37 ADDR
CONGERS-2 - 123  ::  1357 Palomino Trail
[ BUILD: 20220064 ]      
CRITICAL PATH   |   INSPECTIONS   |   FLOOR PLANS   |   SELECTIONS   |   SPECS   |   CHANGES   |   NHS
view photo archive
 
TO DO
---
UPGRADES
    Upgraded Carpet stairs and upstairs  
    8 lb Pad Upstairs  
    Upgraded Carpet Bonus Room  
    Upgraded Carpet Pad Bonus Room  
CRITICAL PATH
---
TO DO - COMPLETED OR DELETED
UPGRADES - COMPLETED
    Painted Kitchen Cabinetry  
    Finished Bonus Room  
    Finished Bonus Bath  
    Level III Quartz Countertop in Kitchen  
    Level III Quartz Countertops Master Bath  
    Shower Door with black trim  
    Third Paint Color  
    Patio 10 x 10  
    Deck 12 x 12  
    white subway shower panel  
    Cabinet Crown Moulding  
    Kitchen- 3 drawer stack  
    Amendment to increase price by $29,800  
CRITICAL PATH - COMPLETED
-- -- Inspection (Footers) (1)  01.31.2022    
-- -- Inspection (Concrete Wall) (1)  09.07.2022    
-- -- Inspection (Plumbing Under Slab) (1)  03.31.2022    
-- -- Inspection (Conduit Under Slab) (1)  09.07.2022    
-- -- Inspection (Slab) (1)  03.31.2022    
-- -- Inspection (Drain Tile) (0)  09.07.2022    
-- -- Inspection (Rough In HVAC) (1)  06.20.2022    
-- -- Inspection (Rough In Plumbing) (1)  09.07.2022    
-- -- Inspection (Rough In Electric) (1)  09.07.2022    
-- -- Inspection (Framing) (1) *   09.07.2022    
-- -- Inspection (Deck Piers) (0)  09.07.2022    
-- -- Inspection (Insulation) (1)  06.27.2022    
-- -- Inspection (Electric Service) (0)  09.12.2022     On order
-- -- Inspection (Main Sewer Line) (0)  05.12.2022    
-- -- Inspection (Main Water Line) (0)  09.07.2022    
-- -- Inspection (Final HVAC) (0)  09.21.2022    
-- -- Inspection (Final Plumbing) (0)  09.21.2022    
-- -- Inspection (Final Electric) (0)  09.21.2022    
-- -- Inspection (Final Building) (4) *   09.21.2022     Tue, Sep 20