1 33 37 89 47 73 67 55 56 59 57 66 65 64 60 61 62 63 ADDR
CONGERS-2 - 118  ::  1383 Palomino Trail
[ BUILD: 20220401 ]      
CRITICAL PATH   |   INSPECTIONS   |   FLOOR PLANS   |   SELECTIONS   |   SPECS   |   CHANGES   |   NHS
view photo archive
 
--   --   Deck is not standard.
--   --   Deck is not standard. Charge owners 1/2?
--   --   USDA loan - closing approx 20 days after completion
--   --   Amendment #2 Has not signed 11/16
--   --   Cover carpets Jill
--   --  
--   --  
--   --   Side piece of garage needed Davenport - Weatherstripping on left side of exterior garage door
--   --   Powder bath light needed Electrician
--   --   Cabinet drawer needs adjusting. Kitchen drawer to right of oven, Mid South. Thursday-12/9
--   --   Stop spitting sunflower seeds on the carpet!
--   --   Attic cover Painter
--   --   Recover carpet on steps to protect
--   --   Sunflower seeds everywhere on the carpet
--   --   Install attic access panel
--   --   Cut down closet doors rubbing on carpet Painter
--   --   Titan master bathroom escutcheons at showerhead and toilet to wall Tom
--   --   Cover steps Jill
--   --   CODED LOCKBOX 0118
--   --   Fix basement insulation Tom
--   --   Extra screens in foyer Jill
--   --   Adjust kitchen drawer
--   --   drywall seam living room
--   --   remove exposed nail island adn fix Mid South
--   --   tighten light switch to wall living room Electrician not completed 12/31
--   --   Cable box cover Jill
--   --   Paint living room wall Painter
--   --   Fill cracks in steps Painter
--   --   Final paint touch up after drywall repair Painter
--   --   Add PVC board under back door Tom
--   --  
--   --   Towel holder hall bath install
--   --   Paint touch up near stair case
--   --   Parking space client discussion Monday per Jerry
--   --   siding falling off the front of townhouse davenport. Not completed 8/3
-- -- Ratified Contract? (0)  02.16.2022    
-- -- $2500 Deposit Received (0)  02.24.2022    
-- -- Association Packet Requested (0)  02.16.2022    
-- -- Association Packet Received (0)  02.18.2022    
-- -- Selections Meeting (0)  07.16.2022    
-- -- Selections Sheet Signed (0)  08.23.2022     7/16: sent to Kozhin for signatures
-- -- Amendment for Upgrades (B,S,L,T,BCP) (0)  08.31.2022     8/30/2022: sent to Jerry for signature
-- -- Deposit For Upgrades Received (0)  08.30.2022    
-- -- Building Permit (30)  03.06.2022    
-- -- Order Roof & Floor Trusses (1)  06.20.2022    
-- -- Order Windows & Doors (0)  05.03.2022    
-- -- Stake Out Home (1)  03.24.2022    
-- -- Excavate (2)  03.24.2022    
-- -- Inspection (Footers) (1)  03.24.2022    
-- -- Inspection (Concrete Wall) (1)  09.07.2022    
-- -- Pour Footers (1)  03.24.2022    
-- -- Set Forms (2)  04.19.2022    
-- -- Pour Foundation Walls (1)  04.21.2022    
-- -- Plumb Slab (2)  06.06.2022    
-- -- Inspection (Plumbing Under Slab) (1)  06.27.2022    
-- -- Inspection (Conduit Under Slab) (1)  09.07.2022    
-- -- Prepare Slab (1)  03.22.2022    
-- -- Inspection (Slab) (1)  07.05.2022    
-- -- Inspection (Drain Tile) (0)  09.07.2022    
-- -- Pour Slab (1) *   07.05.2022    
-- -- Settlement Agent Confirmed (0)  08.18.2022    
-- -- Framing I (9)  07.25.2022    
-- -- Order Steps (0)  08.22.2022    
-- -- Order Tubs / Showers (0)  06.20.2022    
-- -- Framing II (8)  07.28.2022    
-- -- Framing III (8) *   08.08.2022    
-- -- Verify Window & Roof Structure (0)  07.20.2024    
-- -- Install Stairs (0)  08.22.2022    
-- -- Windows & Doors (0)  08.22.2022    
-- -- House Number and Status in Window (0)  08.22.2022    
-- -- Roofing (0)  09.01.2022    
-- -- Order Cabinets (0)  08.24.2022    
-- -- Order Appliances (0)  08.30.2022     Standard SS
-- -- Deck (0)  09.06.2022    
-- -- Gutters (0)  10.26.2022    
-- -- Driveway (0)  11.09.2022     Expanded Driveway
-- -- Patio (0)  10.11.2022    
-- -- Privacy Divider / Fence (0)  10.22.2022    
-- -- Sod / Seed / Landscaping (0)  11.27.2022    
-- -- HVAC Rough In (4)  08.25.2022    
-- -- Inspection (Rough In HVAC) (1)  09.08.2022    
-- -- Rough In Microwave Vent (0)  07.20.2024    
-- -- Plumbing Rough In (4)  09.01.2022     In process 8/31
-- -- Inspection (Rough In Plumbing) (1)  09.08.2022    
-- -- Electric Rough In (4)  09.06.2022    
-- -- Inspection (Rough In Electric) (1)  09.08.2022    
-- -- Inspection (Deck Piers) (0)  09.08.2022    
-- -- Inspection (Framing) (1)  09.08.2022    
-- -- Exterior Vinyl (0) *   10.19.2022    
-- -- Exterior Stone (0)  11.27.2022     In process 11/19
-- -- Insulation (2)  09.11.2022    
-- -- Inspection (Insulation) (1)  09.15.2022    
-- -- Inspection (Electric Service) (0)  10.27.2022    
-- -- Set Electric Meter (0)  04.11.2023    
-- -- Inspection (Main Sewer Line) (0)  08.29.2022    
-- -- Inspection (Main Water Line) (0)  10.27.2022    
-- -- Order Interior Doors & Trim (0)  10.27.2022    
-- -- Drywall (Hang) (4) *   09.24.2022     In process 9/21
-- -- Loan Approval (0)  09.07.2022    
-- -- Deed Preparation (0)  12.02.2022     After amendment
-- -- Drywall (Tape, Block, Skim, Sand) (6) *   10.19.2022     In process 10/16. Maybe just need to sweep up?
-- -- Paint 1 (1)  10.19.2022    
-- -- Garage Door (0)  10.26.2022    
-- -- House Numbers (0)  11.27.2022    
-- -- Mailbox (0)  11.27.2022    
-- -- Cabinet Installation (2) *   10.26.2022     install 10/24. On site 10/22
-- -- Granite Installation (1) *   11.02.2022    
-- -- Interior Trim - Install (3)  11.09.2022     in process 11/5
-- -- Order Plumbing / Lighting Fixtures (0)  07.20.2024    
-- -- Interior Trim - Paint (1)  11.12.2022     In process 11/9
-- -- Luxury Vinyl Plank (3) *   11.16.2022    
-- -- Luxury Vinyl Tile (0)  11.16.2022    
-- -- Paint 2 (3)  11.27.2022     In process 11/19
-- -- Cover Floors (1)  11.27.2022    
-- -- Deliver Plumbing / Lighting Fixtures (0)  11.27.2022    
-- -- Shoe Moulding (0)  11.19.2022    
-- -- Shelving, Door Knobs, Fire Extinguisher (0)  12.03.2022     Black accessories in process 11/30. Shelving needed. Mirrors too.
-- -- Install Coded Lockbox (add extra keys) (0)  12.05.2022    
-- -- Pay Water / Sewer Taps (0)  10.18.2022    
-- -- Set Water Meter (0)  11.10.2022    
-- -- Electric Trim Out (3)  11.30.2022     Black Standard. 99% completed
-- -- Ceiling Fans (0)  11.27.2022    
-- -- HVAC Trim Out (1)  11.27.2022    
-- -- Blower Door Test (1)  07.20.2024    
-- -- Plumbing Trim Out (2)  11.27.2022     Black Standard
-- -- Install Appliances (0) *   11.30.2022     Everything installed but refrigerator. Maybe awaiting outlet cover behind it?
-- -- Paint 3 (2) *   11.27.2022    
-- -- Carpet (2)  11.27.2022    
-- -- Appraiser Confirms Construction Completion (0)  01.02.2023    
-- -- Inspection (Final HVAC) (1)  12.01.2022    
-- -- Inspection (Final Plumbing) (1)  12.01.2022    
-- -- Inspection (Final Electric) (1)  12.01.2022    
-- -- Inspection (Final Building) (2) *   12.02.2022     Mon, Nov 28
-- -- Pre Walk Through (0)  12.05.2022    
-- -- Stain Hardwood Stairs (1)  11.30.2022    
-- -- Cleaning (1)  12.07.2022     in process 12/3
-- -- Certificate of Occupancy (1) *   12.02.2022    
-- -- C.O. to Lender (0)  12.02.2022    
-- -- Schedule Closing (0)  01.25.2023    
-- -- Buyer Walk Through (1)  12.08.2022     12/5 11:30am
-- -- Payment for Upgrades (0)  12.08.2022    
-- -- Keys to Settlement Agent (0)  12.07.2022    
-- -- Review Settlement Statement (0)  01.23.2023    
-- -- Jerry Signs Closing Documents (0)  01.28.2023    
-- -- Request Trash Tote From POA Manager (0)  12.08.2022    
-- -- Closing (1)  01.28.2023     Main Street Title Group, Friday Jan 27
-- -- Remove Coded Lockbox (0)  01.30.2023