| TO DO | ||||
| --- | ||||
| UPGRADES | ||||
| --- | ||||
| CRITICAL PATH | ||||
| --- | ||||
| TO DO - COMPLETED OR DELETED | ||||
| UPGRADES - COMPLETED | ||||
| White Painted Kitchen Cabinetry | ||||
| Level III Quartz Countertop in Kitchen | ||||
| French Model Refrigerator | ||||
| Painted Stairs to bedroom level | ||||
| Expanded Driveway | ||||
| Luxury Vinyl Plank - Upper Level Hallway and Bedrooms | ||||
| Stack of three drawers (36") | ||||
| Amendment to increase price by $9,290 | ||||
| CRITICAL PATH - COMPLETED | ||||
| -- | -- | Inspection (Footers) (1) 03.07.2022 | ||
| -- | -- | Inspection (Concrete Wall) (1) 09.07.2022 | ||
| -- | -- | Inspection (Plumbing Under Slab) (1) 04.21.2022 | ||
| -- | -- | Inspection (Conduit Under Slab) (1) 09.07.2022 | ||
| -- | -- | Inspection (Slab) (1) 05.02.2022 | ||
| -- | -- | Inspection (Drain Tile) (0) 09.07.2022 | ||
| -- | -- | Inspection (Rough In HVAC) (1) 08.07.2022 | ||
| -- | -- | Inspection (Rough In Plumbing) (1) 09.07.2022 | ||
| -- | -- | Inspection (Rough In Electric) (1) 09.07.2022 | ||
| -- | -- | Inspection (Framing) (1) * 09.07.2022 | ||
| -- | -- | Inspection (Deck Piers) (0) 09.07.2022 | ||
| -- | -- | Inspection (Insulation) (1) 08.14.2022 | ||
| -- | -- | Inspection (Electric Service) (0) 09.29.2022 | ||
| -- | -- | Inspection (Main Sewer Line) (0) 05.12.2022 | ||
| -- | -- | Inspection (Main Water Line) (0) 09.08.2022 | ||
| -- | -- | Inspection (Final HVAC) (0) 10.24.2022 | ||
| -- | -- | Inspection (Final Plumbing) (0) 10.24.2022 | ||
| -- | -- | Inspection (Final Electric) (0) 10.24.2022 | ||
| -- | -- | Inspection (Final Building) (4) * 10.25.2022 | Mon, Oct 24 | |