| TO DO | ||||
| UPGRADES | ||||
| LVP in Up Hallway ($1100) and Bonus Room($1520) | ||||
| CRITICAL PATH | ||||
| --- | ||||
| TO DO - COMPLETED OR DELETED | ||||
| UPGRADES - COMPLETED | ||||
| Finished Bonus Room | ||||
| Bonus Bathroom | ||||
| Window in Bonus Room | ||||
| White Kitchen Cabinetry | ||||
| Double Waste Basket Kitchen Island | ||||
| Oak Stair system stained to match LVP | ||||
| Expanded Patio 10 x 18 | ||||
| Expanded Driveway | ||||
| Level III Granite | ||||
| Vent microwave to exterior | ||||
| Amendment to increase price by $26,720 | ||||
| CRITICAL PATH - COMPLETED | ||||
| -- | -- | Inspection (Footers) (1) 03.24.2022 | ||
| -- | -- | Inspection (Concrete Wall) (1) 09.07.2022 | ||
| -- | -- | Inspection (Plumbing Under Slab) (1) 05.16.2022 | ||
| -- | -- | Inspection (Conduit Under Slab) (1) 09.07.2022 | ||
| -- | -- | Inspection (Slab) (1) 06.03.2022 | ||
| -- | -- | Inspection (Drain Tile) (0) 09.07.2022 | ||
| -- | -- | Inspection (Rough In HVAC) (1) 09.01.2022 | ||
| -- | -- | Inspection (Rough In Plumbing) (1) 09.07.2022 | ||
| -- | -- | Inspection (Rough In Electric) (1) 09.07.2022 | ||
| -- | -- | Inspection (Framing) (1) * 09.07.2022 | ||
| -- | -- | Inspection (Deck Piers) (0) 09.07.2022 | ||
| -- | -- | Inspection (Insulation) (1) 09.08.2022 | ||
| -- | -- | Inspection (Electric Service) (0) 10.27.2022 | ||
| -- | -- | Inspection (Main Sewer Line) (0) 05.12.2022 | ||
| -- | -- | Inspection (Main Water Line) (0) 09.08.2022 | ||
| -- | -- | Inspection (Final HVAC) (0) 11.09.2022 | ||
| -- | -- | Inspection (Final Plumbing) (0) 11.09.2022 | ||
| -- | -- | Inspection (Final Electric) (0) 11.09.2022 | ||
| -- | -- | Inspection (Final Building) (4) * 11.09.2022 | Tuesday, Nov 8 | |