Thu |
Nov 28 |
Verify Window & Roof Structure (0) |
|
|
Thu |
Nov 28 |
Rough In Microwave Vent (0) |
|
|
Thu |
Nov 28 |
Order Plumbing / Lighting Fixtures (0) |
|
|
Thu |
Nov 28 |
Blower Door Test (1) |
|
|
|
-- |
-- |
Missing back basement window |
|
|
-- |
-- |
Patio standard? |
|
|
-- |
-- |
Crown molding on kitchen cabinets-don’t see in changes? |
|
|
-- |
-- |
3 drawer stack as well.. |
|
|
-- |
-- |
Kitchen trash can also |
|
|
-- |
-- |
All cabinetry is same color-is that correct? |
Kate will follow up |
|
-- |
-- |
Replace door to main level closet |
|
|
-- |
-- |
Closet door under stairs missing |
|
|
-- |
-- |
Remove golf cart from garage |
Tom |
|
-- |
-- |
Cable cover garage |
Jill |
|
-- |
-- |
Fill holes in basement floor? |
Paint touchup throughoutTom |
|
-- |
-- |
Repair bath fan |
Mast & Brunk |
|
-- |
-- |
Push oven in once outlet is ready |
|
|
-- |
-- |
Squeaky for outside of master closet |
Tom |
|
-- |
-- |
Squeaky floor in one of spare bedrooms |
Tom |
|
-- |
-- |
Squeaky floor in one of spare bedrooms |
|
|
-- |
-- |
Powder bath light needs installed |
|
|
-- |
-- |
CODED LOCKBOX 0117 |
|
|
-- |
-- |
Push attic cover into place |
|
|
-- |
-- |
Add silicone to the top of the range |
CJ will replace the range |
|
-- |
-- |
Put range in place |
|
|
-- |
-- |
Fix hole in master shower |
Thu, Dec 29 |
|
-- |
-- |
Re-sand and paint tray ceiling |
Painter |
|
-- |
-- |
Repaint attic access door |
|
|
-- |
-- |
Repaint attic access door |
|
|
-- |
-- |
Fill and paint areas of settling at ceiling |
Painter |
|
-- |
-- |
Squeaking floor in master bedroom |
|
|
-- |
-- |
Add silicone and paint above master shower and hall bathroom shower |
Painter |
|
-- |
-- |
Island vertical corner trim to be replaced |
Fred has ordered it |
|
-- |
-- |
Window in door does not seem to be squarely installed? |
|
|
-- |
-- |
Cabinet door on refrigerator door to be replaced |
Fred has ordered it |
|
-- |
-- |
Max = 540-246-5877 |
|
|
-- |
-- |
Holes in trim board around garage |
Davenport |
|
-- |
-- |
receptacle needs straightened in upstairs bathroom |
electricians |
|
-- |
-- |
Ratified Contract? (0) 02.16.2022 |
|
|
-- |
-- |
$2500 Deposit Received (0) 02.18.2022 |
|
|
-- |
-- |
Association Packet Requested (0) 02.16.2022 |
|
|
-- |
-- |
Association Packet Received (0) 02.18.2022 |
|
|
-- |
-- |
Selections Meeting (0) 03.23.2022 |
|
|
-- |
-- |
Selections Sheet Signed (0) 04.07.2022 |
3/30/2022: waiting on Kate to add expanded driveway |
|
-- |
-- |
Amendment for Upgrades (B,S,L,T,BCP) (0) 04.20.2022 |
4/18/2022: sent to Jerry for signature |
|
-- |
-- |
Deposit For Upgrades Received (0) 04.19.2022 |
|
|
-- |
-- |
Building Permit (30) 03.06.2022 |
|
|
-- |
-- |
Order Roof & Floor Trusses (1) 06.20.2022 |
|
|
-- |
-- |
Order Windows & Doors (0) 05.03.2022 |
|
|
-- |
-- |
Stake Out Home (1) 03.24.2022 |
|
|
-- |
-- |
Excavate (2) 03.24.2022 |
|
|
-- |
-- |
Inspection (Footers) (1) 03.24.2022 |
|
|
-- |
-- |
Inspection (Concrete Wall) (1) 09.07.2022 |
|
|
-- |
-- |
Pour Footers (1) 03.24.2022 |
|
|
-- |
-- |
Set Forms (2) 04.19.2022 |
|
|
-- |
-- |
Pour Foundation Walls (1) 04.21.2022 |
|
|
-- |
-- |
Plumb Slab (2) 06.06.2022 |
|
|
-- |
-- |
Inspection (Plumbing Under Slab) (1) 06.27.2022 |
|
|
-- |
-- |
Inspection (Conduit Under Slab) (1) 09.07.2022 |
|
|
-- |
-- |
Prepare Slab (1) 07.05.2022 |
|
|
-- |
-- |
Inspection (Slab) (1) 07.05.2022 |
|
|
-- |
-- |
Inspection (Drain Tile) (0) 09.07.2022 |
|
|
-- |
-- |
Pour Slab (1) * 07.05.2022 |
|
|
-- |
-- |
Settlement Agent Confirmed (0) 03.24.2022 |
|
|
-- |
-- |
Framing I (9) 07.25.2022 |
|
|
-- |
-- |
Order Steps (0) 08.22.2022 |
|
|
-- |
-- |
Order Tubs / Showers (0) 06.20.2022 |
|
|
-- |
-- |
Framing II (8) 07.28.2022 |
|
|
-- |
-- |
Framing III (8) * 08.08.2022 |
|
|
-- |
-- |
Install Stairs (0) 08.22.2022 |
|
|
-- |
-- |
Windows & Doors (0) 08.22.2022 |
|
|
-- |
-- |
House Number and Status in Window (0) 08.22.2022 |
|
|
-- |
-- |
Roofing (0) 09.01.2022 |
|
|
-- |
-- |
Order Cabinets (0) 08.24.2022 |
|
|
-- |
-- |
Order Appliances (0) 08.30.2022 |
Standard |
|
-- |
-- |
Deck (0) 09.06.2022 |
Expanded 12 x 18 |
|
-- |
-- |
Gutters (0) 10.26.2022 |
|
|
-- |
-- |
Driveway (0) 11.09.2022 |
Expanded Driveway |
|
-- |
-- |
Patio (0) 10.11.2022 |
|
|
-- |
-- |
Privacy Divider / Fence (0) 10.22.2022 |
|
|
-- |
-- |
Sod / Seed / Landscaping (0) 11.27.2022 |
|
|
-- |
-- |
HVAC Rough In (4) 08.25.2022 |
|
|
-- |
-- |
Inspection (Rough In HVAC) (1) 09.08.2022 |
|
|
-- |
-- |
Plumbing Rough In (4) 12.10.2022 |
In process 8/31 |
|
-- |
-- |
Inspection (Rough In Plumbing) (1) 09.08.2022 |
|
|
-- |
-- |
Electric Rough In (4) 09.05.2022 |
|
|
-- |
-- |
Inspection (Rough In Electric) (1) 09.08.2022 |
|
|
-- |
-- |
Inspection (Deck Piers) (0) 09.08.2022 |
|
|
-- |
-- |
Inspection (Framing) (1) 09.08.2022 |
|
|
-- |
-- |
Exterior Vinyl (0) * 10.22.2022 |
|
|
-- |
-- |
Exterior Stone (0) 04.14.2022 |
|
|
-- |
-- |
Insulation (2) 09.11.2022 |
|
|
-- |
-- |
Inspection (Insulation) (1) 09.15.2022 |
|
|
-- |
-- |
Inspection (Electric Service) (0) 10.27.2022 |
|
|
-- |
-- |
Set Electric Meter (0) 04.11.2023 |
|
|
-- |
-- |
Inspection (Main Sewer Line) (0) 07.05.2022 |
|
|
-- |
-- |
Inspection (Main Water Line) (0) 10.27.2022 |
|
|
-- |
-- |
Order Interior Doors & Trim (0) 10.27.2022 |
|
|
-- |
-- |
Drywall (Hang) (4) * 09.17.2022 |
NONE |
|
-- |
-- |
Loan Approval (0) 04.18.2022 |
|
|
-- |
-- |
Deed Preparation (0) 10.31.2022 |
|
|
-- |
-- |
Drywall (Tape, Block, Skim, Sand) (6) * 10.19.2022 |
In process10/15. Appears very close to completion. |
|
-- |
-- |
Paint 1 (1) 10.19.2022 |
|
|
-- |
-- |
Garage Door (0) 10.26.2022 |
|
|
-- |
-- |
House Numbers (0) 12.03.2022 |
|
|
-- |
-- |
Mailbox (0) 11.27.2022 |
|
|
-- |
-- |
Cabinet Installation (2) * 10.26.2022 |
On site 10/22. Install 10/24 |
|
-- |
-- |
Granite Installation (1) * 11.02.2022 |
|
|
-- |
-- |
Interior Trim - Install (3) 11.19.2022 |
in process 11/19 |
|
-- |
-- |
Interior Trim - Paint (1) 11.27.2022 |
|
|
-- |
-- |
Luxury Vinyl Plank (3) * 12.03.2022 |
In process 11/30 |
|
-- |
-- |
Luxury Vinyl Tile (0) 12.03.2022 |
In process 11/30 |
|
-- |
-- |
Paint 2 (3) 12.07.2022 |
painting 12/5 |
|
-- |
-- |
Cover Floors (1) 12.17.2022 |
|
|
-- |
-- |
Deliver Plumbing / Lighting Fixtures (0) 12.01.2022 |
|
|
-- |
-- |
Shoe Moulding (0) 12.07.2022 |
|
|
-- |
-- |
Shelving, Door Knobs, Fire Extinguisher (0) 12.14.2022 |
Black Standard. In process 12/10 |
|
-- |
-- |
Install Coded Lockbox (add extra keys) (0) 12.17.2022 |
|
|
-- |
-- |
Pay Water / Sewer Taps (0) 10.18.2022 |
|
|
-- |
-- |
Set Water Meter (0) 11.10.2022 |
|
|
-- |
-- |
Electric Trim Out (3) 12.17.2022 |
Needs a lot done 12/14 |
|
-- |
-- |
Ceiling Fans (0) 12.17.2022 |
|
|
-- |
-- |
HVAC Trim Out (1) 12.10.2022 |
|
|
-- |
-- |
Plumbing Trim Out (2) 12.14.2022 |
Black Standard. Jill will tell him to start. Only master bath vanity is plumbed. 12/10 |
|
-- |
-- |
Install Appliances (0) * 12.10.2022 |
12/8 |
|
-- |
-- |
Paint 3 (2) * 12.07.2022 |
|
|
-- |
-- |
Carpet (2) 12.03.2022 |
|
|
-- |
-- |
Appraiser Confirms Construction Completion (0) 12.27.2022 |
|
|
-- |
-- |
Inspection (Final HVAC) (1) 12.21.2022 |
|
|
-- |
-- |
Inspection (Final Plumbing) (1) 12.21.2022 |
|
|
-- |
-- |
Inspection (Final Electric) (1) 12.21.2022 |
|
|
-- |
-- |
Inspection (Final Building) (2) * 12.23.2022 |
Tuesday, Dec 20 |
|
-- |
-- |
Pre Walk Through (0) 12.15.2022 |
|
|
-- |
-- |
Stain Hardwood Stairs (1) 12.10.2022 |
In process 12/7 |
|
-- |
-- |
Cleaning (1) 12.27.2022 |
|
|
-- |
-- |
Certificate of Occupancy (1) * 12.23.2022 |
|
|
-- |
-- |
C.O. to Lender (0) 12.27.2022 |
|
|
-- |
-- |
Schedule Closing (0) 12.20.2022 |
|
|
-- |
-- |
Buyer Walk Through (1) 12.20.2022 |
Mon, Dec 19 at noon |
|
-- |
-- |
Payment for Upgrades (0) 12.20.2022 |
|
|
-- |
-- |
Keys to Settlement Agent (0) 12.15.2022 |
|
|
-- |
-- |
Review Settlement Statement (0) 12.29.2022 |
|
|
-- |
-- |
Jerry Signs Closing Documents (0) 12.20.2022 |
|
|
-- |
-- |
Request Trash Tote From POA Manager (0) 12.19.2022 |
|
|
-- |
-- |
Closing (1) 12.29.2022 |
Brittany @ West View Title, Dec 27, 2PM |
|
-- |
-- |
Remove Coded Lockbox (0) 01.02.2023 |
|
|