1 33 37 89 47 73 67 55 56 59 57 66 65 64 60 61 62 63 ADDR
CONGERS-2 - 16  ::  1376 Palomino Trail
[ BUILD: 20220063 ]      
CRITICAL PATH   |   INSPECTIONS   |   FLOOR PLANS   |   SELECTIONS   |   SPECS   |   CHANGES   |   NHS
view photo archive
 
--   --   Sizing issue of kitchen island 9/17
--   --   Install side splash MB counter Tom
--   --   Wrong window sash upstairs bedroom Tom
--   --   Drywall repair needed by front door Drywaller - to sand
--   --   Rate lock expires Nov 17
--   --   Bonus room light looks small Electrician
--   --   Push dishwasher into place & hook up (cabinet guy will fix)
--   --   POWDER bath mirror needed
--   --   Need all mirrors and shower rods Shower rod in. Need all mirrors 11/2
--   --   Touch up light switch and front door frame Drywaller
--   --   Trim garage Edgar
--   --   Utility room needs a door Edgar - Tom
--   --   Move garage door opener to inside of garage Davenport
--   --   Home Inspection, Wednesday, November 2
--   --   Touch up shoe molding Painter
--   --   Attic cover Painter
--   --   HVAC vent needed in kitchen
--   --   Keys?
--   --   screw covers in French door and front door Jill
--   --   drywall hole- front door switch plate
--   --   drywall hole- hall bath vanity light
--   --   drywall hole- hall bath switch plate
--   --   caulk in front of tubs/showers Painter
--   --   Heat pump iced over Clem on site 11/7
--   --   Siding in contact with the ground Greg
--   --   Paint exterior trim
--   --   Plumbing line leaking at kitchen sink
--   --   Corner trim missing at kitchen island Tom will coordinate. Trim is in foyer-needs installed 11/9
--   --   Paint touch up Painter
--   --   Replace trim around laundry valves Tom
--   --   Add silicone at stove top CJ
--   --   Cracks in three tubs Jill contact Kevin
--   --   Caulk in front of shoe mould in front of tubs Painter
--   --   Light bulb in guest bathroom Jill
--   --   Repair back of island (screw, putty) Jill
--   --   Caulk around dryer vent cover on wall Painter
--   --   Final cleaning
--   --   Remove ladder, etc.
--   --   Wants the gift basket :-) Kate
-- -- Ratified Contract? (0)  12.04.2021    
-- -- $2500 Deposit Received (0)  12.08.2021     12/4/2021: waiting on the buyer to drop off the check
-- -- Association Packet Requested (0)  12.08.2021     12/4/2021: requested from Kayleigh
-- -- Association Packet Received (0)  12.09.2021    
-- -- Selections Meeting (0)  12.14.2021    
-- -- Selections Sheet Signed (0)  12.14.2021     12/13/2021: sent to Brad for buyer signatures
-- -- Amendment for Upgrades (B,S,L,T,BCP) (0)  12.21.2021     12/20/2021: sent to Jerry for signature
-- -- Deposit For Upgrades Received (0)  12.20.2021    
-- -- Building Permit (30)  01.12.2022    
-- -- Order Roof & Floor Trusses (1)  05.02.2022    
-- -- Order Windows & Doors (0)  05.02.2022    
-- -- Stake Out Home (1)  02.24.2022    
-- -- Excavate (2)  03.07.2022    
-- -- Inspection (Footers) (1)  03.07.2022    
-- -- Inspection (Concrete Wall) (1)  09.07.2022    
-- -- Pour Footers (1)  03.07.2022    
-- -- Set Forms (2)  03.28.2022    
-- -- Pour Foundation Walls (1)  03.28.2022    
-- -- Plumb Slab (2)  04.19.2022    
-- -- Inspection (Plumbing Under Slab) (1)  04.21.2022    
-- -- Inspection (Conduit Under Slab) (1)  09.07.2022    
-- -- Prepare Slab (1)  04.25.2022    
-- -- Inspection (Slab) (1)  05.02.2022    
-- -- Inspection (Drain Tile) (0)  09.07.2022    
-- -- Pour Slab (1) *   05.12.2022    
-- -- Settlement Agent Confirmed (0)  01.07.2022    
-- -- Framing I (9)  05.26.2022    
-- -- Order Steps (0)  06.18.2022    
-- -- Order Tubs / Showers (0)  06.20.2022    
-- -- Framing II (8)  06.02.2022    
-- -- Framing III (8) *   06.05.2022    
-- -- Verify Window & Roof Structure (0)  08.12.2024    
-- -- Install Stairs (0)  06.25.2022    
-- -- Windows & Doors (0)  06.25.2022    
-- -- House Number and Status in Window (0)  07.07.2022    
-- -- Roofing (0)  07.17.2022    
-- -- Order Cabinets (0)  07.11.2022    
-- -- Order Appliances (0)  08.30.2022     Standard
-- -- Deck (0)  04.23.2022     n/a
-- -- Gutters (0)  10.05.2022    
-- -- Driveway (0)  09.17.2022     Expanded Driveway
-- -- Patio (0)  10.11.2022    
-- -- Privacy Divider / Fence (0)  09.17.2022    
-- -- Sod / Seed / Landscaping (0)  10.19.2022    
-- -- HVAC Rough In (4)  07.03.2022     In process 6/29
-- -- Inspection (Rough In HVAC) (1)  08.17.2022    
-- -- Rough In Microwave Vent (0)  08.12.2024    
-- -- Plumbing Rough In (4)  08.03.2022     In process 7/31
-- -- Inspection (Rough In Plumbing) (1)  09.07.2022    
-- -- Electric Rough In (4)  08.10.2022    
-- -- Inspection (Rough In Electric) (1)  09.07.2022    
-- -- Inspection (Deck Piers) (0)  09.07.2022    
-- -- Inspection (Framing) (1)  09.07.2022    
-- -- Exterior Vinyl (0) *   09.11.2022     in process 8/31
-- -- Exterior Stone (0)  10.02.2022     In process 9/21
-- -- Insulation (2)  08.17.2022    
-- -- Inspection (Insulation) (1)  08.18.2022    
-- -- Inspection (Electric Service) (0)  09.29.2022    
-- -- Set Electric Meter (0)  04.11.2023    
-- -- Inspection (Main Sewer Line) (0)  05.12.2022    
-- -- Inspection (Main Water Line) (0)  09.08.2022    
-- -- Order Interior Doors & Trim (0)  08.04.2022    
-- -- Drywall (Hang) (4) *   08.24.2022     Finish Bonus Room, Bath. Stocked 8/20
-- -- Loan Approval (0)  02.15.2022     2/14/2022
-- -- Deed Preparation (0)  10.25.2022    
-- -- Drywall (Tape, Block, Skim, Sand) (6) *   09.14.2022     In process 9/11
-- -- Paint 1 (1)  09.14.2022    
-- -- Garage Door (0)  10.05.2022    
-- -- House Numbers (0)  10.02.2022    
-- -- Mailbox (0)  09.29.2022    
-- -- Cabinet Installation (2) *   09.17.2022     Delivery 9/13. On site 9/14
-- -- Granite Installation (1) *   09.26.2022     Partially complete 9/17
-- -- Interior Trim - Install (3)  10.08.2022     In process 10/5 needs painting.
-- -- Order Plumbing / Lighting Fixtures (0)  08.12.2024    
-- -- Interior Trim - Paint (1)  10.26.2022    
-- -- Luxury Vinyl Plank (3) *   10.22.2022     In process 10/19
-- -- Luxury Vinyl Tile (0)  10.19.2022    
-- -- Paint 2 (3)  10.15.2022    
-- -- Cover Floors (1)  10.29.2022    
-- -- Deliver Plumbing / Lighting Fixtures (0)  09.19.2022    
-- -- Shoe Moulding (0)  10.22.2022    
-- -- Shelving, Door Knobs, Fire Extinguisher (0)  10.29.2022     Black accessories, Bonus bath. In process 10/26
-- -- Install Coded Lockbox (add extra keys) (0)  11.05.2022    
-- -- Pay Water / Sewer Taps (0)  09.19.2022    
-- -- Set Water Meter (0)  09.29.2022    
-- -- Electric Trim Out (3)  10.29.2022     Black Lighting. In process 10/26
-- -- Ceiling Fans (0)  10.26.2022    
-- -- HVAC Trim Out (1)  10.26.2022    
-- -- Blower Door Test (1)  08.12.2024    
-- -- Plumbing Trim Out (2)  10.29.2022     Black Standard. In process 10/26
-- -- Install Appliances (0) *   10.26.2022    
-- -- Paint 3 (2) *   10.15.2022    
-- -- Carpet (2)  10.26.2022    
-- -- Appraiser Confirms Construction Completion (0)  11.05.2022    
-- -- Inspection (Final HVAC) (1)  11.02.2022    
-- -- Inspection (Final Plumbing) (1)  11.05.2022     Reinspection 11/4/22
-- -- Inspection (Final Electric) (1)  11.05.2022     Reinspection 11/3/22
-- -- Inspection (Final Building) (2) *   11.05.2022     Tues, Nov 1reinspect 11/3/22
-- -- Pre Walk Through (0)  11.03.2022    
-- -- Stain Hardwood Stairs (1)  11.07.2022     In process 11/5
-- -- Cleaning (1)  11.07.2022    
-- -- Certificate of Occupancy (1) *   11.05.2022    
-- -- C.O. to Lender (0)  11.05.2022    
-- -- Schedule Closing (0)  11.07.2022    
-- -- Buyer Walk Through (1)  11.07.2022     Monday, November 7, 8:45 AM
-- -- Payment for Upgrades (0)  11.03.2022    
-- -- Keys to Settlement Agent (0)  11.03.2022    
-- -- Review Settlement Statement (0)  11.03.2022    
-- -- Jerry Signs Closing Documents (0)  11.08.2022    
-- -- Request Trash Tote From POA Manager (0)  11.05.2022    
-- -- Closing (1)  11.08.2022     Lisa @ Stewart Title
-- -- Remove Coded Lockbox (0)  11.14.2022