Top of third floor half wall is not square at the corner? |
Tried to capture photos |
|
-- |
-- |
A sizable crack has developed in the sheetrock on the ceiling in the master bedroom. |
Painter, Drywaller |
|
-- |
-- |
To Schedule Repairs: Henry Daugherty 940-704-0855 Ashley Daugherty 718-885-6167 |
|
|
|
-- |
-- |
Can the buyer add an expanded patio? |
|
|
-- |
-- |
Vent microwave!!! 9/17 |
|
|
-- |
-- |
Trash can installed? Door hardware is off as buyer requested |
|
|
-- |
-- |
Farm sink layout but no farm sink |
|
|
-- |
-- |
Drywallers need to sweep |
|
|
-- |
-- |
Standard sink base to be installed on 11/5 |
In process 11/5 |
|
-- |
-- |
Extra cabinet in dining area |
Move somewhere safe |
|
-- |
-- |
Missing cultured marble tops in bathrooms |
In living room/boxed |
|
-- |
-- |
Side splash needed in m bath |
Tom will install |
|
-- |
-- |
Closet framing issue up bedroom |
Jill will tell drywaller to fix |
|
-- |
-- |
Siding falling front left corner |
Davenport |
|
-- |
-- |
Landscaping at back of lot |
to provide visual screen |
|
-- |
-- |
Cover hw treads |
|
|
-- |
-- |
Electric meter |
Mon, Jan 9 |
|
-- |
-- |
Trim garage |
Edgar or Henry |
|
-- |
-- |
Leaking sink |
|
|
-- |
-- |
Cable cover in garage |
Jill or Tom |
|
-- |
-- |
Patch in powder bath light |
Drywaller |
|
-- |
-- |
Hall bath light needed |
Electrician |
|
-- |
-- |
All cable outlets need covered |
Electrician |
|
-- |
-- |
Bath fan needs installed |
Electrician |
|
-- |
-- |
Black shower drain needed |
Plumber |
|
-- |
-- |
Outlet cover needed in kitchen |
Electrician |
|
-- |
-- |
Outdoor vent cover needed on stone in end units |
Davenport, Jeremy |
|
-- |
-- |
Nail holes in white trim need patched |
PVC board between first and second floor, Davenport |
|
-- |
-- |
CODED LOCKBOX |
2121 |
|
-- |
-- |
Two sconces in top stairwell not level? |
Electrician |
|
-- |
-- |
Is the microwave vented? |
Tom is having appliance people fix 1/11 |
|
-- |
-- |
Paint drywall fix in bedroom closet |
Painter |
|
-- |
-- |
Outlets needed on kit island |
Electrician |
|
-- |
-- |
Install cable covers |
|
|
-- |
-- |
Install cable covers |
|
|
-- |
-- |
Install light in hall bathroom |
|
|
-- |
-- |
Install fan in master bathroom |
|
|
-- |
-- |
Install thermostat |
HVAC |
|
-- |
-- |
Patch small hole in stairway wall |
|
|
-- |
-- |
Patch small hole in stairway wall |
Painter |
|
-- |
-- |
Crack in glass globe on left in stairwell |
Sconce |
|
-- |
-- |
Remove overspray paint from cabinets |
|
|
-- |
-- |
Cabinet door for 13 is in kitchen |
Jill will remove |
|
-- |
-- |
Master bath cabinet blemishes |
Jill |
|
-- |
-- |
Put attic cover into place |
Tom or Jill |
|
-- |
-- |
Repaint banister |
Painters |
|
-- |
-- |
Screens |
Jill |
|
-- |
-- |
Master ceiling fan changes colors |
Ask Jill |
|
-- |
-- |
Missing burlap touch up pen needed |
Fred is aware |
|
-- |
-- |
Pressure wash out front and pay |
|
|
-- |
-- |
Pressure wash the front and patio |
Jill or Tom will arrange |
|
-- |
-- |
Remap floors after y |
|
|
-- |
-- |
Remap floors after punch out is complete |
Jill will have done |
|
-- |
-- |
Pad needed in front door gap |
Tom |
|
-- |
-- |
2x4 is crooked in basement bonus room |
Tom will coordinate |
|
-- |
-- |
Baseboard in the garage needs painted |
Painters |
|
-- |
-- |
Clean overspray off of kitchen cabinets |
Painters |
|
-- |
-- |
Remove extra screens from closet under the stairs on main level |
Jill |
|
-- |
-- |
Lots of paint touch ups throughout the home |
Painters |
|
-- |
-- |
Patch hole on landing |
Painters |
|
-- |
-- |
Replace flooring o |
|
|
-- |
-- |
Replace flooring in living room |
Flooring, Eagle, Denny |
|
-- |
-- |
Secure the globe to wall sconce on landing |
Electricians |
|
-- |
-- |
Sand and paint around the bedroom closet |
Painters |
|
-- |
-- |
Master and guest stool are both a little crooked |
Plumber |
|
-- |
-- |
Push pins down on all hinges |
Jill |
|
-- |
-- |
Reclean stool in powder room |
Jill |
|
-- |
-- |
Mud on carpet a few spots |
Jill |
|
-- |
-- |
Trash can door isn’t |
|
|
-- |
-- |
Trash can door isn’t lined up with the drawer above it |
Mid south, Fred |
|
-- |
-- |
Replace flooring |
Kitchen, Flooring, Eagle, Denny |
|
-- |
-- |
Patch/repair hall where sconces were moved |
Drywaller, painter |
|
-- |
-- |
Lightbulb powder bath |
Jill |
|
-- |
-- |
Hall bath electric cover |
After painting |
|
-- |
-- |
|
|
|
-- |
-- |
Clean off patio |
Jill |
|
-- |
-- |
Reclean floors |
|
|
-- |
-- |
LR window missing screen |
Jill |
|
-- |
-- |
Front door awning needs paint touch up |
Davenport, new aluminum wrap around porch supports |
|
-- |
-- |
Concrete needs removed from awning and garage frame |
Jill |
|
-- |
-- |
Paint garage door exterior trim |
Scrape off concrete, use steel wool - Davenport |
|
-- |
-- |
Touch up paint street numbers with chipped paint |
Jill |
|
-- |
-- |
Splash blocks needed (2) |
Tom |
|
-- |
-- |
Remove grey paint from from door trim (painter-blue taped) |
Painter |
|
-- |
-- |
Outside next to bonus room window rusty piece of steel needs painted or removed? |
Break off metal - Tom |
|
-- |
-- |
Paint concrete of house (side/bonus room) |
Painter |
|
-- |
-- |
Light bulb powder bath |
|
|
-- |
-- |
Repaint pantry door |
Painter |
|
-- |
-- |
Paint back door hinge. Top. |
Painter |
|
-- |
-- |
Drywall sconce hole |
|
|
-- |
-- |
Few scuffs bathtub hall |
|
|
-- |
-- |
Paint master bedroom window trim (taped) |
Painter |
|
-- |
-- |
Touch up paint riser on first set of stains |
Stairs - blue taped - Painter |
|
-- |
-- |
More weather stripping on back patio door |
Jill |
|
-- |
-- |
Paint bubbles on window trim MB |
Painter |
|
-- |
-- |
|
|
|
-- |
-- |
Touch up paint |
Painter |
|
-- |
-- |
Crack on wall of master shower |
Wed, Feb 8 - in process |
|
-- |
-- |
New aluminum wrap around porch supports |
Davenport |
|
-- |
-- |
Henry 940-704-0855 |
|
|
-- |
-- |
Siding on the eve over the street side 2nd story window has fallen out. |
Davenport, Jeremy |
|
-- |
-- |
The floor on the 2nd floor next to the stairs has developed a severe soft spot. This is the same spot where our floor had to be replaced due to damage from a heater while painting. |
Denny/Eric |
|
-- |
-- |
The grass between the sidewalk and the street is rutted from a worker driving through the yard with a skid steer. |
Pettit |
|
-- |
-- |
Siding needs to be re-attached |
Davenport, Above living room window |
|
-- |
-- |
Ratified Contract? (0) 02.24.2022 |
|
|
-- |
-- |
$2500 Deposit Received (0) 02.25.2022 |
|
|
-- |
-- |
Association Packet Requested (0) 02.24.2022 |
|
|
-- |
-- |
Association Packet Received (0) 02.25.2022 |
|
|
-- |
-- |
Selections Meeting (0) 03.26.2022 |
|
|
-- |
-- |
Selections Sheet Signed (0) 04.02.2022 |
3/26/2022: Sent to Sam for signatures |
|
-- |
-- |
Amendment for Upgrades (B,S,L,T,BCP) (0) 04.14.2022 |
4/12/2022: sent to Jerry for signatures |
|
-- |
-- |
Deposit For Upgrades Received (0) 04.13.2022 |
|
|
-- |
-- |
Building Permit (30) 03.06.2022 |
|
|
-- |
-- |
Order Roof & Floor Trusses (1) 08.04.2022 |
|
|
-- |
-- |
Order Windows & Doors (0) 05.03.2022 |
|
|
-- |
-- |
Stake Out Home (1) 03.24.2022 |
|
|
-- |
-- |
Excavate (2) 03.24.2022 |
|
|
-- |
-- |
Inspection (Footers) (1) 03.24.2022 |
|
|
-- |
-- |
Inspection (Concrete Wall) (1) 09.07.2022 |
|
|
-- |
-- |
Pour Footers (1) 03.24.2022 |
|
|
-- |
-- |
Set Forms (2) 04.07.2022 |
|
|
-- |
-- |
Pour Foundation Walls (1) 04.07.2022 |
|
|
-- |
-- |
Plumb Slab (2) 06.27.2022 |
|
|
-- |
-- |
Inspection (Plumbing Under Slab) (1) 06.27.2022 |
|
|
-- |
-- |
Inspection (Conduit Under Slab) (1) 09.07.2022 |
|
|
-- |
-- |
Prepare Slab (1) 07.25.2022 |
|
|
-- |
-- |
Inspection (Slab) (1) 08.04.2022 |
|
|
-- |
-- |
Inspection (Drain Tile) (0) 09.07.2022 |
|
|
-- |
-- |
Pour Slab (1) * 08.04.2022 |
July 26 or 27th |
|
-- |
-- |
Settlement Agent Confirmed (0) 08.04.2022 |
|
|
-- |
-- |
Framing I (9) 08.22.2022 |
|
|
-- |
-- |
Order Steps (0) 08.29.2022 |
|
|
-- |
-- |
Order Tubs / Showers (0) 06.20.2022 |
|
|
-- |
-- |
Framing II (8) 09.01.2022 |
|
|
-- |
-- |
Framing III (8) * 09.06.2022 |
|
|
-- |
-- |
Verify Window & Roof Structure (0) 02.01.2024 |
|
|
-- |
-- |
Install Stairs (0) 09.11.2022 |
|
|
-- |
-- |
Windows & Doors (0) 10.24.2022 |
|
|
-- |
-- |
House Number and Status in Window (0) 10.24.2022 |
|
|
-- |
-- |
Roofing (0) 10.03.2022 |
|
|
-- |
-- |
Order Cabinets (0) 09.08.2022 |
|
|
-- |
-- |
Order Appliances (0) 08.30.2022 |
STANDARD |
|
-- |
-- |
Deck (0) 10.16.2022 |
STANDARD |
|
-- |
-- |
Gutters (0) 12.28.2022 |
Davenport |
|
-- |
-- |
Driveway (0) 10.26.2022 |
Expanded Driveway |
|
-- |
-- |
Patio (0) 10.16.2022 |
|
|
-- |
-- |
Privacy Divider / Fence (0) 12.17.2022 |
In process 12/14 |
|
-- |
-- |
Sod / Seed / Landscaping (0) 01.02.2023 |
|
|
-- |
-- |
HVAC Rough In (4) 09.17.2022 |
In process 9/11 |
|
-- |
-- |
Inspection (Rough In HVAC) (1) 09.22.2022 |
|
|
-- |
-- |
Rough In Microwave Vent (0) 02.01.2024 |
|
|
-- |
-- |
Plumbing Rough In (4) 09.22.2022 |
In process 9/17 |
|
-- |
-- |
Inspection (Rough In Plumbing) (1) 09.22.2022 |
|
|
-- |
-- |
Electric Rough In (4) 10.02.2022 |
In process 9/28 |
|
-- |
-- |
Inspection (Rough In Electric) (1) 10.03.2022 |
|
|
-- |
-- |
Inspection (Deck Piers) (0) 09.28.2022 |
|
|
-- |
-- |
Inspection (Framing) (1) 10.03.2022 |
|
|
-- |
-- |
Exterior Vinyl (0) * 12.10.2022 |
In process 11/27 |
|
-- |
-- |
Exterior Stone (0) 12.14.2022 |
In process 12/10 |
|
-- |
-- |
Insulation (2) 10.05.2022 |
|
|
-- |
-- |
Inspection (Insulation) (1) 10.05.2022 |
|
|
-- |
-- |
Inspection (Electric Service) (0) 01.10.2023 |
|
|
-- |
-- |
Set Electric Meter (0) 04.11.2023 |
|
|
-- |
-- |
Inspection (Main Sewer Line) (0) 12.08.2022 |
|
|
-- |
-- |
Inspection (Main Water Line) (0) 12.08.2022 |
|
|
-- |
-- |
Order Interior Doors & Trim (0) 11.27.2022 |
|
|
-- |
-- |
Drywall (Hang) (4) * 10.08.2022 |
NONE |
|
-- |
-- |
Loan Approval (0) 03.30.2022 |
|
|
-- |
-- |
Deed Preparation (0) 11.08.2022 |
|
|
-- |
-- |
Drywall (Tape, Block, Skim, Sand) (6) * 10.29.2022 |
In process 10/26 |
|
-- |
-- |
Paint 1 (1) 10.29.2022 |
|
|
-- |
-- |
Garage Door (0) 12.31.2022 |
Davenport |
|
-- |
-- |
House Numbers (0) 12.27.2022 |
|
|
-- |
-- |
Mailbox (0) 01.07.2023 |
Post up, needs mailbox |
|
-- |
-- |
Cabinet Installation (2) * 10.29.2022 |
10/29 |
|
-- |
-- |
Granite Installation (1) * 11.09.2022 |
Wed, Nov 9 |
|
-- |
-- |
Interior Trim - Install (3) 11.27.2022 |
In process 11/19 |
|
-- |
-- |
Order Plumbing / Lighting Fixtures (0) 02.01.2024 |
|
|
-- |
-- |
Interior Trim - Paint (1) 11.30.2022 |
|
|
-- |
-- |
Luxury Vinyl Plank (3) * 12.10.2022 |
In process 12/7 |
|
-- |
-- |
Luxury Vinyl Tile (0) 12.10.2022 |
In process 12/7 |
|
-- |
-- |
Paint 2 (3) 12.03.2022 |
|
|
-- |
-- |
Cover Floors (1) 01.05.2023 |
|
|
-- |
-- |
Deliver Plumbing / Lighting Fixtures (0) 12.08.2022 |
|
|
-- |
-- |
Shoe Moulding (0) 12.17.2022 |
In process 12/14 |
|
-- |
-- |
Shelving, Door Knobs, Fire Extinguisher (0) 01.02.2023 |
Black accessories, bonus room. In process 12/28 |
|
-- |
-- |
Install Coded Lockbox (add extra keys) (0) 01.02.2023 |
|
|
-- |
-- |
Pay Water / Sewer Taps (0) 12.12.2022 |
|
|
-- |
-- |
Set Water Meter (0) 01.05.2023 |
|
|
-- |
-- |
Electric Trim Out (3) 01.04.2023 |
Black Standard. In process 12/28 |
|
-- |
-- |
Ceiling Fans (0) 12.27.2022 |
|
|
-- |
-- |
HVAC Trim Out (1) 01.11.2023 |
|
|
-- |
-- |
Blower Door Test (1) 02.01.2024 |
|
|
-- |
-- |
Plumbing Trim Out (2) 12.17.2022 |
Black Standard. In process 12/14 |
|
-- |
-- |
Install Appliances (0) * 01.05.2023 |
being installed 1/4 |
|
-- |
-- |
Paint 3 (2) * 12.03.2022 |
|
|
-- |
-- |
Carpet (2) 12.10.2022 |
|
|
-- |
-- |
Appraiser Confirms Construction Completion (0) 01.23.2023 |
Joe Chadwell, Mon, Jan 16 |
|
-- |
-- |
Inspection (Final HVAC) (1) 01.12.2023 |
|
|
-- |
-- |
Inspection (Final Plumbing) (1) 01.12.2023 |
|
|
-- |
-- |
Inspection (Final Electric) (1) 01.12.2023 |
|
|
-- |
-- |
Inspection (Final Building) (2) * 01.20.2023 |
Reinspect, Thu, Jan 19 |
|
-- |
-- |
Pre Walk Through (0) 01.09.2023 |
|
|
-- |
-- |
Stain Hardwood Stairs (1) 12.28.2022 |
|
|
-- |
-- |
Cleaning (1) 01.11.2023 |
Started 1/7 |
|
-- |
-- |
Certificate of Occupancy (1) * 01.20.2023 |
|
|
-- |
-- |
C.O. to Lender (0) 01.20.2023 |
|
|
-- |
-- |
Schedule Closing (0) 01.30.2023 |
|
|
-- |
-- |
Buyer Walk Through (1) 01.12.2023 |
Wed, Jan 11 |
|
-- |
-- |
Payment for Upgrades (0) 01.04.2023 |
|
|
-- |
-- |
Keys to Settlement Agent (0) 01.09.2023 |
|
|
-- |
-- |
Review Settlement Statement (0) 01.30.2023 |
|
|
-- |
-- |
Jerry Signs Closing Documents (0) 01.24.2023 |
|
|
-- |
-- |
Request Trash Tote From POA Manager (0) 01.09.2023 |
|
|
-- |
-- |
Closing (1) 01.30.2023 |
Brittany @ West View Title, Jan 30 |
|
-- |
-- |
Remove Coded Lockbox (0) 02.06.2023 |
|
|