Deck is not standard. |
|
|
-- |
-- |
Deck is not standard. |
Charge owners 1/2? |
|
-- |
-- |
USDA loan - closing approx 20 days after completion |
|
|
-- |
-- |
Amendment #2 |
Has not signed 11/16 |
|
-- |
-- |
Cover carpets |
Jill |
|
-- |
-- |
|
|
|
-- |
-- |
|
|
|
-- |
-- |
Side piece of garage needed |
Davenport - Weatherstripping on left side of exterior garage door |
|
-- |
-- |
Powder bath light needed |
Electrician |
|
-- |
-- |
Cabinet drawer needs adjusting. |
Kitchen drawer to right of oven, Mid South. Thursday-12/9 |
|
-- |
-- |
Stop spitting sunflower seeds on the carpet! |
|
|
-- |
-- |
Attic cover |
Painter |
|
-- |
-- |
Recover carpet on steps to protect |
|
|
-- |
-- |
Sunflower seeds everywhere on the carpet |
|
|
-- |
-- |
Install attic access panel |
|
|
-- |
-- |
Cut down closet doors rubbing on carpet |
Painter |
|
-- |
-- |
Titan master bathroom escutcheons at showerhead and toilet to wall |
Tom |
|
-- |
-- |
Cover steps |
Jill |
|
-- |
-- |
CODED LOCKBOX 0118 |
|
|
-- |
-- |
Fix basement insulation |
Tom |
|
-- |
-- |
Extra screens in foyer |
Jill |
|
-- |
-- |
Adjust kitchen drawer |
|
|
-- |
-- |
drywall seam living room |
|
|
-- |
-- |
remove exposed nail island adn fix |
Mid South |
|
-- |
-- |
tighten light switch to wall living room |
Electrician not completed 12/31 |
|
-- |
-- |
Cable box cover |
Jill |
|
-- |
-- |
Paint living room wall |
Painter |
|
-- |
-- |
Fill cracks in steps |
Painter |
|
-- |
-- |
Final paint touch up after drywall repair |
Painter |
|
-- |
-- |
Add PVC board under back door |
Tom |
|
-- |
-- |
|
|
|
-- |
-- |
Towel holder hall bath install |
|
|
-- |
-- |
Paint touch up near stair case |
|
|
-- |
-- |
Parking space client discussion |
Monday per Jerry |
|
-- |
-- |
siding falling off the front of townhouse |
davenport. Not completed 8/3 |
|
-- |
-- |
Ratified Contract? (0)
02.16.2022 |
|
|
-- |
-- |
$2500 Deposit Received (0)
02.24.2022 |
|
|
-- |
-- |
Association Packet Requested (0)
02.16.2022 |
|
|
-- |
-- |
Association Packet Received (0)
02.18.2022 |
|
|
-- |
-- |
Selections Meeting (0)
07.16.2022 |
|
|
-- |
-- |
Selections Sheet Signed (0)
08.23.2022 |
7/16: sent to Kozhin for signatures |
|
-- |
-- |
Amendment for Upgrades (B,S,L,T,BCP) (0)
08.31.2022 |
8/30/2022: sent to Jerry for signature |
|
-- |
-- |
Deposit For Upgrades Received (0)
08.30.2022 |
|
|
-- |
-- |
Building Permit (30)
03.06.2022 |
|
|
-- |
-- |
Order Roof & Floor Trusses (1)
06.20.2022 |
|
|
-- |
-- |
Order Windows & Doors (0)
05.03.2022 |
|
|
-- |
-- |
Stake Out Home (1)
03.24.2022 |
|
|
-- |
-- |
Excavate (2)
03.24.2022 |
|
|
-- |
-- |
Inspection (Footers) (1)
03.24.2022 |
|
|
-- |
-- |
Inspection (Concrete Wall) (1)
09.07.2022 |
|
|
-- |
-- |
Pour Footers (1)
03.24.2022 |
|
|
-- |
-- |
Set Forms (2)
04.19.2022 |
|
|
-- |
-- |
Pour Foundation Walls (1)
04.21.2022 |
|
|
-- |
-- |
Plumb Slab (2)
06.06.2022 |
|
|
-- |
-- |
Inspection (Plumbing Under Slab) (1)
06.27.2022 |
|
|
-- |
-- |
Inspection (Conduit Under Slab) (1)
09.07.2022 |
|
|
-- |
-- |
Prepare Slab (1)
03.22.2022 |
|
|
-- |
-- |
Inspection (Slab) (1)
07.05.2022 |
|
|
-- |
-- |
Inspection (Drain Tile) (0)
09.07.2022 |
|
|
-- |
-- |
Pour Slab (1)
07.05.2022 |
|
|
-- |
-- |
Settlement Agent Confirmed (0)
08.18.2022 |
|
|
-- |
-- |
Framing I (9)
07.25.2022 |
|
|
-- |
-- |
Order Steps (0)
08.22.2022 |
|
|
-- |
-- |
Order Tubs / Showers (0)
06.20.2022 |
|
|
-- |
-- |
Framing II (8)
07.28.2022 |
|
|
-- |
-- |
Framing III (8)
08.08.2022 |
|
|
-- |
-- |
Verify Window & Roof Structure (0)
07.20.2024 |
|
|
-- |
-- |
Install Stairs (0)
08.22.2022 |
|
|
-- |
-- |
Windows & Doors (0)
08.22.2022 |
|
|
-- |
-- |
House Number and Status in Window (0)
08.22.2022 |
|
|
-- |
-- |
Roofing (0)
09.01.2022 |
|
|
-- |
-- |
Order Cabinets (0)
08.24.2022 |
|
|
-- |
-- |
Order Appliances (0)
08.30.2022 |
Standard SS |
|
-- |
-- |
Deck (0)
09.06.2022 |
|
|
-- |
-- |
Gutters (0)
10.26.2022 |
|
|
-- |
-- |
Driveway (0)
11.09.2022 |
Expanded Driveway |
|
-- |
-- |
Patio (0)
10.11.2022 |
|
|
-- |
-- |
Privacy Divider / Fence (0)
10.22.2022 |
|
|
-- |
-- |
Sod / Seed / Landscaping (0)
11.27.2022 |
|
|
-- |
-- |
HVAC Rough In (4)
08.25.2022 |
|
|
-- |
-- |
Inspection (Rough In HVAC) (1)
09.08.2022 |
|
|
-- |
-- |
Rough In Microwave Vent (0)
07.20.2024 |
|
|
-- |
-- |
Plumbing Rough In (4)
09.01.2022 |
In process 8/31 |
|
-- |
-- |
Inspection (Rough In Plumbing) (1)
09.08.2022 |
|
|
-- |
-- |
Electric Rough In (4)
09.06.2022 |
|
|
-- |
-- |
Inspection (Rough In Electric) (1)
09.08.2022 |
|
|
-- |
-- |
Inspection (Deck Piers) (0)
09.08.2022 |
|
|
-- |
-- |
Inspection (Framing) (1)
09.08.2022 |
|
|
-- |
-- |
Exterior Vinyl (0)
10.19.2022 |
|
|
-- |
-- |
Exterior Stone (0)
11.27.2022 |
In process 11/19 |
|
-- |
-- |
Insulation (2)
09.11.2022 |
|
|
-- |
-- |
Inspection (Insulation) (1)
09.15.2022 |
|
|
-- |
-- |
Inspection (Electric Service) (0)
10.27.2022 |
|
|
-- |
-- |
Set Electric Meter (0)
04.11.2023 |
|
|
-- |
-- |
Inspection (Main Sewer Line) (0)
08.29.2022 |
|
|
-- |
-- |
Inspection (Main Water Line) (0)
10.27.2022 |
|
|
-- |
-- |
Order Interior Doors & Trim (0)
10.27.2022 |
|
|
-- |
-- |
Drywall (Hang) (4)
09.24.2022 |
In process 9/21 |
|
-- |
-- |
Loan Approval (0)
09.07.2022 |
|
|
-- |
-- |
Deed Preparation (0)
12.02.2022 |
After amendment |
|
-- |
-- |
Drywall (Tape, Block, Skim, Sand) (6)
10.19.2022 |
In process 10/16. Maybe just need to sweep up? |
|
-- |
-- |
Paint 1 (1)
10.19.2022 |
|
|
-- |
-- |
Garage Door (0)
10.26.2022 |
|
|
-- |
-- |
House Numbers (0)
11.27.2022 |
|
|
-- |
-- |
Mailbox (0)
11.27.2022 |
|
|
-- |
-- |
Cabinet Installation (2)
10.26.2022 |
install 10/24. On site 10/22 |
|
-- |
-- |
Granite Installation (1)
11.02.2022 |
|
|
-- |
-- |
Interior Trim - Install (3)
11.09.2022 |
in process 11/5 |
|
-- |
-- |
Order Plumbing / Lighting Fixtures (0)
07.20.2024 |
|
|
-- |
-- |
Interior Trim - Paint (1)
11.12.2022 |
In process 11/9 |
|
-- |
-- |
Luxury Vinyl Plank (3)
11.16.2022 |
|
|
-- |
-- |
Luxury Vinyl Tile (0)
11.16.2022 |
|
|
-- |
-- |
Paint 2 (3)
11.27.2022 |
In process 11/19 |
|
-- |
-- |
Cover Floors (1)
11.27.2022 |
|
|
-- |
-- |
Deliver Plumbing / Lighting Fixtures (0)
11.27.2022 |
|
|
-- |
-- |
Shoe Moulding (0)
11.19.2022 |
|
|
-- |
-- |
Shelving, Door Knobs, Fire Extinguisher (0)
12.03.2022 |
Black accessories in process 11/30. Shelving needed. Mirrors too. |
|
-- |
-- |
Install Coded Lockbox (add extra keys) (0)
12.05.2022 |
|
|
-- |
-- |
Pay Water / Sewer Taps (0)
10.18.2022 |
|
|
-- |
-- |
Set Water Meter (0)
11.10.2022 |
|
|
-- |
-- |
Electric Trim Out (3)
11.30.2022 |
Black Standard. 99% completed |
|
-- |
-- |
Ceiling Fans (0)
11.27.2022 |
|
|
-- |
-- |
HVAC Trim Out (1)
11.27.2022 |
|
|
-- |
-- |
Blower Door Test (1)
07.20.2024 |
|
|
-- |
-- |
Plumbing Trim Out (2)
11.27.2022 |
Black Standard |
|
-- |
-- |
Install Appliances (0)
11.30.2022 |
Everything installed but refrigerator. Maybe awaiting outlet cover behind it? |
|
-- |
-- |
Paint 3 (2)
11.27.2022 |
|
|
-- |
-- |
Carpet (2)
11.27.2022 |
|
|
-- |
-- |
Appraiser Confirms Construction Completion (0)
01.02.2023 |
|
|
-- |
-- |
Inspection (Final HVAC) (1)
12.01.2022 |
|
|
-- |
-- |
Inspection (Final Plumbing) (1)
12.01.2022 |
|
|
-- |
-- |
Inspection (Final Electric) (1)
12.01.2022 |
|
|
-- |
-- |
Inspection (Final Building) (2)
12.02.2022 |
Mon, Nov 28 |
|
-- |
-- |
Pre Walk Through (0)
12.05.2022 |
|
|
-- |
-- |
Stain Hardwood Stairs (1)
11.30.2022 |
|
|
-- |
-- |
Cleaning (1)
12.07.2022 |
in process 12/3 |
|
-- |
-- |
Certificate of Occupancy (1)
12.02.2022 |
|
|
-- |
-- |
C.O. to Lender (0)
12.02.2022 |
|
|
-- |
-- |
Schedule Closing (0)
01.25.2023 |
|
|
-- |
-- |
Buyer Walk Through (1)
12.08.2022 |
12/5 11:30am |
|
-- |
-- |
Payment for Upgrades (0)
12.08.2022 |
|
|
-- |
-- |
Keys to Settlement Agent (0)
12.07.2022 |
|
|
-- |
-- |
Review Settlement Statement (0)
01.23.2023 |
|
|
-- |
-- |
Jerry Signs Closing Documents (0)
01.28.2023 |
|
|
-- |
-- |
Request Trash Tote From POA Manager (0)
12.08.2022 |
|
|
-- |
-- |
Closing (1)
01.28.2023 |
Main Street Title Group, Friday Jan 27 |
|
-- |
-- |
Remove Coded Lockbox (0)
01.30.2023 |
|
|