37 ADDR
CONGERS-2 - 26  ::  1444 Palomino Trail
[ BUILD: 20221382 ]      
CRITICAL PATH   |   INSPECTIONS   |   FLOOR PLANS   |   SELECTIONS   |   SPECS   |   CHANGES   |   NHS
view photo archive
 
TO DO
---
UPGRADES
---
CRITICAL PATH
    Verify Window & Roof Structure (0)      
    Rough In Microwave Vent (0)      
    Order Plumbing / Lighting Fixtures (0)      
Tue    Feb 3      Blower Door Test (1)      
TO DO - COMPLETED OR DELETED
Add egress window to selection sheet?
H/w treads to second level installed
H/w treads to 2nd level
Fix upper stairs cover
CODED LOCKBOX 2626
Was rough in plumbing tub location adjusted? Tom. Does it have to be patched?
Roof vinyl piece needed Davenport
Mirrors Joe
Outlet cover needed kitchen Electrician
Ceiling fan needed in master Electrician
Stair transition is knocked Knicked, Denny. It appears that somebody tried to patch it?
repaint stairs painter
Fascia on side bump out Davenport
Cable covers needed in all garages Electrician
Final touch up needed at stairs Painter
Black shower drain needed Plumber. Still needs done 3/15
Stain on stairs Jill
Missing aluminum behind gutter at back corner of townhouse Davenport
Outdoor electric trim out missing Electrician
Remove siding from garage Davenport
Stair railings needed Trim guys? Painter
Final touch up? Painter
Three single electric meters Waiting on trough
Right side of vertical trim on island needs to be cleaned or replaced. May 9
Escutcheon behind pedestal sink is wonkie Plumber - not level on base
Drywall patch next to vanity light in powder bath In process. Needs painting. 4/5
Should the bowl on the pedestal sink because opt to the bottom part? Looks like there’s a gap
Gap between bowl of pedestal sink and stand. Should this be caulked? Painter
clean
Does something need to be hooked up at the garage door opener? Lots of wires. Jeff - Davenport
Trim out basement window PVC trim - Jeremy, Davenport
Stain on the steps Painter
Electric cover, needed and foyer. A few electric covers needed and foyer and light switch as well. Electrician
Powder bath touch up light Painter
Clean out garage and the bonus room Jill
Install window screens Jill
Remove paint from kitchen cabinetry Painter
Remove black paper from the back patio Jill
Address kitchen miters where the shoe in the cabinet trim meet on both the right and left hand side of perimeter cabinets Trim guy
Cock inside splashes in master and hall bath vanity
Install window screens
Several cabinet touchups on master vanity Jill
Paint the ceiling in bedroom number two Painter
Adjust closet doors in bedroom number two Jill
Fix crack in upstairs hall bath tub Repair scheduled for Monday may 1st
Replace island right side trim and side panel for island May 9
Pocket door adjustment in pantry Edgar
Finish installing the drainage pipe in the back/side yard Bub
Pressure wash front and back Tom will coordinate
Remove black plastic from under the siding at the back patio Jill
Reclean services in floors after punch out complete Jill or Lynn
Fridge panel too short on the kitchen perimeter. Does this need to be replaced or can it be covered by shoe mold? Edgar
Caulk inside splashes in master and hall bath vanity Painter
Clean paint off of base of cabinets in kitchen Jill
Paint exposed exterior concrete wall Painter
Trim metallic tape on basement bonus window Jill
Paint touch up
Paint outside of foundation
Final grading and sod
Window AC unit
UPGRADES - COMPLETED
    Double Waste Basket in Island  
    Roll Out Trays in 18  
    Roll Out Trays in 36  
    Luxury Vinyl Plank - Upper Level  
    Expanded Driveway  
    Painted Steps to Upper Level  
    Egress Window in Bonus Room  
    Amendment to increase price by $8,040  
CRITICAL PATH - COMPLETED
-- -- Ratified Contract? (0)  04.08.2022    
-- -- $2500 Deposit Received (0)  04.13.2022    
-- -- Association Packet Requested (0)  04.08.2022    
-- -- Association Packet Received (0)  04.13.2022    
-- -- Selections Meeting (0)  04.28.2022    
-- -- Selections Sheet Signed (0)  04.30.2022     4/28/2022: Sent to Kristo for signatures
-- -- Amendment for Upgrades (B,S,L,T,BCP) (0)  05.12.2022     4/30/2022: sent to Kristo for signature
-- -- Deposit For Upgrades Received (0)  05.12.2022    
-- -- Building Permit (30) *   07.22.2022    
-- -- Order Roof & Floor Trusses (1)  09.08.2022    
-- -- Order Windows & Doors (0)  09.08.2022    
-- -- Stake Out Home (1)  07.28.2022    
-- -- Excavate (2)  08.08.2022    
-- -- Inspection (Footers) (1)  08.08.2022    
-- -- Inspection (Concrete Wall) (1)  09.07.2022    
-- -- Pour Footers (1) *   08.08.2022    
-- -- Set Forms (2)  08.08.2022    
-- -- Pour Foundation Walls (1)  08.15.2022    
-- -- Plumb Slab (2)  09.06.2022    
-- -- Inspection (Plumbing Under Slab) (1)  09.06.2022    
-- -- Inspection (Conduit Under Slab) (1)  09.08.2022    
-- -- Prepare Slab (1)  09.06.2022    
-- -- Inspection (Slab) (1)  09.08.2022    
-- -- Inspection (Drain Tile) (0)  10.10.2022    
-- -- Pour Slab (1) *   09.12.2022    
-- -- Settlement Agent Confirmed (0)  02.01.2023    
-- -- Framing I (9)  09.29.2022    
-- -- Order Steps (0)  10.10.2022    
-- -- Order Tubs / Showers (0)  10.10.2022    
-- -- Framing II (8)  10.09.2022    
-- -- Framing III (8) *   10.17.2022    
-- -- Install Stairs (0) *   11.19.2022    
-- -- Windows & Doors (0) *   11.19.2022    
-- -- House Number and Status in Window (0)  01.07.2023    
-- -- Roofing (0) *   11.19.2022    
-- -- Order Cabinets (0)  11.22.2022    
-- -- Order Appliances (0)  08.30.2022     Standard
-- -- Deck (0)  11.19.2022     Standard
-- -- Gutters (0)  03.06.2023    
-- -- Driveway (0) *   02.08.2023     Expanded Driveway
-- -- Patio (0)  01.01.2023     Standard
-- -- Privacy Divider / Fence (0) *   02.08.2023    
-- -- Sod / Seed / Landscaping (0)  04.23.2023     In process 4/12
-- -- HVAC Rough In (4)  11.09.2022     In process 11/2
-- -- Plumbing Rough In (4)  11.19.2022     In process 11/16
-- -- Electric Rough In (4)  11.30.2022     almost completed 11/26
-- -- Inspection (Rough In HVAC) (1)  12.07.2022    
-- -- Inspection (Rough In Plumbing) (1)  12.07.2022     11/17
-- -- Inspection (Rough In Electric) (1)  12.07.2022    
-- -- Inspection (Framing) (1) *   12.07.2022    
-- -- Inspection (Deck Piers) (0)  02.13.2023    
-- -- Exterior Vinyl (0) *   02.15.2023     almost completed 2/11
-- -- Exterior Stone (0)  03.15.2023     in process 2/25
-- -- Insulation (2) *   12.07.2022    
-- -- Inspection (Insulation) (1)  12.17.2022    
-- -- Inspection (Electric Service) (0)  04.06.2023     Hopefully Tuesday, Mar 28
-- -- Set Electric Meter (0) *   04.20.2023    
-- -- Inspection (Main Sewer Line) (0)  02.13.2023    
-- -- Inspection (Main Water Line) (0)  02.13.2023    
-- -- Order Interior Doors & Trim (0)  12.08.2022    
-- -- Drywall (Hang) (4) *   12.17.2022     NONE
-- -- Loan Approval (0)  03.05.2023    
-- -- Deed Preparation (0)  03.05.2023    
-- -- Drywall (Tape, Block, Skim, Sand) (6) *   01.07.2023     In process 1/1
-- -- Paint 1 (1)  01.07.2023    
-- -- Garage Door (0)  03.15.2023    
-- -- House Numbers (0)  03.01.2023    
-- -- Mailbox (0)  02.20.2023    
-- -- Cabinet Installation (2) *   01.07.2023     Jan 6
-- -- Granite Installation (1) *   01.14.2023    
-- -- Interior Trim - Install (3) *   01.18.2023     1/14
-- -- Interior Trim - Paint (1)  01.21.2023     In process 1/18
-- -- Luxury Vinyl Plank (3) *   02.01.2023     In process 1/28
-- -- Luxury Vinyl Tile (0)  02.01.2023     In process 1/28
-- -- Paint 2 (3)  01.25.2023    
-- -- Cover Floors (0)  02.06.2023    
-- -- Deliver Plumbing / Lighting Fixtures (0)  02.13.2023    
-- -- Shoe Moulding (0)  02.08.2023    
-- -- Shelving, Door Knobs, Fire Extinguisher (1) *   02.15.2023     Black accessories. In process 2/11. Needs mirrors.
-- -- Install Coded Lockbox (add extra keys) (0)  02.15.2023    
-- -- Pay Water / Sewer Taps (0)  02.16.2023    
-- -- Set Water Meter (1) *   03.16.2023    
-- -- Electric Trim Out (3) *   02.15.2023     Black Standard. In process 2/11
-- -- Ceiling Fans (0)  03.15.2023    
-- -- HVAC Trim Out (1) *   02.18.2023    
-- -- Plumbing Trim Out (2) *   02.08.2023     Black standard. In process 2/4
-- -- Install Appliances (0) *   03.15.2023     Delivery 10/31- Schedule install with CJ
-- -- Paint 3 (2) *   01.25.2023    
-- -- Carpet (2)  02.01.2023    
-- -- Appraiser Confirms Construction Completion (0)  03.05.2023    
-- -- Inspection (Final HVAC) (0)  04.22.2023    
-- -- Inspection (Final Plumbing) (0)  04.22.2023    
-- -- Inspection (Final Electric) (0)  04.22.2023    
-- -- Inspection (Final Building) (4) *   04.22.2023    
-- -- Pre Walk Through (0)  04.20.2023    
-- -- Stain Hardwood Stairs (1) *   03.15.2023     In process 2/25
-- -- Cleaning (1)  04.23.2023    
-- -- Certificate of Occupancy (1) *   04.25.2023    
-- -- C.O. to Lender (0)  04.25.2023    
-- -- Schedule Closing (0)  05.01.2023    
-- -- Buyer Walk Through (1) *   04.25.2023     Monday, April 24, 11:45 AM
-- -- Payment for Upgrades (0)  03.05.2023    
-- -- Keys to Settlement Agent (0)  04.20.2023    
-- -- Review Settlement Statement (0)  05.04.2023    
-- -- Jerry Signs Closing Documents (0)  05.04.2023    
-- -- Request Trash Tote From POA Manager (0)  04.20.2023    
-- -- Closing (1)  05.04.2023     Brittany @ West View Title
-- -- Remove Coded Lockbox (0)  05.22.2023