CONGERS-2 - 17  ::  1386 Palomino Trail
[ BUILD: 20220405 ]      
CRITICAL PATH   |   INSPECTIONS   |   FLOOR PLANS   |   SELECTIONS   |   SPECS   |   CHANGES   |   NHS
view photo archive
 
TO DO
---
UPGRADES
---
CRITICAL PATH
    Verify Window & Roof Structure (0)      
    Rough In Microwave Vent (0)      
    Order Plumbing / Lighting Fixtures (0)      
Tue    Feb 3      Blower Door Test (1)      
TO DO - COMPLETED OR DELETED
Missing Master bedroom window
Kitchen side window too
Enlarged patio here. Ok?
USDA loan - closing approx 20 days after completion
Badly dented aluminum front porch piece Davenport, Jeremy 12/31
Chunk missing in island. Edgar thinks trim may cover
Push oven into place after outlet is uncovered/trimmed out
Trim garage
Coded lockbox1717
Missing closet door 11/30 Jill will install after it is painted
Dining light???
Screw covers in doors Plugs
Sweep rocks off the first set of stairs Jill
Install closet door upstairs bedroom
Titan master bath escutcheon at toilet and shower head to wall Tom. Patched 12/7
Caulk master bathroom vanity between wall and cabinet on pantry wall Painter
Snap light broken in kitchen
Bath fan missing mb
Cable box cover in garage Jill
Drywall patch dining room and ceiling cracks Jill will coordinate with painter or drywaller
Attic cover needed Jill. In needs painted 12/10
All mirrors needed
Screens Jill
Garage needs cleaned out Needs swept
Knob needed new closet door in up bedroom Joe
Beeping smoke detector
Beeping smoke detector Upstairs (master?) - Tom
Master bathroom vanity shaker cabinets several rough areas Fred - waiting on replacement as of 12/19
Closet doors rubbing on carpet Painter
Big squeak on floor upstairs bedroom next to stairs Tom
Knob needed new closet door in up bedroom
Ceiling cracks Painter not completed 12/31. In process 1/11
Stuff on top of kitchen cabinets Jill
Cabinet knobs On counter 12/31 - Tom
Smoke detectors beeping Jill
Add another garage door Davenport - we want two garage doors
Spot remove mud on carpet Jill
Muddy spots on steps Jill
UPGRADES - COMPLETED
    Eggshell Paint  
    Amendment to increase price by $1,050  
CRITICAL PATH - COMPLETED
-- -- Ratified Contract? (0)  02.09.2022    
-- -- $2500 Deposit Received (0)  02.15.2022    
-- -- Association Packet Requested (0)  02.09.2022    
-- -- Association Packet Received (0)  02.11.2022    
-- -- Selections Meeting (0)  03.11.2022    
-- -- Selections Sheet Signed (0)  06.06.2022     6/4/2022: sent to Kozhin for signatures;
-- -- Amendment for Upgrades (B,S,L,T,BCP) (0)  06.16.2022     6/14/2022: sent to Jerry for signatures
-- -- Deposit For Upgrades Received (0)  06.16.2022    
-- -- Building Permit (30) *   03.06.2022    
-- -- Order Roof & Floor Trusses (1)  06.20.2022    
-- -- Order Windows & Doors (0)  05.03.2022    
-- -- Stake Out Home (1)  03.24.2022    
-- -- Excavate (2)  03.24.2022    
-- -- Inspection (Footers) (1)  03.24.2022    
-- -- Inspection (Concrete Wall) (1)  09.07.2022    
-- -- Pour Footers (1) *   03.24.2022    
-- -- Set Forms (2)  04.04.2022    
-- -- Pour Foundation Walls (1)  04.04.2022    
-- -- Plumb Slab (2)  04.28.2022    
-- -- Inspection (Plumbing Under Slab) (1)  04.28.2022    
-- -- Inspection (Conduit Under Slab) (1)  09.07.2022    
-- -- Prepare Slab (1)  05.12.2022    
-- -- Inspection (Slab) (1)  06.02.2022    
-- -- Inspection (Drain Tile) (0)  09.07.2022    
-- -- Pour Slab (1) *   06.02.2022    
-- -- Settlement Agent Confirmed (0)  08.18.2022    
-- -- Framing I (9)  06.09.2022    
-- -- Order Steps (0)  06.20.2022    
-- -- Order Tubs / Showers (0)  06.20.2022    
-- -- Framing II (8)  06.27.2022    
-- -- Framing III (8) *   07.05.2022    
-- -- Install Stairs (0) *   07.21.2022    
-- -- Windows & Doors (0) *   07.21.2022    
-- -- House Number and Status in Window (0)  08.22.2022    
-- -- Roofing (0) *   08.01.2022    
-- -- Order Cabinets (0)  07.19.2022    
-- -- Order Appliances (0)  08.30.2022     STANDARD
-- -- Deck (0)  09.17.2022     STANDARD
-- -- Gutters (0)  10.15.2022    
-- -- Driveway (0) *   11.05.2022     Standard
-- -- Patio (0)  10.11.2022    
-- -- Privacy Divider / Fence (0) *   10.19.2022    
-- -- Sod / Seed / Landscaping (0)  12.14.2022     Front area needs sod
-- -- HVAC Rough In (4)  07.21.2022    
-- -- Plumbing Rough In (4)  08.14.2022    
-- -- Electric Rough In (4)  08.14.2022    
-- -- Inspection (Rough In HVAC) (1)  08.18.2022    
-- -- Inspection (Rough In Plumbing) (1)  09.07.2022    
-- -- Inspection (Rough In Electric) (1)  09.07.2022    
-- -- Inspection (Framing) (1) *   09.07.2022    
-- -- Inspection (Deck Piers) (0)  09.07.2022    
-- -- Exterior Vinyl (0) *   10.02.2022    
-- -- Exterior Stone (0)  10.02.2022    
-- -- Insulation (2) *   08.20.2022    
-- -- Inspection (Insulation) (1)  08.22.2022    
-- -- Inspection (Electric Service) (0)  10.27.2022    
-- -- Set Electric Meter (0) *   04.11.2023    
-- -- Inspection (Main Sewer Line) (0)  05.12.2022    
-- -- Inspection (Main Water Line) (0)  09.08.2022    
-- -- Order Interior Doors & Trim (0)  08.29.2022    
-- -- Drywall (Hang) (4) *   08.31.2022     In process 8/28
-- -- Loan Approval (0)  09.06.2022     USDA loan
-- -- Deed Preparation (0)  10.25.2022    
-- -- Drywall (Tape, Block, Skim, Sand) (6) *   09.21.2022     In process 9/14
-- -- Paint 1 (1)  09.24.2022    
-- -- Garage Door (0)  10.22.2022    
-- -- House Numbers (0)  10.26.2022    
-- -- Mailbox (0)  11.17.2022     Tom
-- -- Cabinet Installation (2) *   10.02.2022     On site 9/28. delivery 9/26 (Tom says we can always trim first if we are ready for cabinets sooner)
-- -- Granite Installation (1) *   10.08.2022     10/7
-- -- Interior Trim - Install (3) *   10.19.2022     Needs painting 10/15
-- -- Interior Trim - Paint (1)  10.26.2022    
-- -- Luxury Vinyl Plank (3) *   10.22.2022    
-- -- Luxury Vinyl Tile (0)  10.22.2022    
-- -- Paint 2 (3)  10.26.2022    
-- -- Cover Floors (0)  10.22.2022    
-- -- Deliver Plumbing / Lighting Fixtures (0)  10.27.2022    
-- -- Shoe Moulding (0)  11.09.2022     On site 11/5
-- -- Shelving, Door Knobs, Fire Extinguisher (1) *   11.16.2022     Black accessories, shower door black trim. In process 11/9
-- -- Install Coded Lockbox (add extra keys) (0)  11.19.2022    
-- -- Pay Water / Sewer Taps (0)  10.18.2022    
-- -- Set Water Meter (1) *   11.03.2022    
-- -- Electric Trim Out (3) *   12.03.2022     70% complete 12–1 kk
-- -- Ceiling Fans (0)  12.03.2022    
-- -- HVAC Trim Out (1) *   11.16.2022     Needs thermostat
-- -- Plumbing Trim Out (2) *   11.02.2022     Black Standard
-- -- Install Appliances (0) *   11.07.2022    
-- -- Paint 3 (2) *   10.29.2022    
-- -- Carpet (2)  10.22.2022    
-- -- Appraiser Confirms Construction Completion (0)  01.02.2023    
-- -- Inspection (Final HVAC) (0)  12.08.2022    
-- -- Inspection (Final Plumbing) (0)  12.08.2022    
-- -- Inspection (Final Electric) (0)  12.08.2022    
-- -- Inspection (Final Building) (4) *   12.09.2022     Reinspect 12/8
-- -- Pre Walk Through (0)  12.10.2022    
-- -- Stain Hardwood Stairs (1) *   11.19.2022    
-- -- Cleaning (1)  12.10.2022    
-- -- Certificate of Occupancy (1) *   12.09.2022    
-- -- C.O. to Lender (0)  12.09.2022    
-- -- Schedule Closing (0)  01.25.2023    
-- -- Buyer Walk Through (1) *   12.20.2022     12/19 at 11:00 AM
-- -- Payment for Upgrades (0)  12.12.2022    
-- -- Keys to Settlement Agent (0)  12.19.2022    
-- -- Review Settlement Statement (0)  01.25.2023    
-- -- Jerry Signs Closing Documents (0)  01.28.2023    
-- -- Request Trash Tote From POA Manager (0)  12.08.2022    
-- -- Closing (1)  01.28.2023     Main Street Title Group, Friday Jan 27
-- -- Remove Coded Lockbox (0)  01.30.2023