37 ADDR
CONGERS-2 - 11  ::  1356 Palomino Trail
[ BUILD: 20220058 ]      
CRITICAL PATH   |   INSPECTIONS   |   FLOOR PLANS   |   SELECTIONS   |   SPECS   |   CHANGES   |   NHS
view photo archive
 
TO DO
---
UPGRADES
    Luxury Vinyl Plank in Upstairs Hallway and Bedrooms  
    Luxury Vinyl Plank in Bonus Room Behind Garage  
CRITICAL PATH
---
TO DO - COMPLETED OR DELETED
UPGRADES - COMPLETED
    Expanded Driveway  
    Egress Window in Basement Bonus Room  
    Finished Bonus Room Behind Garage  
    Finished Full Bathroom in Bonus Room  
    Stained Hardwood Treads to Bedroom Level  
    Amendment to increase price by $23,650  
CRITICAL PATH - COMPLETED
-- -- Inspection (Footers) (1)  03.07.2022    
-- -- Inspection (Concrete Wall) (1)  09.07.2022    
-- -- Inspection (Plumbing Under Slab) (1)  04.21.2022    
-- -- Inspection (Conduit Under Slab) (1)  09.07.2022    
-- -- Inspection (Slab) (1)  05.02.2022    
-- -- Inspection (Drain Tile) (0)  09.07.2022    
-- -- Inspection (Rough In HVAC) (1)  07.27.2022     7/21
-- -- Inspection (Rough In Plumbing) (1)  09.07.2022    
-- -- Inspection (Rough In Electric) (1)  09.07.2022    
-- -- Inspection (Framing) (1) *   09.07.2022    
-- -- Inspection (Deck Piers) (0)  09.07.2022    
-- -- Inspection (Insulation) (1)  07.28.2022    
-- -- Inspection (Electric Service) (0)  10.02.2022    
-- -- Inspection (Main Sewer Line) (0)  05.12.2022    
-- -- Inspection (Main Water Line) (0)  09.08.2022    
-- -- Inspection (Final HVAC) (0)  10.27.2022    
-- -- Inspection (Final Plumbing) (0)  10.27.2022    
-- -- Inspection (Final Electric) (0)  10.27.2022    
-- -- Inspection (Final Building) (4) *   10.31.2022     Reinspect, 10/28