Fri |
Sep 20 |
Verify Window & Roof Structure (0)
|
|
|
Fri |
Sep 20 |
Rough In Microwave Vent (0)
|
|
|
Fri |
Sep 20 |
Order Plumbing / Lighting Fixtures (0)
|
|
|
Fri |
Sep 20 |
Blower Door Test (1)
|
|
|
|
-- |
-- |
Loan Officer = Jeanne Seils, SECU, Jeanne.seils@secumd.com |
|
|
-- |
-- |
Cover hardwood treads |
|
|
-- |
-- |
Door repair to master bath |
Drywaller |
|
-- |
-- |
Missing shower panel |
Mon, Aug 15 |
|
-- |
-- |
Drywall patch above garage door |
|
|
-- |
-- |
Shower door on site 8/14 |
Mon, Aug 22 |
|
-- |
-- |
Install shelving under stairs closet |
|
|
-- |
-- |
CODED LOCKBOX 0126 |
|
|
-- |
-- |
Coffee stain on granite |
owner cleared it off |
|
-- |
-- |
Attic cover needs installed |
Painter |
|
-- |
-- |
Install screw covers French doors |
Jill |
|
-- |
-- |
Install screw covers French doors |
|
|
-- |
-- |
Finish installing pantry shelving |
Tues, Aug 23 |
|
-- |
-- |
Powder bathroom toilet won’t flush. And it’s filled with P |
Tom-still wont flush 8/24 |
|
-- |
-- |
Wonky receptacle in powder bath by pedestal sink |
Electrician |
|
-- |
-- |
Master bedroom tray ceiling drywall touch up and sanding |
Painter |
|
-- |
-- |
Caught in between shower walls and trim near toilet in master bath |
Caulk - Painter |
|
-- |
-- |
Steps here have streaking-painters beware |
Sand and paint risers |
|
-- |
-- |
Paint touch ups |
Painter. In process 8/24 |
|
-- |
-- |
Final pantry shelving installation |
|
|
-- |
-- |
Cable cover LR needed |
2 - electrician |
|
-- |
-- |
Trim needed in garage after clean out |
|
|
-- |
-- |
Extra side splash pieces in kitchen |
|
|
-- |
-- |
Master shelving needs completed |
|
|
-- |
-- |
Clean off deck |
|
|
-- |
-- |
Caulk corner of master shower |
Painter |
|
-- |
-- |
Screens |
Jill on site just need installed 8/31 |
|
-- |
-- |
Repaint garage |
|
|
-- |
-- |
Pint touch up |
|
|
-- |
-- |
Install screens |
|
|
-- |
-- |
clean around windows |
|
|
-- |
-- |
Adjust water pressure |
Jill |
|
-- |
-- |
adjust closet doors |
I think ok 9/4? |
|
-- |
-- |
Robe hooks upstairs baths |
Just Master Bath 9/4 |
|
-- |
-- |
wash off deck |
|
|
-- |
-- |
Secure carpet at top of stairs (look at subfloor) |
Denny-i think repaired 9/4? |
|
-- |
-- |
Adjust French door |
Tom-basement door deadbolt |
|
-- |
-- |
Chip in cabinet door above fridge |
Jill |
|
-- |
-- |
powder bath toilet slow flush |
Plumber-toilet is still odd 9/4 |
|
-- |
-- |
water not working in fridger |
CJ |
|
-- |
-- |
Paint garage walls |
|
|
-- |
-- |
weather stripping garage door |
Jill |
|
-- |
-- |
remove stickers from upstairs windows |
Tom |
|
-- |
-- |
Top nosing of first set of steps need replaced |
waiting to hear from the buyers |
|
-- |
-- |
Ratified Contract? (0)
11.21.2021 |
|
|
-- |
-- |
$2500 Deposit Received (0)
11.21.2021 |
|
|
-- |
-- |
Association Packet Requested (0)
11.21.2021 |
|
|
-- |
-- |
Association Packet Received (0)
11.21.2021 |
|
|
-- |
-- |
Selections Meeting (0)
12.07.2021 |
|
|
-- |
-- |
Selections Sheet Signed (0)
12.08.2021 |
12/7/2021: sent to Serge for buyer signature |
|
-- |
-- |
Amendment for Upgrades (B,S,L,T,BCP) (0)
06.02.2022 |
12/11/2021: waiting on signature from Jerry |
|
-- |
-- |
Deposit For Upgrades Received (0)
12.11.2021 |
12/8/2021: waiting on deposit check from buyers |
|
-- |
-- |
Building Permit (30)
01.10.2022 |
|
|
-- |
-- |
Order Roof & Floor Trusses (1)
03.31.2022 |
|
|
-- |
-- |
Order Windows & Doors (0)
03.31.2022 |
|
|
-- |
-- |
Stake Out Home (1)
12.14.2021 |
|
|
-- |
-- |
Excavate (2)
01.17.2022 |
|
|
-- |
-- |
Inspection (Footers) (1)
01.17.2022 |
|
|
-- |
-- |
Inspection (Concrete Wall) (1)
09.07.2022 |
|
|
-- |
-- |
Pour Footers (1)
01.17.2022 |
|
|
-- |
-- |
Set Forms (2)
02.10.2022 |
|
|
-- |
-- |
Pour Foundation Walls (1)
02.10.2022 |
|
|
-- |
-- |
Plumb Slab (2)
02.24.2022 |
|
|
-- |
-- |
Inspection (Plumbing Under Slab) (1)
03.13.2022 |
|
|
-- |
-- |
Inspection (Conduit Under Slab) (1)
09.07.2022 |
|
|
-- |
-- |
Prepare Slab (1)
03.13.2022 |
|
|
-- |
-- |
Inspection (Slab) (1)
03.13.2022 |
|
|
-- |
-- |
Inspection (Drain Tile) (0)
09.07.2022 |
|
|
-- |
-- |
Pour Slab (1)
03.13.2022 |
|
|
-- |
-- |
Settlement Agent Confirmed (0)
04.27.2022 |
Sara at West View Title |
|
-- |
-- |
Framing I (9)
03.24.2022 |
|
|
-- |
-- |
Order Steps (0)
04.11.2022 |
|
|
-- |
-- |
Order Tubs / Showers (0)
04.28.2022 |
ONYX SHOWER WALLS |
|
-- |
-- |
Framing II (8)
03.31.2022 |
|
|
-- |
-- |
Framing III (8)
04.04.2022 |
|
|
-- |
-- |
Install Stairs (0)
04.11.2022 |
|
|
-- |
-- |
Windows & Doors (0)
05.19.2022 |
|
|
-- |
-- |
House Number and Status in Window (0)
05.30.2022 |
|
|
-- |
-- |
Roofing (0)
05.02.2022 |
|
|
-- |
-- |
Order Cabinets (0)
01.31.2022 |
|
|
-- |
-- |
Order Appliances (0)
05.16.2022 |
Standard |
|
-- |
-- |
Deck (0)
05.30.2022 |
Expanded Deck 12 x 12 |
|
-- |
-- |
Gutters (0)
07.03.2022 |
|
|
-- |
-- |
Driveway (0)
07.23.2022 |
Expanded Driveway |
|
-- |
-- |
Patio (0)
02.14.2023 |
|
|
-- |
-- |
Privacy Divider / Fence (0)
08.20.2022 |
|
|
-- |
-- |
Sod / Seed / Landscaping (0)
08.28.2022 |
|
|
-- |
-- |
HVAC Rough In (4)
04.27.2022 |
In process4/20 |
|
-- |
-- |
Inspection (Rough In HVAC) (1)
05.21.2022 |
|
|
-- |
-- |
Plumbing Rough In (4)
05.11.2022 |
In process 5/8 |
|
-- |
-- |
Inspection (Rough In Plumbing) (1)
09.07.2022 |
|
|
-- |
-- |
Electric Rough In (4)
05.19.2022 |
In process 5/18 |
|
-- |
-- |
Inspection (Rough In Electric) (1)
09.07.2022 |
|
|
-- |
-- |
Inspection (Deck Piers) (0)
09.07.2022 |
|
|
-- |
-- |
Inspection (Framing) (1)
09.07.2022 |
|
|
-- |
-- |
Exterior Vinyl (0)
06.25.2022 |
|
|
-- |
-- |
Exterior Stone (0)
04.14.2022 |
|
|
-- |
-- |
Insulation (2)
05.21.2022 |
|
|
-- |
-- |
Inspection (Insulation) (1)
05.25.2022 |
5/24 |
|
-- |
-- |
Inspection (Electric Service) (0)
07.25.2022 |
|
|
-- |
-- |
Set Electric Meter (0)
04.11.2023 |
|
|
-- |
-- |
Inspection (Main Sewer Line) (0)
03.13.2022 |
|
|
-- |
-- |
Inspection (Main Water Line) (0)
09.07.2022 |
|
|
-- |
-- |
Order Interior Doors & Trim (0)
05.16.2022 |
|
|
-- |
-- |
Drywall (Hang) (4)
05.30.2022 |
|
|
-- |
-- |
Loan Approval (0)
12.27.2021 |
|
|
-- |
-- |
Deed Preparation (0)
04.27.2022 |
|
|
-- |
-- |
Drywall (Tape, Block, Skim, Sand) (6)
06.12.2022 |
In process6/5 |
|
-- |
-- |
Paint 1 (1)
06.18.2022 |
|
|
-- |
-- |
Garage Door (0)
07.03.2022 |
|
|
-- |
-- |
House Numbers (0)
07.16.2022 |
|
|
-- |
-- |
Mailbox (0)
08.11.2022 |
|
|
-- |
-- |
Cabinet Installation (2)
06.25.2022 |
|
|
-- |
-- |
Granite Installation (1)
08.03.2022 |
Tue, Jul 26. Partially installed 7/27 |
|
-- |
-- |
Interior Trim - Install (3)
07.16.2022 |
Needs painting 7/13 |
|
-- |
-- |
Interior Trim - Paint (1)
02.14.2023 |
|
|
-- |
-- |
Luxury Vinyl Plank (3)
08.03.2022 |
|
|
-- |
-- |
Luxury Vinyl Tile (0)
08.03.2022 |
In process 7/31 |
|
-- |
-- |
Paint 2 (3)
07.31.2022 |
|
|
-- |
-- |
Cover Floors (1)
08.07.2022 |
|
|
-- |
-- |
Deliver Plumbing / Lighting Fixtures (0)
07.28.2022 |
|
|
-- |
-- |
Shoe Moulding (0)
08.10.2022 |
|
|
-- |
-- |
Shelving, Door Knobs, Fire Extinguisher (0)
08.14.2022 |
Black accessories, shower door black trim. In process 8/10 |
|
-- |
-- |
Install Coded Lockbox (add extra keys) (0)
08.15.2022 |
|
|
-- |
-- |
Pay Water / Sewer Taps (0)
07.28.2022 |
|
|
-- |
-- |
Set Water Meter (0)
08.04.2022 |
|
|
-- |
-- |
Electric Trim Out (3)
08.14.2022 |
Black Lighting. In process 8/10 |
|
-- |
-- |
Ceiling Fans (0)
08.10.2022 |
|
|
-- |
-- |
HVAC Trim Out (1)
08.10.2022 |
Heat Pump Set 7/10 |
|
-- |
-- |
Plumbing Trim Out (2)
08.10.2022 |
Black Standard. In process 8/7 |
|
-- |
-- |
Install Appliances (0)
08.14.2022 |
|
|
-- |
-- |
Paint 3 (2)
07.31.2022 |
|
|
-- |
-- |
Carpet (2)
08.24.2022 |
|
|
-- |
-- |
Appraiser Confirms Construction Completion (0)
09.15.2022 |
Tell Shawanna when to submit the request |
|
-- |
-- |
Inspection (Final HVAC) (1)
09.07.2022 |
|
|
-- |
-- |
Inspection (Final Plumbing) (1)
09.07.2022 |
|
|
-- |
-- |
Inspection (Final Electric) (1)
09.07.2022 |
|
|
-- |
-- |
Inspection (Final Building) (2)
08.26.2022 |
Reinspect 8/25 |
|
-- |
-- |
Pre Walk Through (0)
08.22.2022 |
|
|
-- |
-- |
Stain Hardwood Stairs (1)
08.28.2022 |
|
|
-- |
-- |
Cleaning (1)
08.31.2022 |
|
|
-- |
-- |
Certificate of Occupancy (1)
08.27.2022 |
|
|
-- |
-- |
C.O. to Lender (0)
08.27.2022 |
|
|
-- |
-- |
Schedule Closing (0)
09.15.2022 |
|
|
-- |
-- |
Buyer Walk Through (1)
09.01.2022 |
Tuesday, Aug 30-Wednesday |
|
-- |
-- |
Payment for Upgrades (0)
08.19.2022 |
|
|
-- |
-- |
Keys to Settlement Agent (0)
08.19.2022 |
|
|
-- |
-- |
Review Settlement Statement (0)
09.15.2022 |
|
|
-- |
-- |
Jerry Signs Closing Documents (0)
09.03.2022 |
|
|
-- |
-- |
Request Trash Tote From POA Manager (0)
08.11.2022 |
|
|
-- |
-- |
Closing (1)
09.15.2022 |
Brittany @ West View Title, Sep 14? |
|
-- |
-- |
Remove Coded Lockbox (0)
09.15.2022 |
|
|