Replace post in master bath |
|
|
-- |
-- |
This house has an oversized patio |
|
|
-- |
-- |
Rotten/broken spot in floor |
|
|
-- |
-- |
Drywall repair needed in garage |
|
|
-- |
-- |
Drywallers need to sweep |
|
|
-- |
-- |
Coffee bar installed in the wrong location |
wrong wall, facing the wrong direction. moving 11/14 |
|
-- |
-- |
Spice rack handle should have been installed horizontally? |
No spice rack is installed. Just standard cabinet. |
|
-- |
-- |
No roll out trays in kitchen |
|
|
-- |
-- |
Final cabinets needs installed |
11/5 install? On site in living room 11/16 |
|
-- |
-- |
Order spice rack? |
Kate will talk to the buyer |
|
-- |
-- |
Spice rack and three drawer stack |
On order |
|
-- |
-- |
Cultured mable tops needed here too |
In living room11/16 |
|
-- |
-- |
Pieces needed at baseboard to make coffee bar look correct? |
|
|
-- |
-- |
|
|
|
-- |
-- |
Handles needed on 3 drawer stack |
Friday, 12/9 |
|
-- |
-- |
Cabinet piece needed by 3 drawer stack |
Filler piece needed, bottom piece, Friday, 12/9 |
|
-- |
-- |
Install coffee bar counter |
|
|
-- |
-- |
|
|
|
-- |
-- |
Do we need side splash on coffee bar? |
On order |
|
-- |
-- |
USDA amendment to be signed by Jerry |
|
|
-- |
-- |
Outlet missing at coffee nook? |
Needed! |
|
-- |
-- |
Trim garage |
Henry or Edgar |
|
-- |
-- |
Cable / electric covers needed in garage |
Jill or Tom |
|
-- |
-- |
Hole in powder bath near light fixture |
Drywaller |
|
-- |
-- |
Black drain needed in shower |
Plumber |
|
-- |
-- |
Digital deadbolt not installed. C did not take keys. |
|
|
-- |
-- |
CODED LOCKBOX 2222 |
|
|
-- |
-- |
Corner siding-are we fixing? |
|
|
-- |
-- |
Electric trim out needed in master bath |
Electrician |
|
-- |
-- |
Powder bath mirror looks crooked |
Joe |
|
-- |
-- |
Touchups mirror powder bath where moved |
Painter |
|
-- |
-- |
Dented fridge |
Replace, Kate will follow up with CJ and Leisa |
|
-- |
-- |
Lightbulb hall bath |
Jill |
|
-- |
-- |
Remove extra drain catcher-thing |
Splash block - Tom |
|
-- |
-- |
Screens under steps |
|
|
-- |
-- |
Clean patio and |
|
|
-- |
-- |
Clean patio and out front |
|
|
-- |
-- |
Paint touch ups throughout home |
Painter |
|
-- |
-- |
Spice rack doesn’t open or close good |
Midsouth, Fred |
|
-- |
-- |
Transition strip going into the bonus room isn’t secure |
Denny |
|
-- |
-- |
Remove extra screens from I |
|
|
-- |
-- |
Remove extra screens from closet under stairs o |
|
|
-- |
-- |
Remove extra screens from basement closet under the stairs |
Jill |
|
-- |
-- |
Front door latch needs adjusted so it latches better |
Tom |
|
-- |
-- |
Crack in frame of LR window |
Tom will look at |
|
-- |
-- |
Hole in the skin of the coffee bar in the cabinet |
Midsouth - Fred will get a new skin |
|
-- |
-- |
Cabinet to the right of the fridge won’t open enough for the pull out drawer to open |
Midsouth - Fred to adjust hinges to open wider. Works fine 1/21 |
|
-- |
-- |
Caulk in the coffee bar |
|
|
-- |
-- |
Caulk the top of the coffee bar at ceiling and crown molding |
Painters |
|
-- |
-- |
Adjust the trash can cabinet door to make it even with the drawer above it |
Midsouth |
|
-- |
-- |
Remove film from pvc board on patio |
Jill |
|
-- |
-- |
Caulk the top of the shower/tubs in all bathrooms |
Painter |
|
-- |
-- |
Couple spots of mud on carpet |
Jill |
|
-- |
-- |
Switch chandeliers |
Electricians- Monday morning. Please call and confirm with electricians |
|
-- |
-- |
Living room electric plate |
|
|
-- |
-- |
Power wash patio |
Jill |
|
-- |
-- |
Exterior door paint touchups |
Painter |
|
-- |
-- |
Fix grade in backyard |
Tom will coordinate |
|
-- |
-- |
Trash can wobbly |
Fred |
|
-- |
-- |
Spice rack adjustment |
Fred |
|
-- |
-- |
Clean sticker off pedestal sink |
Jill |
|
-- |
-- |
Dining floor scratches |
New flooring on order |
|
-- |
-- |
Paint on Master closet carpet and orange mud in master bedroom |
Clean- Jill |
|
-- |
-- |
gallon of gray paint |
Painter |
|
-- |
-- |
Clean sticker off pedestal sink |
|
|
-- |
-- |
Backyard grading issue |
Bub? Install French drain in the spring |
|
-- |
-- |
Primary bedroom fan is installed crooked |
Electrician |
|
-- |
-- |
Front door does not close, seal or lock properly (light can be seen around the edges when closed) |
Jill, Paul |
|
-- |
-- |
there is a gap in the drywall inside the first floor coat closet |
Painter |
|
-- |
-- |
missing light cover on 2nd floor landing |
Jill |
|
-- |
-- |
Excessive creaking in primary bedroom shower |
Jeremiah |
|
-- |
-- |
no caulking around the floor of the primary bedroom shower |
Painter |
|
-- |
-- |
the pantry cabinets next to the refrigerator do not open properly due to the door frame of the pantry |
Fred. Being repaired 3/11 |
|
-- |
-- |
no caulking around kitchen sink where it meets the cabinets |
fred |
|
-- |
-- |
- Guest bathroom vent cover is not properly attached |
Jill- Mast & Brunk |
|
-- |
-- |
Scribe moulding for sink |
Fred |
|
-- |
-- |
Ratified Contract? (0) 03.04.2022 |
|
|
-- |
-- |
$2500 Deposit Received (0) 03.08.2022 |
|
|
-- |
-- |
Association Packet Requested (0) 03.04.2022 |
|
|
-- |
-- |
Association Packet Received (0) 03.05.2022 |
|
|
-- |
-- |
Selections Meeting (0) 04.08.2022 |
|
|
-- |
-- |
Selections Sheet Signed (0) 04.16.2022 |
4/12/2022: sent to Brad for signatures |
|
-- |
-- |
Amendment for Upgrades (B,S,L,T,BCP) (0) 08.19.2022 |
8/18/2022: new version sent to Jerry |
|
-- |
-- |
Deposit For Upgrades Received (0) 04.29.2022 |
|
|
-- |
-- |
Building Permit (30) 03.06.2022 |
|
|
-- |
-- |
Order Roof & Floor Trusses (1) 08.04.2022 |
|
|
-- |
-- |
Order Windows & Doors (0) 05.03.2022 |
|
|
-- |
-- |
Stake Out Home (1) 03.24.2022 |
|
|
-- |
-- |
Excavate (2) 03.24.2022 |
|
|
-- |
-- |
Inspection (Footers) (1) 03.24.2022 |
|
|
-- |
-- |
Inspection (Concrete Wall) (1) 09.07.2022 |
|
|
-- |
-- |
Pour Footers (1) 03.24.2022 |
|
|
-- |
-- |
Set Forms (2) 04.07.2022 |
|
|
-- |
-- |
Pour Foundation Walls (1) 04.07.2022 |
|
|
-- |
-- |
Plumb Slab (2) 06.27.2022 |
|
|
-- |
-- |
Inspection (Plumbing Under Slab) (1) 06.27.2022 |
|
|
-- |
-- |
Inspection (Conduit Under Slab) (1) 09.07.2022 |
|
|
-- |
-- |
Prepare Slab (1) 07.25.2022 |
|
|
-- |
-- |
Inspection (Slab) (1) 08.04.2022 |
|
|
-- |
-- |
Inspection (Drain Tile) (0) 09.07.2022 |
|
|
-- |
-- |
Pour Slab (1) * 08.04.2022 |
|
|
-- |
-- |
Settlement Agent Confirmed (0) 09.10.2022 |
|
|
-- |
-- |
Framing I (9) 08.22.2022 |
|
|
-- |
-- |
Order Steps (0) 08.29.2022 |
|
|
-- |
-- |
Order Tubs / Showers (0) 06.20.2022 |
|
|
-- |
-- |
Framing II (8) 09.01.2022 |
|
|
-- |
-- |
Framing III (8) * 09.06.2022 |
|
|
-- |
-- |
Verify Window & Roof Structure (0) 12.11.2023 |
|
|
-- |
-- |
Install Stairs (0) 10.03.2022 |
|
|
-- |
-- |
Windows & Doors (0) 10.03.2022 |
|
|
-- |
-- |
House Number and Status in Window (0) 10.24.2022 |
|
|
-- |
-- |
Roofing (0) 10.03.2022 |
|
|
-- |
-- |
Order Cabinets (0) 09.06.2022 |
|
|
-- |
-- |
Order Appliances (0) 08.30.2022 |
Standard |
|
-- |
-- |
Deck (0) 10.16.2022 |
STANDARD |
|
-- |
-- |
Gutters (0) 12.28.2022 |
|
|
-- |
-- |
Driveway (0) 10.26.2022 |
Expanded Driveway |
|
-- |
-- |
Patio (0) 10.16.2022 |
|
|
-- |
-- |
Privacy Divider / Fence (0) 12.17.2022 |
|
|
-- |
-- |
Sod / Seed / Landscaping (0) 12.31.2022 |
|
|
-- |
-- |
HVAC Rough In (4) 09.17.2022 |
|
|
-- |
-- |
Inspection (Rough In HVAC) (1) 09.22.2022 |
|
|
-- |
-- |
Rough In Microwave Vent (0) 12.11.2023 |
|
|
-- |
-- |
Plumbing Rough In (4) 09.21.2022 |
In process 9/17 |
|
-- |
-- |
Inspection (Rough In Plumbing) (1) 09.22.2022 |
|
|
-- |
-- |
Electric Rough In (4) 10.02.2022 |
|
|
-- |
-- |
Inspection (Rough In Electric) (1) 10.05.2022 |
|
|
-- |
-- |
Inspection (Deck Piers) (0) 10.03.2022 |
|
|
-- |
-- |
Inspection (Framing) (1) 10.05.2022 |
|
|
-- |
-- |
Exterior Vinyl (0) * 12.10.2022 |
In process 11/27 |
|
-- |
-- |
Exterior Stone (0) 04.14.2022 |
|
|
-- |
-- |
Insulation (2) 10.08.2022 |
|
|
-- |
-- |
Inspection (Insulation) (1) 10.16.2022 |
|
|
-- |
-- |
Inspection (Electric Service) (0) 01.10.2023 |
|
|
-- |
-- |
Set Electric Meter (0) 04.11.2023 |
|
|
-- |
-- |
Inspection (Main Sewer Line) (0) 12.08.2022 |
|
|
-- |
-- |
Inspection (Main Water Line) (0) 12.08.2022 |
|
|
-- |
-- |
Order Interior Doors & Trim (0) 12.08.2022 |
|
|
-- |
-- |
Drywall (Hang) (4) * 10.16.2022 |
NONE |
|
-- |
-- |
Loan Approval (0) 04.16.2022 |
|
|
-- |
-- |
Deed Preparation (0) 12.01.2022 |
|
|
-- |
-- |
Drywall (Tape, Block, Skim, Sand) (6) * 10.29.2022 |
In process 10/26 |
|
-- |
-- |
Paint 1 (1) 10.29.2022 |
|
|
-- |
-- |
Garage Door (0) 12.31.2022 |
|
|
-- |
-- |
House Numbers (0) 12.27.2022 |
|
|
-- |
-- |
Mailbox (0) 01.07.2023 |
Post up, needs mailbox |
|
-- |
-- |
Cabinet Installation (2) * 11.02.2022 |
10/29. On site 10/29 |
|
-- |
-- |
Granite Installation (1) * 11.27.2022 |
Monday 11/21 |
|
-- |
-- |
Interior Trim - Install (3) 12.03.2022 |
In process 11/30 |
|
-- |
-- |
Order Plumbing / Lighting Fixtures (0) 12.11.2023 |
|
|
-- |
-- |
Interior Trim - Paint (1) 12.03.2022 |
|
|
-- |
-- |
Luxury Vinyl Plank (3) * 12.14.2022 |
week of 12/5 |
|
-- |
-- |
Luxury Vinyl Tile (0) 12.14.2022 |
|
|
-- |
-- |
Paint 2 (3) 12.07.2022 |
|
|
-- |
-- |
Cover Floors (1) 12.31.2022 |
|
|
-- |
-- |
Deliver Plumbing / Lighting Fixtures (0) 12.08.2022 |
|
|
-- |
-- |
Shoe Moulding (0) 12.28.2022 |
|
|
-- |
-- |
Shelving, Door Knobs, Fire Extinguisher (0) 12.31.2022 |
Black accessories |
|
-- |
-- |
Install Coded Lockbox (add extra keys) (0) 01.06.2023 |
|
|
-- |
-- |
Pay Water / Sewer Taps (0) 12.12.2022 |
|
|
-- |
-- |
Set Water Meter (0) 01.05.2023 |
|
|
-- |
-- |
Electric Trim Out (3) 01.07.2023 |
Black Standard. In process 1/4 |
|
-- |
-- |
Ceiling Fans (0) 12.31.2022 |
Living Room |
|
-- |
-- |
HVAC Trim Out (1) 01.11.2023 |
|
|
-- |
-- |
Blower Door Test (1) 12.11.2023 |
|
|
-- |
-- |
Plumbing Trim Out (2) 12.28.2022 |
UPGRADE Black Farmhouse. Started 12/17 |
|
-- |
-- |
Install Appliances (0) * 01.05.2023 |
being installed 1/4 |
|
-- |
-- |
Paint 3 (2) * 12.07.2022 |
|
|
-- |
-- |
Carpet (2) 12.17.2022 |
In process 12/14 |
|
-- |
-- |
Appraiser Confirms Construction Completion (0) 01.19.2023 |
Mike Shirfey - Mon, Jan 16, noon |
|
-- |
-- |
Inspection (Final HVAC) (1) 01.12.2023 |
|
|
-- |
-- |
Inspection (Final Plumbing) (1) 01.12.2023 |
|
|
-- |
-- |
Inspection (Final Electric) (1) 01.12.2023 |
|
|
-- |
-- |
Inspection (Final Building) (2) * 01.16.2023 |
Reinspect, Friday, Jan 13 |
|
-- |
-- |
Pre Walk Through (0) 01.12.2023 |
|
|
-- |
-- |
Stain Hardwood Stairs (1) 12.28.2022 |
|
|
-- |
-- |
Cleaning (1) 01.11.2023 |
|
|
-- |
-- |
Certificate of Occupancy (1) * 01.17.2023 |
|
|
-- |
-- |
C.O. to Lender (0) 01.17.2023 |
|
|
-- |
-- |
Schedule Closing (0) 01.17.2023 |
|
|
-- |
-- |
Buyer Walk Through (1) 01.16.2023 |
Friday, Jan 13, 3PM |
|
-- |
-- |
Payment for Upgrades (0) 01.04.2023 |
|
|
-- |
-- |
Keys to Settlement Agent (0) 01.09.2023 |
|
|
-- |
-- |
Review Settlement Statement (0) 01.23.2023 |
|
|
-- |
-- |
Jerry Signs Closing Documents (0) 01.20.2023 |
|
|
-- |
-- |
Request Trash Tote From POA Manager (0) 01.10.2023 |
|
|
-- |
-- |
Closing (1) 01.21.2023 |
Cheryl Payne, Clark & Bradshaw |
|
-- |
-- |
Remove Coded Lockbox (0) 01.26.2023 |
|
|