37 ADDR
CONGERS-2 - 120  ::  1369 Palomino Trail
[ BUILD: 20220067 ]      
CRITICAL PATH   |   INSPECTIONS   |   FLOOR PLANS   |   SELECTIONS   |   SPECS   |   CHANGES   |   NHS
view photo archive
 
TO DO
---
UPGRADES
---
CRITICAL PATH
    Verify Window & Roof Structure (0)      
    Rough In Microwave Vent (0)      
    Order Plumbing / Lighting Fixtures (0)      
Tue    Feb 3      Blower Door Test (1)      
TO DO - COMPLETED OR DELETED
Radon Pipe?
Updated Selection Sheet
Updated Amendment
Knot broken out of stair tread TJ - Please fix...
Framing issue basement bathroom Needs drywall repair
Hole needs patched in closet under stairs near kitchen Floor - framer
Powder bath plumbing ok? Is pipe for pedestal sink ready?
Drywall repair garage around electric panel
Garage trim bent
24" Bonus vanity on order- to be installed upon arrival; ( hopefully right before closing) I think installed. Painters told me not to open door
Hall closet door missing trim, needs to be installed
Snap lights installed in bedrooms 9/17 Fans!
Kitchen drawer handle not level New drawer panel is on site, Fred will schedule
Swap out door hinges and handles to brushed nickel
Master sink needs one faucet
Replace snap light w fan in living room 9/24 Electrician
Plumbing trim out faucet when basement vanity arrives ???
Final paint touch up needed 9/30
Kitchen Island Lights need installed 9/30
Patch holes around garage trim Davenport
Needs lots of paint touch up
Clean out garage Jill
Trim bathroom Edgar or Henry
Drywall repair living room ceiling Drywaller, Painter
Cracking on floor in master bedroom. Denny noticed. Bedroom as well. He said carpet may have to be reinstalled to install wedges.
Crack in bedroom door Swap out - Tom
Larger ceiling fan needed in living room Electrician
Trim down utility room door Trim off the bottom of the door - Edgar
Landscaping repairs Pettit
Amendment for fans... Scott
Secure hand rail leading up the second tier of steps
Shelving in master bathroom Hopefully Mon, Oct 10
Install attic access panel Painter. I think panel is in garage
Install living room ceiling fan
Trim down bonus room door Edgar
Silver exterior hardware ok? Leave it!
Caulk side splashes Painter
CODED LOCKBOX 0120
PLEASE TAKE PICTURES OF KITCHEN
Creek in floor at the top of the stairs Tom
Sand ceiling in LR Painter
Tell Scott when kitchen is complete and clean
Shelf i
Shelf under stairs needs installed?
Basement bathtub drain needed Jill
Repaint banister And sand, painter
Get thermostat on?
Paint touch up staircase upstairs Painter
Scuff marks in closet on main level Painter
trim around all doors needs attention Painter
repaint back of front door Painter
paint touch up throughout Painter
sand edges of doors and repaint Painter
all bulbs need to be daylight and match Jill
stain in granite countertop Greg will try a poultice
scratch on closet door at top of 1st set of stairs Painter
resand and repaint side of ? and second set of stairs
sand and repaint side of risers and on 2nd set of stairs Painter
touch up ceiling above fan in master bedroom Painter
change closet closures to brushed nickel Joe has them and will get them to Jill
trim bottom of all bedroom doors a bit Edgar
sand underside of railing on all stairs Painter
Scratched kitchen floor/damaged wall Painter
Fan in living room Electrician
Scratched kitchen floor Denny can fix it
Replace back window? Delivered 12/12
UPGRADES - COMPLETED
    Finished Bonus Room  
    Expanded 12 x 12 deck  
    Expanded Driveway  
    Four Ceiling fans ( LR, Up BR,Bonus)  
    Finished Bonus Bath  
    Amendment to increase price by $19,420  
    3 Larger ceiling fans requested for Master and Living Room  
    Cost to remove and reinstall lights/fans  
CRITICAL PATH - COMPLETED
-- -- Ratified Contract? (0)  01.15.2022    
-- -- $2500 Deposit Received (0)  01.15.2022    
-- -- Association Packet Requested (0)  01.15.2022    
-- -- Association Packet Received (0)  01.20.2022     1/14/2022: requested
-- -- Selections Meeting (0)  01.26.2022    
-- -- Selections Sheet Signed (0)  01.31.2022     1/26/2022: sent to buyers for review
-- -- Amendment for Upgrades (B,S,L,T,BCP) (0)  02.16.2022     2/14/2022: sent to Jerry for signature
-- -- Deposit For Upgrades Received (0)  02.15.2022    
-- -- Building Permit (30) *   01.12.2022    
-- -- Order Roof & Floor Trusses (1)  05.02.2022    
-- -- Order Windows & Doors (0)  05.03.2022    
-- -- Stake Out Home (1)  01.27.2022    
-- -- Excavate (2)  01.31.2022    
-- -- Inspection (Footers) (1)  10.06.2022    
-- -- Inspection (Concrete Wall) (1)  10.06.2022    
-- -- Pour Footers (1) *   01.31.2022    
-- -- Set Forms (2)  02.10.2022    
-- -- Pour Foundation Walls (1)  02.10.2022    
-- -- Plumb Slab (2)  03.31.2022    
-- -- Inspection (Plumbing Under Slab) (1)  10.06.2022    
-- -- Inspection (Conduit Under Slab) (1)  10.06.2022    
-- -- Prepare Slab (1)  03.31.2022    
-- -- Inspection (Slab) (1)  10.06.2022    
-- -- Inspection (Drain Tile) (0)  10.06.2022    
-- -- Pour Slab (1) *   03.31.2022    
-- -- Settlement Agent Confirmed (0)  04.23.2022    
-- -- Framing I (9)  04.19.2022    
-- -- Order Steps (0)  05.05.2022    
-- -- Order Tubs / Showers (0)  05.30.2022    
-- -- Framing II (8)  04.28.2022    
-- -- Framing III (8) *   05.16.2022    
-- -- Install Stairs (0) *   05.30.2022    
-- -- Windows & Doors (0) *   05.30.2022    
-- -- House Number and Status in Window (0)  06.12.2022    
-- -- Roofing (0) *   05.30.2022    
-- -- Order Cabinets (0)  07.07.2022    
-- -- Order Appliances (0)  06.20.2022     Standard SS
-- -- Deck (0)  05.30.2022     Expanded 12x12
-- -- Gutters (0)  08.03.2022    
-- -- Driveway (0) *   08.25.2022     Expanded Driveway
-- -- Patio (0)  10.11.2022    
-- -- Privacy Divider / Fence (0) *   09.17.2022    
-- -- Sod / Seed / Landscaping (0)  09.17.2022    
-- -- HVAC Rough In (4)  05.25.2022    
-- -- Plumbing Rough In (4)  06.25.2022     In process 6/18
-- -- Electric Rough In (4)  06.29.2022     In process 6/25
-- -- Inspection (Rough In HVAC) (1)  10.06.2022    
-- -- Inspection (Rough In Plumbing) (1)  09.07.2022    
-- -- Inspection (Rough In Electric) (1)  09.07.2022    
-- -- Inspection (Framing) (1) *   09.07.2022    
-- -- Inspection (Deck Piers) (0)  09.07.2022    
-- -- Exterior Vinyl (0) *   07.27.2022    
-- -- Exterior Stone (0)  04.14.2022    
-- -- Insulation (2) *   07.03.2022    
-- -- Inspection (Insulation) (1)  07.10.2022    
-- -- Inspection (Electric Service) (0)  09.12.2022    
-- -- Set Electric Meter (0) *   04.11.2023    
-- -- Inspection (Main Sewer Line) (0)  05.12.2022    
-- -- Inspection (Main Water Line) (0)  09.07.2022    
-- -- Order Interior Doors & Trim (0)  06.27.2022    
-- -- Drywall (Hang) (4) *   07.13.2022     In process 7/10 Finish Bonus Room Bath
-- -- Loan Approval (0)  09.06.2022    
-- -- Deed Preparation (0)  04.27.2022    
-- -- Drywall (Tape, Block, Skim, Sand) (6) *   07.31.2022     In process7/20
-- -- Paint 1 (1)  08.10.2022    
-- -- Garage Door (0)  08.14.2022    
-- -- House Numbers (0)  09.01.2022    
-- -- Mailbox (0)  09.15.2022    
-- -- Cabinet Installation (2) *   07.31.2022     Delivered 7/27
-- -- Granite Installation (1) *   09.04.2022     Week of Aug 29
-- -- Interior Trim - Install (3) *   08.31.2022     In process 8/28. Needs painting
-- -- Interior Trim - Paint (1)  10.26.2022    
-- -- Luxury Vinyl Plank (3) *   09.14.2022     In process 9/11 almost completed
-- -- Luxury Vinyl Tile (0)  09.14.2022    
-- -- Paint 2 (3)  09.07.2022    
-- -- Cover Floors (0)  09.14.2022    
-- -- Deliver Plumbing / Lighting Fixtures (0)  08.25.2022    
-- -- Shoe Moulding (0)  09.17.2022    
-- -- Shelving, Door Knobs, Fire Extinguisher (1) *   10.13.2022     In process 10/8 bath accessories and shelving in a few places still needed.
-- -- Install Coded Lockbox (add extra keys) (0)  10.08.2022    
-- -- Pay Water / Sewer Taps (0)  08.25.2022    
-- -- Set Water Meter (1) *   09.08.2022    
-- -- Electric Trim Out (3) *   09.30.2022     Brushed Nickel Standard-in process 9/28
-- -- Ceiling Fans (0)  09.24.2022     Living Room, BR 2 /3, Bonus. In process 9/17
-- -- HVAC Trim Out (1) *   09.22.2022    
-- -- Plumbing Trim Out (2) *   09.28.2022     Brushed Nickel Standard. In process 9/24. Shower and faucet still needed 9/24
-- -- Install Appliances (0) *   10.05.2022     Oct 2 or 3
-- -- Paint 3 (2) *   09.14.2022    
-- -- Carpet (2)  09.30.2022     In process 9/28
-- -- Appraiser Confirms Construction Completion (0)  10.03.2022    
-- -- Inspection (Final HVAC) (0)  10.07.2022    
-- -- Inspection (Final Plumbing) (0)  10.07.2022    
-- -- Inspection (Final Electric) (0)  10.07.2022    
-- -- Inspection (Final Building) (4) *   10.07.2022     Thu, Oct 6
-- -- Pre Walk Through (0)  10.10.2022    
-- -- Stain Hardwood Stairs (1) *   09.30.2022    
-- -- Cleaning (1)  10.12.2022    
-- -- Certificate of Occupancy (1) *   10.07.2022    
-- -- C.O. to Lender (0)  10.07.2022    
-- -- Schedule Closing (0)  10.06.2022    
-- -- Buyer Walk Through (1) *   10.13.2022     Wed, Oct 12, 3:30 PM
-- -- Payment for Upgrades (0)  10.06.2022     $380 for fans
-- -- Keys to Settlement Agent (0)  10.10.2022    
-- -- Review Settlement Statement (0)  10.06.2022    
-- -- Jerry Signs Closing Documents (0)  09.28.2022    
-- -- Request Trash Tote From POA Manager (0)  10.10.2022    
-- -- Closing (1)  10.15.2022     Brittany @ West View Title, Oct 14, 10AM
-- -- Remove Coded Lockbox (0)  11.03.2022