Thu |
Nov 28 |
Verify Window & Roof Structure (0) |
|
|
Thu |
Nov 28 |
Rough In Microwave Vent (0) |
|
|
Thu |
Nov 28 |
Order Plumbing / Lighting Fixtures (0) |
|
|
Thu |
Nov 28 |
Blower Door Test (1) |
|
|
|
-- |
-- |
1031 Closing Deadline = 11/22/2022 |
|
|
-- |
-- |
STANDARD NOT FRENCH MODEL FRIDGE |
|
|
-- |
-- |
Pretty large crack in basement floor. Needs patching? |
|
|
-- |
-- |
All cabinet hardware needed 10/26 |
Brushed nickel, Mid South to install |
|
-- |
-- |
1031 Closing Deadline = 12/20/2022 |
|
|
-- |
-- |
Paint 1 in process 11/12 |
|
|
-- |
-- |
Cover carpet |
Jill |
|
-- |
-- |
crack in basement concrete |
tom will caulk |
|
-- |
-- |
Crack in trim basement door |
Tom - around frame (foam) |
|
-- |
-- |
CODED LOCKBOX 0116 |
|
|
-- |
-- |
Transition strip at steps needs installed 12/10 |
Eagle |
|
-- |
-- |
Two handles on kitchen drawers-is this correct? |
Does not need replaced (IMO) |
|
-- |
-- |
Vented micro not working 12/10 |
Tom |
|
-- |
-- |
Attic cover |
Jill |
|
-- |
-- |
Wire hanging out of ceiling fan in mb 12/10 |
Electrician |
|
-- |
-- |
Crack in hardwood steps |
Painter |
|
-- |
-- |
Clean garage |
Jill |
|
-- |
-- |
Need towel bars in up baths |
Joe |
|
-- |
-- |
Cracks in steps |
Drywaller, Painter |
|
-- |
-- |
Sand and caulk around dryer vent |
Painter |
|
-- |
-- |
Splotches on upper cabinet doors |
Fred ordered |
|
-- |
-- |
Sand laundry room door |
Painter |
|
-- |
-- |
Caulk side and backsplash in master bathroom |
Painter |
|
-- |
-- |
Patch hole in master linen nook |
Painter. Needs painted. |
|
-- |
-- |
Touch up outside patio door |
Painter |
|
-- |
-- |
Sand and paint touch up above powder room light |
Painter |
|
-- |
-- |
Re-paint closet under second set of steps |
Painter |
|
-- |
-- |
Fill screw holes at trim around garage door |
Davenport |
|
-- |
-- |
Paint touch up |
|
|
-- |
-- |
Fix garage exterior trim |
Davenport - top trim piece, gap, Jeremy |
|
-- |
-- |
Holes above cabinets from installation |
|
|
-- |
-- |
Patch/paint pipe in powder bath |
Painter - silicone |
|
-- |
-- |
Plumber needs to push in dishwasher so doesn’t move |
CJ |
|
-- |
-- |
Adjust upper left cabinet door |
Fred |
|
-- |
-- |
Wobbly light on deck |
Missing screw, Electrician |
|
-- |
-- |
Patch paint |
Painter |
|
-- |
-- |
Dirt on living room ceiling |
Painter |
|
-- |
-- |
Adjust window in living room and master bedroom to latch properly |
Tom |
|
-- |
-- |
Hole under stairs from stair repair |
Painter |
|
-- |
-- |
Clean out broken pieces of refrigerator bulb |
Jill |
|
-- |
-- |
Scratches on cabinet doors to the right of the range |
Fred will order |
|
-- |
-- |
Scratched deck door |
Jill will look at it |
|
-- |
-- |
Basement door missing silicone and weatherstripping |
|
|
-- |
-- |
Cabinet shelf to the left of kitchen island was not installed |
|
|
-- |
-- |
Scratches on cabinet door to the left of kitchen island |
Jill will show Fred |
|
-- |
-- |
Add missing window part on master bedroom window |
Tom |
|
-- |
-- |
Coded lockbox 0116 |
|
|
-- |
-- |
Ratified Contract? (0) 02.16.2022 |
|
|
-- |
-- |
$2500 Deposit Received (0) 02.18.2022 |
|
|
-- |
-- |
Association Packet Requested (0) 02.16.2022 |
|
|
-- |
-- |
Association Packet Received (0) 02.18.2022 |
|
|
-- |
-- |
Selections Meeting (0) 03.23.2022 |
|
|
-- |
-- |
Selections Sheet Signed (0) 11.28.2022 |
5/3/2022: sending again with changes |
|
-- |
-- |
Amendment for Upgrades (B,S,L,T,BCP) (0) 11.28.2022 |
|
|
-- |
-- |
Deposit For Upgrades Received (0) 11.28.2022 |
|
|
-- |
-- |
Building Permit (30) 03.06.2022 |
|
|
-- |
-- |
Order Roof & Floor Trusses (1) 06.20.2022 |
|
|
-- |
-- |
Order Windows & Doors (0) 05.03.2022 |
|
|
-- |
-- |
Stake Out Home (1) 03.24.2022 |
|
|
-- |
-- |
Excavate (2) 03.24.2022 |
|
|
-- |
-- |
Inspection (Footers) (1) 03.24.2022 |
|
|
-- |
-- |
Inspection (Concrete Wall) (1) 09.07.2022 |
|
|
-- |
-- |
Pour Footers (1) 03.24.2022 |
|
|
-- |
-- |
Set Forms (2) 04.19.2022 |
|
|
-- |
-- |
Pour Foundation Walls (1) 04.21.2022 |
|
|
-- |
-- |
Plumb Slab (2) 06.06.2022 |
|
|
-- |
-- |
Inspection (Plumbing Under Slab) (1) 06.27.2022 |
|
|
-- |
-- |
Inspection (Conduit Under Slab) (1) 09.07.2022 |
|
|
-- |
-- |
Prepare Slab (1) 07.05.2022 |
|
|
-- |
-- |
Inspection (Slab) (1) 07.05.2022 |
|
|
-- |
-- |
Inspection (Drain Tile) (0) 09.07.2022 |
|
|
-- |
-- |
Pour Slab (1) * 07.05.2022 |
|
|
-- |
-- |
Settlement Agent Confirmed (0) 02.18.2022 |
|
|
-- |
-- |
Framing I (9) 07.25.2022 |
|
|
-- |
-- |
Order Steps (0) 08.22.2022 |
|
|
-- |
-- |
Order Tubs / Showers (0) 06.20.2022 |
|
|
-- |
-- |
Framing II (8) 07.28.2022 |
|
|
-- |
-- |
Framing III (8) * 08.08.2022 |
|
|
-- |
-- |
Install Stairs (0) 08.22.2022 |
|
|
-- |
-- |
Windows & Doors (0) 08.22.2022 |
|
|
-- |
-- |
House Number and Status in Window (0) 08.22.2022 |
|
|
-- |
-- |
Roofing (0) 09.01.2022 |
|
|
-- |
-- |
Order Cabinets (0) 08.24.2022 |
|
|
-- |
-- |
Order Appliances (0) 08.30.2022 |
Standard |
|
-- |
-- |
Deck (0) 09.06.2022 |
Expanded 12 x 18 |
|
-- |
-- |
Gutters (0) 10.26.2022 |
|
|
-- |
-- |
Driveway (0) 11.12.2022 |
Expanded Driveway |
|
-- |
-- |
Patio (0) 10.11.2022 |
|
|
-- |
-- |
Privacy Divider / Fence (0) 10.22.2022 |
|
|
-- |
-- |
Sod / Seed / Landscaping (0) 11.30.2022 |
|
|
-- |
-- |
HVAC Rough In (4) 08.25.2022 |
|
|
-- |
-- |
Inspection (Rough In HVAC) (1) 09.12.2022 |
|
|
-- |
-- |
Plumbing Rough In (4) 09.05.2022 |
in process 8/31 |
|
-- |
-- |
Inspection (Rough In Plumbing) (1) 09.15.2022 |
|
|
-- |
-- |
Electric Rough In (4) 09.17.2022 |
In process 9/14 |
|
-- |
-- |
Inspection (Rough In Electric) (1) 09.21.2022 |
|
|
-- |
-- |
Inspection (Deck Piers) (0) 09.19.2022 |
|
|
-- |
-- |
Inspection (Framing) (1) 09.21.2022 |
|
|
-- |
-- |
Exterior Vinyl (0) * 10.22.2022 |
|
|
-- |
-- |
Exterior Stone (0) 04.14.2022 |
|
|
-- |
-- |
Insulation (2) 09.21.2022 |
|
|
-- |
-- |
Inspection (Insulation) (1) 09.22.2022 |
|
|
-- |
-- |
Inspection (Electric Service) (0) 10.27.2022 |
|
|
-- |
-- |
Set Electric Meter (0) 04.11.2023 |
|
|
-- |
-- |
Inspection (Main Sewer Line) (0) 07.05.2022 |
|
|
-- |
-- |
Inspection (Main Water Line) (0) 10.27.2022 |
|
|
-- |
-- |
Order Interior Doors & Trim (0) 10.27.2022 |
|
|
-- |
-- |
Drywall (Hang) (4) * 09.24.2022 |
In process 9/24 |
|
-- |
-- |
Loan Approval (0) 11.28.2022 |
|
|
-- |
-- |
Deed Preparation (0) 11.08.2022 |
|
|
-- |
-- |
Drywall (Tape, Block, Skim, Sand) (6) * 10.19.2022 |
In process10/15 appears almost complete |
|
-- |
-- |
Paint 1 (1) 10.19.2022 |
|
|
-- |
-- |
Garage Door (0) 11.07.2022 |
|
|
-- |
-- |
House Numbers (0) 12.03.2022 |
|
|
-- |
-- |
Mailbox (0) 11.27.2022 |
|
|
-- |
-- |
Cabinet Installation (2) * 10.26.2022 |
install 10/25 |
|
-- |
-- |
Granite Installation (1) * 11.02.2022 |
|
|
-- |
-- |
Interior Trim - Install (3) 11.12.2022 |
In process11/9 |
|
-- |
-- |
Interior Trim - Paint (1) 11.12.2022 |
|
|
-- |
-- |
Luxury Vinyl Plank (3) * 11.27.2022 |
In process 11/19 |
|
-- |
-- |
Luxury Vinyl Tile (0) 11.19.2022 |
In process 11/16 |
|
-- |
-- |
Paint 2 (3) 11.30.2022 |
In process 11/27 |
|
-- |
-- |
Cover Floors (1) 12.14.2022 |
|
|
-- |
-- |
Deliver Plumbing / Lighting Fixtures (0) 11.28.2022 |
|
|
-- |
-- |
Shoe Moulding (0) 11.30.2022 |
In process 11/27 |
|
-- |
-- |
Shelving, Door Knobs, Fire Extinguisher (0) 12.14.2022 |
Brushed Nickel accessories. In process 12/10. Need shelves and mirrors |
|
-- |
-- |
Install Coded Lockbox (add extra keys) (0) 12.10.2022 |
|
|
-- |
-- |
Pay Water / Sewer Taps (0) 10.18.2022 |
|
|
-- |
-- |
Set Water Meter (0) 11.10.2022 |
|
|
-- |
-- |
Electric Trim Out (3) 12.10.2022 |
Brushed Nickel Standard. Starting 12/5. Will be done 12/8 (court) |
|
-- |
-- |
Ceiling Fans (0) 12.10.2022 |
|
|
-- |
-- |
HVAC Trim Out (1) 12.10.2022 |
|
|
-- |
-- |
Plumbing Trim Out (2) 11.30.2022 |
Brushed Nickel Standard in process 11/27 |
|
-- |
-- |
Install Appliances (0) * 12.10.2022 |
12/8 |
|
-- |
-- |
Paint 3 (2) * 11.30.2022 |
|
|
-- |
-- |
Carpet (2) 11.27.2022 |
|
|
-- |
-- |
Appraiser Confirms Construction Completion (0) 12.14.2022 |
|
|
-- |
-- |
Inspection (Final HVAC) (1) 12.14.2022 |
|
|
-- |
-- |
Inspection (Final Plumbing) (1) 12.14.2022 |
|
|
-- |
-- |
Inspection (Final Electric) (1) 12.14.2022 |
|
|
-- |
-- |
Inspection (Final Building) (2) * 12.14.2022 |
Mon, Dec 12 |
|
-- |
-- |
Pre Walk Through (0) 12.14.2022 |
12/12 |
|
-- |
-- |
Stain Hardwood Stairs (1) 12.03.2022 |
|
|
-- |
-- |
Cleaning (1) 12.12.2022 |
|
|
-- |
-- |
Certificate of Occupancy (1) * 12.14.2022 |
|
|
-- |
-- |
C.O. to Lender (0) 12.14.2022 |
|
|
-- |
-- |
Schedule Closing (0) 12.27.2022 |
|
|
-- |
-- |
Buyer Walk Through (1) 12.16.2022 |
Wednesday 12/14. at 1:30??? |
|
-- |
-- |
Payment for Upgrades (0) 12.12.2022 |
|
|
-- |
-- |
Keys to Settlement Agent (0) 12.10.2022 |
|
|
-- |
-- |
Review Settlement Statement (0) 12.29.2022 |
|
|
-- |
-- |
Jerry Signs Closing Documents (0) 09.28.2022 |
|
|
-- |
-- |
Request Trash Tote From POA Manager (0) 12.12.2022 |
|
|
-- |
-- |
Closing (1) 12.29.2022 |
Brittany @ West View Title, Thu, Dec 29 |
|
-- |
-- |
Remove Coded Lockbox (0) 02.06.2023 |
|
|