37 ADDR
CONGERS-2 - 28  ::  1468 Palomino Trail
[ BUILD: 20221530 ]      
CRITICAL PATH   |   INSPECTIONS   |   FLOOR PLANS   |   SELECTIONS   |   SPECS   |   CHANGES   |   NHS
view photo archive
 
TO DO
---
UPGRADES
---
CRITICAL PATH
---
TO DO - COMPLETED OR DELETED
Missing cabinet hardware 3/29
They have 5-piece cabinetry in kitchen
Need vanity tops
Paint all over front porch black aluminum wrap Painter
Needs flooring in back bonus room
Cover carpet Jill
Pedestal sink needed
Large scratch on fridge CJ has parts and will repair 7/31 or 8/1
Nickel dining light should be black Electrician - on order
Hall bath light receptacle needed Electrician
Push oven into place
Few electrical items need completed Smoke det in bonus room. Powder light.
Mirrors needed
CODED LOCKBOX 2828
Needs a few receptacle covers in kitchen Electrician
Install door to closet under staircase Tom
Install shelving in bonus room Paul
Trim in garages Henry
Gaps in trim around garage door
Install PVC board behind weather stripping at garage door Davenport
Door installed at closet under staircase needs handle Paul
Home Inspection - Friday, June 23
Screen door to back patio needs adjustment Tom. I think repaired 6/28
Buyer has question about supply duct in unfinished portion of the basement
Top floor hall bathroom shower head leaks at the shower head connection to the supply pipe Plumber
Basement door into unfinished area does not latch Jill or Tom
Touch up paint powder bath light Painter
Finish touch up paint Painter
Paint on aluminum support post under roof Jeremy - Davenport
UPGRADES - COMPLETED
    Bonus Room ( not bath)  
    White Kitchen Cabinetry  
    3 drawer stack  
    French Model Refrigerator  
    2 added ceiling fans- LR and painted BR upstairs  
    Custom Paint Color  
    Expanded Driveway  
    Amendment to increase price by $13,820  
CRITICAL PATH - COMPLETED
-- -- Ratified Contract? (0)  08.12.2022    
-- -- $2500 Deposit Received (0)  08.16.2022    
-- -- Association Packet Requested (0)  08.14.2022    
-- -- Association Packet Received (0)  08.14.2022    
-- -- Selections Meeting (0)  08.21.2022    
-- -- Selections Sheet Signed (0)  08.24.2022     8/21/2022: sent to Katie for signatures
-- -- Amendment for Upgrades (B,S,L,T,BCP) (0)  08.31.2022     8/30/2022: sent to Jerry for signatures
-- -- Deposit For Upgrades Received (0)  08.30.2022    
-- -- Building Permit (30) *   08.15.2022    
-- -- Order Roof & Floor Trusses (1)  11.03.2022    
-- -- Order Windows & Doors (0)  11.03.2022    
-- -- Stake Out Home (1)  09.26.2022    
-- -- Excavate (2)  09.29.2022    
-- -- Inspection (Footers) (1)  10.09.2022    
-- -- Inspection (Concrete Wall) (1)  10.09.2022    
-- -- Pour Footers (1) *   10.09.2022    
-- -- Set Forms (2)  10.31.2022    
-- -- Pour Foundation Walls (1)  11.03.2022    
-- -- Plumb Slab (2)  12.01.2022    
-- -- Inspection (Plumbing Under Slab) (1)  12.05.2022    
-- -- Inspection (Conduit Under Slab) (1)  12.08.2022    
-- -- Prepare Slab (1)  12.08.2022    
-- -- Inspection (Slab) (1)  12.27.2022    
-- -- Inspection (Drain Tile) (0)  12.27.2022    
-- -- Pour Slab (1) *   12.27.2022    
-- -- Settlement Agent Confirmed (0)  08.25.2022    
-- -- Framing I (9)  01.05.2023    
-- -- Order Steps (0)  02.02.2023    
-- -- Order Tubs / Showers (0)  02.18.2023    
-- -- Framing II (8)  01.12.2023    
-- -- Framing III (8) *   01.30.2023    
-- -- Verify Window & Roof Structure (0)  09.12.2024    
-- -- Install Stairs (0) *   02.02.2023    
-- -- Windows & Doors (0) *   02.18.2023    
-- -- House Number and Status in Window (0)  02.22.2023    
-- -- Roofing (0) *   02.18.2023    
-- -- Order Cabinets (0)  03.02.2023    
-- -- Order Appliances (0)  05.06.2023     French Upgrade
-- -- Deck (0)  04.01.2023     NONE
-- -- Gutters (0)  04.01.2023    
-- -- Driveway (0) *   04.26.2023     Expanded Driveway
-- -- Patio (0)  04.01.2023     Standard
-- -- Privacy Divider / Fence (0) *   06.11.2023    
-- -- Sod / Seed / Landscaping (0)  06.26.2023     Pettit
-- -- HVAC Rough In (4)  02.18.2023     In process 2/15
-- -- Rough In Microwave Vent (0)  09.12.2024    
-- -- Plumbing Rough In (4)  02.18.2023     In process 2/15
-- -- Electric Rough In (4)  02.27.2023     In process 2/22
-- -- Inspection (Rough In HVAC) (1)  02.27.2023    
-- -- Inspection (Rough In Plumbing) (1)  02.27.2023    
-- -- Inspection (Rough In Electric) (1)  02.27.2023    
-- -- Inspection (Framing) (1) *   02.27.2023    
-- -- Inspection (Deck Piers) (0)  02.27.2023    
-- -- Exterior Vinyl (0) *   04.01.2023    
-- -- Exterior Stone (0)  04.03.2023    
-- -- Insulation (2) *   02.27.2023    
-- -- Inspection (Insulation) (1)  03.06.2023    
-- -- Inspection (Electric Service) (0)  06.12.2023    
-- -- Set Electric Meter (0) *   06.16.2023    
-- -- Inspection (Main Sewer Line) (0)  03.20.2023    
-- -- Inspection (Main Water Line) (0)  03.20.2023    
-- -- Order Interior Doors & Trim (0)  04.12.2023    
-- -- Drywall (Hang) (4) *   03.15.2023     In process 3/8
-- -- Loan Approval (0)  06.12.2023    
-- -- Deed Preparation (0)  06.01.2023    
-- -- Drywall (Tape, Block, Skim, Sand) (6) *   04.01.2023     In process 3/29. Needs final sanding.
-- -- Paint 1 (1)  04.01.2023    
-- -- Garage Door (0)  04.23.2023    
-- -- House Numbers (0)  05.06.2023    
-- -- Mailbox (0)  05.20.2023    
-- -- Cabinet Installation (2) *   03.29.2023     Sat, April 1
-- -- Granite Installation (1) *   04.12.2023    
-- -- Interior Trim - Install (3) *   04.23.2023     In process 4/19
-- -- Order Plumbing / Lighting Fixtures (0)  07.26.2023    
-- -- Interior Trim - Paint (1)  04.29.2023     Prepping to paint 4/26
-- -- Luxury Vinyl Plank (3) *   05.03.2023     In process 4/29
-- -- Luxury Vinyl Tile (0)  05.03.2023    
-- -- Paint 2 (3)  04.05.2023    
-- -- Cover Floors (0)  05.24.2023    
-- -- Deliver Plumbing / Lighting Fixtures (0)  04.27.2023    
-- -- Shoe Moulding (0)  05.06.2023     In process 5/3
-- -- Shelving, Door Knobs, Fire Extinguisher (1) *   06.03.2023     Black accessories In process. Needs mirrors 5/24
-- -- Install Coded Lockbox (add extra keys) (0)  06.03.2023    
-- -- Pay Water / Sewer Taps (0)  05.01.2023    
-- -- Set Water Meter (1) *   05.11.2023    
-- -- Electric Trim Out (3) *   05.24.2023     Black Lighting. In process 5/17. Needs variety of receptacle covers
-- -- Ceiling Fans (0)  05.20.2023     LR and Painted UP BR. In process 5/10
-- -- HVAC Trim Out (1) *   05.10.2023    
-- -- Blower Door Test (1)  09.12.2024    
-- -- Plumbing Trim Out (2) *   05.06.2023     Black Plumbing
-- -- Install Appliances (0) *   05.10.2023    
-- -- Paint 3 (2) *   05.17.2023    
-- -- Carpet (2)  05.03.2023    
-- -- Appraiser Confirms Construction Completion (0)  06.26.2023     Joe Chadwell
-- -- Inspection (Final HVAC) (0)  06.26.2023    
-- -- Inspection (Final Plumbing) (0)  06.26.2023    
-- -- Inspection (Final Electric) (0)  06.26.2023    
-- -- Inspection (Final Building) (4) *   06.26.2023     June 22
-- -- Pre Walk Through (0)  06.26.2023    
-- -- Stain Hardwood Stairs (1) *   06.26.2023     In process 5/24
-- -- Cleaning (1)  06.28.2023    
-- -- Certificate of Occupancy (1) *   06.27.2023    
-- -- C.O. to Lender (0)  06.27.2023    
-- -- Schedule Closing (0)  06.26.2023    
-- -- Buyer Walk Through (1) *   06.27.2023     Monday, June 26, 5:45 PM
-- -- Payment for Upgrades (0)  06.26.2023    
-- -- Keys to Settlement Agent (0)  06.26.2023    
-- -- Review Settlement Statement (0)  06.27.2023    
-- -- Jerry Signs Closing Documents (0)  03.10.2023    
-- -- Request Trash Tote From POA Manager (0)  06.22.2023    
-- -- Closing (1)  06.29.2023     Brittany @ West View Title, Wed June 28
-- -- Remove Coded Lockbox (0)  07.10.2023