| TO DO | ||||
| --- | ||||
| UPGRADES | ||||
| Luxury Vinyl Plank Upstairs | ||||
| CRITICAL PATH | ||||
| --- | ||||
| TO DO - COMPLETED OR DELETED | ||||
| UPGRADES - COMPLETED | ||||
| Shower Door Black Trim | ||||
| Painted Carpet Grade Stairs | ||||
| Spice Rack | ||||
| Three Drawer Stack | ||||
| Expanded Deck 12 x 12 | ||||
| Expanded Driveway | ||||
| Bonus Room Window Included Per Floorplans | ||||
| Microwave Vented to Exterior | ||||
| Finish Bonus Bath | ||||
| Amendment to increase price by $15,100 | ||||
| CRITICAL PATH - COMPLETED | ||||
| -- | -- | Inspection (Footers) (1) 09.07.2022 | ||
| -- | -- | Inspection (Concrete Wall) (1) 09.07.2022 | ||
| -- | -- | Inspection (Plumbing Under Slab) (1) 09.08.2022 | ||
| -- | -- | Inspection (Conduit Under Slab) (1) 09.08.2022 | ||
| -- | -- | Inspection (Slab) (1) 09.22.2022 | ||
| -- | -- | Inspection (Drain Tile) (0) 10.10.2022 | ||
| -- | -- | Inspection (Rough In HVAC) (1) 12.03.2022 | ||
| -- | -- | Inspection (Rough In Plumbing) (1) 12.27.2022 | ||
| -- | -- | Inspection (Rough In Electric) (1) 12.27.2022 | ||
| -- | -- | Inspection (Framing) (1) * 12.27.2022 | ||
| -- | -- | Inspection (Deck Piers) (0) 12.27.2022 | ||
| -- | -- | Inspection (Insulation) (1) 12.29.2022 | ||
| -- | -- | Inspection (Electric Service) (0) 04.05.2023 | ||
| -- | -- | Inspection (Main Sewer Line) (0) 03.16.2023 | ||
| -- | -- | Inspection (Main Water Line) (0) 03.16.2023 | ||
| -- | -- | Inspection (Final HVAC) (0) 04.08.2023 | ||
| -- | -- | Inspection (Final Plumbing) (0) 04.08.2023 | ||
| -- | -- | Inspection (Final Electric) (0) 04.08.2023 | ||
| -- | -- | Inspection (Final Building) (4) * 04.08.2023 | ||