 05.18.2022 |
Completed. Needs painted. 5/15 |
|
-- |
-- |
Interior Trim - Paint (1) 02.14.2023 |
|
|
-- |
-- |
Luxury Vinyl Plank (3) * 06.12.2022 |
In process 6/8 |
|
-- |
-- |
Luxury Vinyl Tile (0) 06.08.2022 |
In process 6/5 |
|
-- |
-- |
Paint 2 (3) 06.18.2022 |
|
|
-- |
-- |
Cover Floors (1) 06.18.2022 |
|
|
-- |
-- |
Deliver Plumbing / Lighting Fixtures (0) 06.29.2022 |
|
|
-- |
-- |
Shoe Moulding (0) 06.25.2022 |
On site 6/19 |
|
-- |
-- |
Shelving, Door Knobs, Fire Extinguisher (0) * 07.10.2022 |
Brushed Nickel accessories |
|
-- |
-- |
Install Coded Lockbox (add extra keys) (0) 07.13.2022 |
|
|
-- |
-- |
Pay Water / Sewer Taps (0) 06.16.2022 |
|
|
-- |
-- |
Set Water Meter (0) * 07.21.2022 |
|
|
-- |
-- |
Electric Trim Out (3) 07.17.2022 |
Brushed Nickel. In process. 7/13. Almost complete. |
|
-- |
-- |
Ceiling Fans (0) 06.30.2022 |
|
|
-- |
-- |
HVAC Trim Out (1) 07.10.2022 |
|
|
-- |
-- |
Plumbing Trim Out (2) 06.25.2022 |
Brushed Nickel Standard |
|
-- |
-- |
Install Appliances (0) * 07.13.2022 |
Standard SS. On site 6/18 |
|
-- |
-- |
Paint 3 (2) * 06.25.2022 |
|
|
|
|
Painted Pine Steps
|
|
-- |
-- |
Carpet (2) 06.18.2022 |
|
|
-- |
-- |
Appraiser Confirms Construction Completion (0) 08.04.2022 |
|
|
-- |
-- |
Inspection (Final HVAC) (1) 02.14.2023 |
|
|
-- |
-- |
Inspection (Final Plumbing) (1) 02.14.2023 |
|
|
-- |
-- |
Inspection (Final Electric) (1) 02.14.2023 |
|
|
-- |
-- |
Inspection (Final Building) (2) * 07.25.2022 |
July 21 |
|
-- |
-- |
Pre Walk Through (0) 07.24.2022 |
|
|
-- |
-- |
Stain Hardwood Stairs (1) 07.21.2022 |
In process 7/17 |
|
-- |
-- |
Cleaning (1) 07.24.2022 |
almost completed 7/21 |
|
-- |
-- |
Certificate of Occupancy (1) * 07.25.2022 |
|
|
-- |
-- |
C.O. to Lender (0) 07.25.2022 |
|
|
-- |
-- |
Schedule Closing (0) 08.04.2022 |
|
|
-- |
-- |
Buyer Walk Through (1) 07.25.2022 |
Monday July 25 8am |
|
-- |
-- |
Payment for Upgrades (0) 07.22.2022 |
|
|
-- |
-- |
Keys to Settlement Agent (0) 07.22.2022 |
|
|
-- |
-- |
Review Settlement Statement (0) 08.04.2022 |
|
|
-- |
-- |
Jerry Signs Closing Documents (0) 07.26.2022 |
|
|
-- |
-- |
Request Trash Tote From POA Manager (0) 08.03.2022 |
|
|
-- |
-- |
Closing (1) 08.04.2022 |
Brittany @ West View Title |
|
-- |
-- |
Remove Coded Lockbox (0) 08.18.2022 |
|
|