CONGERS-2 - 28  ::  1468 Palomino Trail
[ BUILD: 20221530 ]      
CRITICAL PATH   |   INSPECTIONS   |   FLOOR PLANS   |   SELECTIONS   |   SPECS   |   CHANGES   |   NHS
view photo archive
 
--   --   Missing cabinet hardware 3/29
--   --   They have 5-piece cabinetry in kitchen
--   --   Need vanity tops
--   --   Paint all over front porch black aluminum wrap Painter
--   --   Needs flooring in back bonus room
--   --   Cover carpet Jill
--   --   Pedestal sink needed
--   --   Large scratch on fridge CJ has parts and will repair 7/31 or 8/1
--   --   Nickel dining light should be black Electrician - on order
--   --   Hall bath light receptacle needed Electrician
--   --   Push oven into place
--   --   Few electrical items need completed Smoke det in bonus room. Powder light.
--   --   Mirrors needed
--   --   CODED LOCKBOX 2828
--   --   Needs a few receptacle covers in kitchen Electrician
--   --   Install door to closet under staircase Tom
--   --   Install shelving in bonus room Paul
--   --   Trim in garages Henry
--   --   Gaps in trim around garage door
--   --   Install PVC board behind weather stripping at garage door Davenport
--   --   Door installed at closet under staircase needs handle Paul
--   --   Home Inspection - Friday, June 23
--   --   Screen door to back patio needs adjustment Tom. I think repaired 6/28
--   --   Buyer has question about supply duct in unfinished portion of the basement
--   --   Top floor hall bathroom shower head leaks at the shower head connection to the supply pipe Plumber
--   --   Basement door into unfinished area does not latch Jill or Tom
--   --   Touch up paint powder bath light Painter
--   --   Finish touch up paint Painter
--   --   Paint on aluminum support post under roof Jeremy - Davenport
-- -- Ratified Contract? (0)  08.12.2022    
-- -- $2500 Deposit Received (0)  08.16.2022    
-- -- Association Packet Requested (0)  08.14.2022    
-- -- Association Packet Received (0)  08.14.2022    
-- -- Selections Meeting (0)  08.21.2022    
-- -- Selections Sheet Signed (0)  08.24.2022     8/21/2022: sent to Katie for signatures
-- -- Amendment for Upgrades (B,S,L,T,BCP) (0)  08.31.2022     8/30/2022: sent to Jerry for signatures
-- -- Deposit For Upgrades Received (0)  08.30.2022    
-- -- Building Permit (30)  08.15.2022    
-- -- Order Roof & Floor Trusses (1)  11.03.2022    
-- -- Order Windows & Doors (0)  11.03.2022    
-- -- Stake Out Home (1)  09.26.2022    
-- -- Excavate (2)  09.29.2022    
-- -- Inspection (Footers) (1)  10.09.2022    
-- -- Inspection (Concrete Wall) (1)  10.09.2022    
-- -- Pour Footers (1)  10.09.2022    
-- -- Set Forms (2)  10.31.2022    
-- -- Pour Foundation Walls (1)  11.03.2022    
-- -- Plumb Slab (2)  12.01.2022    
-- -- Inspection (Plumbing Under Slab) (1)  12.05.2022    
-- -- Inspection (Conduit Under Slab) (1)  12.08.2022    
-- -- Prepare Slab (1)  12.08.2022    
-- -- Inspection (Slab) (1)  12.27.2022    
-- -- Inspection (Drain Tile) (0)  12.27.2022    
-- -- Pour Slab (1) *   12.27.2022    
-- -- Settlement Agent Confirmed (0)  08.25.2022    
-- -- Framing I (9)  01.05.2023    
-- -- Order Steps (0)  02.02.2023    
-- -- Order Tubs / Showers (0)  02.18.2023    
-- -- Framing II (8)  01.12.2023    
-- -- Framing III (8) *   01.30.2023    
-- -- Verify Window & Roof Structure (0)  09.12.2024    
-- -- Install Stairs (0)  02.02.2023    
-- -- Windows & Doors (0)  02.18.2023    
-- -- House Number and Status in Window (0)  02.22.2023    
-- -- Roofing (0)  02.18.2023    
-- -- Order Cabinets (0)  03.02.2023    
-- -- Order Appliances (0)  05.06.2023     French Upgrade
-- -- Deck (0)  04.01.2023     NONE
-- -- Gutters (0)  04.01.2023    
-- -- Driveway (0)  04.26.2023     Expanded Driveway
-- -- Patio (0)  04.01.2023     Standard
-- -- Privacy Divider / Fence (0)  06.11.2023    
-- -- Sod / Seed / Landscaping (0)  06.26.2023     Pettit
-- -- HVAC Rough In (4)  02.18.2023     In process 2/15
-- -- Inspection (Rough In HVAC) (1)  02.27.2023    
-- -- Rough In Microwave Vent (0)  09.12.2024    
-- -- Plumbing Rough In (4)  02.18.2023     In process 2/15
-- -- Inspection (Rough In Plumbing) (1)  02.27.2023    
-- -- Electric Rough In (4)  02.27.2023     In process 2/22
-- -- Inspection (Rough In Electric) (1)  02.27.2023    
-- -- Inspection (Deck Piers) (0)  02.27.2023    
-- -- Inspection (Framing) (1)  02.27.2023    
-- -- Exterior Vinyl (0) *   04.01.2023    
-- -- Exterior Stone (0)  04.03.2023    
-- -- Insulation (2)  02.27.2023    
-- -- Inspection (Insulation) (1)  03.06.2023    
-- -- Inspection (Electric Service) (0)  06.12.2023    
-- -- Set Electric Meter (0)  06.16.2023    
-- -- Inspection (Main Sewer Line) (0)  03.20.2023    
-- -- Inspection (Main Water Line) (0)  03.20.2023    
-- -- Order Interior Doors & Trim (0)  04.12.2023    
-- -- Drywall (Hang) (4) *   03.15.2023     In process 3/8
-- -- Loan Approval (0)  06.12.2023    
-- -- Deed Preparation (0)  06.01.2023    
-- -- Drywall (Tape, Block, Skim, Sand) (6) *   04.01.2023     In process 3/29. Needs final sanding.
-- -- Paint 1 (1)  04.01.2023    
-- -- Garage Door (0)  04.23.2023    
-- -- House Numbers (0)  05.06.2023    
-- -- Mailbox (0)  05.20.2023    
-- -- Cabinet Installation (2) *   03.29.2023     Sat, April 1
-- -- Granite Installation (1) *   04.12.2023    
-- -- Interior Trim - Install (3)  04.23.2023     In process 4/19
-- -- Order Plumbing / Lighting Fixtures (0)  07.26.2023    
-- -- Interior Trim - Paint (1)  04.29.2023     Prepping to paint 4/26
-- -- Luxury Vinyl Plank (3) *   05.03.2023     In process 4/29
-- -- Luxury Vinyl Tile (0)  05.03.2023    
-- -- Paint 2 (3)  04.05.2023    
-- -- Cover Floors (1)  05.24.2023    
-- -- Deliver Plumbing / Lighting Fixtures (0)  04.27.2023    
-- -- Shoe Moulding (0)  05.06.2023     In process 5/3
-- -- Shelving, Door Knobs, Fire Extinguisher (0)  06.03.2023     Black accessories In process. Needs mirrors 5/24
-- -- Install Coded Lockbox (add extra keys) (0)  06.03.2023    
-- -- Pay Water / Sewer Taps (0)  05.01.2023    
-- -- Set Water Meter (0)  05.11.2023    
-- -- Electric Trim Out (3)  05.24.2023     Black Lighting. In process 5/17. Needs variety of receptacle covers
-- -- Ceiling Fans (0)  05.20.2023     LR and Painted UP BR. In process 5/10
-- -- HVAC Trim Out (1)  05.10.2023    
-- -- Blower Door Test (1)  09.12.2024    
-- -- Plumbing Trim Out (2)  05.06.2023     Black Plumbing
-- -- Install Appliances (0) *   05.10.2023    
-- -- Paint 3 (2) *   05.17.2023    
-- -- Carpet (2)  05.03.2023    
-- -- Appraiser Confirms Construction Completion (0)  06.26.2023     Joe Chadwell
-- -- Inspection (Final HVAC) (1)  06.26.2023    
-- -- Inspection (Final Plumbing) (1)  06.26.2023    
-- -- Inspection (Final Electric) (1)  06.26.2023    
-- -- Inspection (Final Building) (2) *   06.26.2023     June 22
-- -- Pre Walk Through (0)  06.26.2023    
-- -- Stain Hardwood Stairs (1)  06.26.2023     In process 5/24
-- -- Cleaning (1)  06.28.2023    
-- -- Certificate of Occupancy (1) *   06.27.2023    
-- -- C.O. to Lender (0)  06.27.2023    
-- -- Schedule Closing (0)  06.26.2023    
-- -- Buyer Walk Through (1)  06.27.2023     Monday, June 26, 5:45 PM
-- -- Payment for Upgrades (0)  06.26.2023    
-- -- Keys to Settlement Agent (0)  06.26.2023    
-- -- Review Settlement Statement (0)  06.27.2023    
-- -- Jerry Signs Closing Documents (0)  03.10.2023    
-- -- Request Trash Tote From POA Manager (0)  06.22.2023    
-- -- Closing (1)  06.29.2023     Brittany @ West View Title, Wed June 28
-- -- Remove Coded Lockbox (0)  07.10.2023