Missing cabinet hardware 3/29 |
|
|
-- |
-- |
They have 5-piece cabinetry in kitchen |
|
|
-- |
-- |
Need vanity tops |
|
|
-- |
-- |
Paint all over front porch black aluminum wrap |
Painter |
|
-- |
-- |
Needs flooring in back bonus room |
|
|
-- |
-- |
Cover carpet |
Jill |
|
-- |
-- |
Pedestal sink needed |
|
|
-- |
-- |
Large scratch on fridge |
CJ has parts and will repair 7/31 or 8/1 |
|
-- |
-- |
Nickel dining light should be black |
Electrician - on order |
|
-- |
-- |
Hall bath light receptacle needed |
Electrician |
|
-- |
-- |
Push oven into place |
|
|
-- |
-- |
Few electrical items need completed |
Smoke det in bonus room. Powder light. |
|
-- |
-- |
Mirrors needed |
|
|
-- |
-- |
CODED LOCKBOX 2828 |
|
|
-- |
-- |
Needs a few receptacle covers in kitchen |
Electrician |
|
-- |
-- |
Install door to closet under staircase |
Tom |
|
-- |
-- |
Install shelving in bonus room |
Paul |
|
-- |
-- |
Trim in garages |
Henry |
|
-- |
-- |
Gaps in trim around garage door |
|
|
-- |
-- |
Install PVC board behind weather stripping at garage door |
Davenport |
|
-- |
-- |
Door installed at closet under staircase needs handle |
Paul |
|
-- |
-- |
Home Inspection - Friday, June 23 |
|
|
-- |
-- |
Screen door to back patio needs adjustment |
Tom. I think repaired 6/28 |
|
-- |
-- |
Buyer has question about supply duct in unfinished portion of the basement |
|
|
-- |
-- |
Top floor hall bathroom shower head leaks at the shower head connection to the supply pipe |
Plumber |
|
-- |
-- |
Basement door into unfinished area does not latch |
Jill or Tom |
|
-- |
-- |
Touch up paint powder bath light |
Painter |
|
-- |
-- |
Finish touch up paint |
Painter |
|
-- |
-- |
Paint on aluminum support post under roof |
Jeremy - Davenport |
|
-- |
-- |
Ratified Contract? (0) 08.12.2022 |
|
|
-- |
-- |
$2500 Deposit Received (0) 08.16.2022 |
|
|
-- |
-- |
Association Packet Requested (0) 08.14.2022 |
|
|
-- |
-- |
Association Packet Received (0) 08.14.2022 |
|
|
-- |
-- |
Selections Meeting (0) 08.21.2022 |
|
|
-- |
-- |
Selections Sheet Signed (0) 08.24.2022 |
8/21/2022: sent to Katie for signatures |
|
-- |
-- |
Amendment for Upgrades (B,S,L,T,BCP) (0) 08.31.2022 |
8/30/2022: sent to Jerry for signatures |
|
-- |
-- |
Deposit For Upgrades Received (0) 08.30.2022 |
|
|
-- |
-- |
Building Permit (30) 08.15.2022 |
|
|
-- |
-- |
Order Roof & Floor Trusses (1) 11.03.2022 |
|
|
-- |
-- |
Order Windows & Doors (0) 11.03.2022 |
|
|
-- |
-- |
Stake Out Home (1) 09.26.2022 |
|
|
-- |
-- |
Excavate (2) 09.29.2022 |
|
|
-- |
-- |
Inspection (Footers) (1) 10.09.2022 |
|
|
-- |
-- |
Inspection (Concrete Wall) (1) 10.09.2022 |
|
|
-- |
-- |
Pour Footers (1) 10.09.2022 |
|
|
-- |
-- |
Set Forms (2) 10.31.2022 |
|
|
-- |
-- |
Pour Foundation Walls (1) 11.03.2022 |
|
|
-- |
-- |
Plumb Slab (2) 12.01.2022 |
|
|
-- |
-- |
Inspection (Plumbing Under Slab) (1) 12.05.2022 |
|
|
-- |
-- |
Inspection (Conduit Under Slab) (1) 12.08.2022 |
|
|
-- |
-- |
Prepare Slab (1) 12.08.2022 |
|
|
-- |
-- |
Inspection (Slab) (1) 12.27.2022 |
|
|
-- |
-- |
Inspection (Drain Tile) (0) 12.27.2022 |
|
|
-- |
-- |
Pour Slab (1) * 12.27.2022 |
|
|
-- |
-- |
Settlement Agent Confirmed (0) 08.25.2022 |
|
|
-- |
-- |
Framing I (9) 01.05.2023 |
|
|
-- |
-- |
Order Steps (0) 02.02.2023 |
|
|
-- |
-- |
Order Tubs / Showers (0) 02.18.2023 |
|
|
-- |
-- |
Framing II (8) 01.12.2023 |
|
|
-- |
-- |
Framing III (8) * 01.30.2023 |
|
|
-- |
-- |
Verify Window & Roof Structure (0) 09.12.2024 |
|
|
-- |
-- |
Install Stairs (0) 02.02.2023 |
|
|
-- |
-- |
Windows & Doors (0) 02.18.2023 |
|
|
-- |
-- |
House Number and Status in Window (0) 02.22.2023 |
|
|
-- |
-- |
Roofing (0) 02.18.2023 |
|
|
-- |
-- |
Order Cabinets (0) 03.02.2023 |
|
|
-- |
-- |
Order Appliances (0) 05.06.2023 |
French Upgrade |
|
-- |
-- |
Deck (0) 04.01.2023 |
NONE |
|
-- |
-- |
Gutters (0) 04.01.2023 |
|
|
-- |
-- |
Driveway (0) 04.26.2023 |
Expanded Driveway |
|
-- |
-- |
Patio (0) 04.01.2023 |
Standard |
|
-- |
-- |
Privacy Divider / Fence (0) 06.11.2023 |
|
|
-- |
-- |
Sod / Seed / Landscaping (0) 06.26.2023 |
Pettit |
|
-- |
-- |
HVAC Rough In (4) 02.18.2023 |
In process 2/15 |
|
-- |
-- |
Inspection (Rough In HVAC) (1) 02.27.2023 |
|
|
-- |
-- |
Rough In Microwave Vent (0) 09.12.2024 |
|
|
-- |
-- |
Plumbing Rough In (4) 02.18.2023 |
In process 2/15 |
|
-- |
-- |
Inspection (Rough In Plumbing) (1) 02.27.2023 |
|
|
-- |
-- |
Electric Rough In (4) 02.27.2023 |
In process 2/22 |
|
-- |
-- |
Inspection (Rough In Electric) (1) 02.27.2023 |
|
|
-- |
-- |
Inspection (Deck Piers) (0) 02.27.2023 |
|
|
-- |
-- |
Inspection (Framing) (1) 02.27.2023 |
|
|
-- |
-- |
Exterior Vinyl (0) * 04.01.2023 |
|
|
-- |
-- |
Exterior Stone (0) 04.03.2023 |
|
|
-- |
-- |
Insulation (2) 02.27.2023 |
|
|
-- |
-- |
Inspection (Insulation) (1) 03.06.2023 |
|
|
-- |
-- |
Inspection (Electric Service) (0) 06.12.2023 |
|
|
-- |
-- |
Set Electric Meter (0) 06.16.2023 |
|
|
-- |
-- |
Inspection (Main Sewer Line) (0) 03.20.2023 |
|
|
-- |
-- |
Inspection (Main Water Line) (0) 03.20.2023 |
|
|
-- |
-- |
Order Interior Doors & Trim (0) 04.12.2023 |
|
|
-- |
-- |
Drywall (Hang) (4) * 03.15.2023 |
In process 3/8 |
|
-- |
-- |
Loan Approval (0) 06.12.2023 |
|
|
-- |
-- |
Deed Preparation (0) 06.01.2023 |
|
|
-- |
-- |
Drywall (Tape, Block, Skim, Sand) (6) * 04.01.2023 |
In process 3/29. Needs final sanding. |
|
-- |
-- |
Paint 1 (1) 04.01.2023 |
|
|
-- |
-- |
Garage Door (0) 04.23.2023 |
|
|
-- |
-- |
House Numbers (0) 05.06.2023 |
|
|
-- |
-- |
Mailbox (0) 05.20.2023 |
|
|
-- |
-- |
Cabinet Installation (2) * 03.29.2023 |
Sat, April 1 |
|
-- |
-- |
Granite Installation (1) * 04.12.2023 |
|
|
-- |
-- |
Interior Trim - Install (3) 04.23.2023 |
In process 4/19 |
|
-- |
-- |
Order Plumbing / Lighting Fixtures (0) 07.26.2023 |
|
|
-- |
-- |
Interior Trim - Paint (1) 04.29.2023 |
Prepping to paint 4/26 |
|
-- |
-- |
Luxury Vinyl Plank (3) * 05.03.2023 |
In process 4/29 |
|
-- |
-- |
Luxury Vinyl Tile (0) 05.03.2023 |
|
|
-- |
-- |
Paint 2 (3) 04.05.2023 |
|
|
-- |
-- |
Cover Floors (1) 05.24.2023 |
|
|
-- |
-- |
Deliver Plumbing / Lighting Fixtures (0) 04.27.2023 |
|
|
-- |
-- |
Shoe Moulding (0) 05.06.2023 |
In process 5/3 |
|
-- |
-- |
Shelving, Door Knobs, Fire Extinguisher (0) 06.03.2023 |
Black accessories In process. Needs mirrors 5/24 |
|
-- |
-- |
Install Coded Lockbox (add extra keys) (0) 06.03.2023 |
|
|
-- |
-- |
Pay Water / Sewer Taps (0) 05.01.2023 |
|
|
-- |
-- |
Set Water Meter (0) 05.11.2023 |
|
|
-- |
-- |
Electric Trim Out (3) 05.24.2023 |
Black Lighting. In process 5/17. Needs variety of receptacle covers |
|
-- |
-- |
Ceiling Fans (0) 05.20.2023 |
LR and Painted UP BR. In process 5/10 |
|
-- |
-- |
HVAC Trim Out (1) 05.10.2023 |
|
|
-- |
-- |
Blower Door Test (1) 09.12.2024 |
|
|
-- |
-- |
Plumbing Trim Out (2) 05.06.2023 |
Black Plumbing |
|
-- |
-- |
Install Appliances (0) * 05.10.2023 |
|
|
-- |
-- |
Paint 3 (2) * 05.17.2023 |
|
|
-- |
-- |
Carpet (2) 05.03.2023 |
|
|
-- |
-- |
Appraiser Confirms Construction Completion (0) 06.26.2023 |
Joe Chadwell |
|
-- |
-- |
Inspection (Final HVAC) (1) 06.26.2023 |
|
|
-- |
-- |
Inspection (Final Plumbing) (1) 06.26.2023 |
|
|
-- |
-- |
Inspection (Final Electric) (1) 06.26.2023 |
|
|
-- |
-- |
Inspection (Final Building) (2) * 06.26.2023 |
June 22 |
|
-- |
-- |
Pre Walk Through (0) 06.26.2023 |
|
|
-- |
-- |
Stain Hardwood Stairs (1) 06.26.2023 |
In process 5/24 |
|
-- |
-- |
Cleaning (1) 06.28.2023 |
|
|
-- |
-- |
Certificate of Occupancy (1) * 06.27.2023 |
|
|
-- |
-- |
C.O. to Lender (0) 06.27.2023 |
|
|
-- |
-- |
Schedule Closing (0) 06.26.2023 |
|
|
-- |
-- |
Buyer Walk Through (1) 06.27.2023 |
Monday, June 26, 5:45 PM |
|
-- |
-- |
Payment for Upgrades (0) 06.26.2023 |
|
|
-- |
-- |
Keys to Settlement Agent (0) 06.26.2023 |
|
|
-- |
-- |
Review Settlement Statement (0) 06.27.2023 |
|
|
-- |
-- |
Jerry Signs Closing Documents (0) 03.10.2023 |
|
|
-- |
-- |
Request Trash Tote From POA Manager (0) 06.22.2023 |
|
|
-- |
-- |
Closing (1) 06.29.2023 |
Brittany @ West View Title, Wed June 28 |
|
-- |
-- |
Remove Coded Lockbox (0) 07.10.2023 |
|
|