Thu |
Nov 28 |
Verify Window & Roof Structure (0) |
|
|
Thu |
Nov 28 |
Rough In Microwave Vent (0) |
|
|
Thu |
Nov 28 |
Order Plumbing / Lighting Fixtures (0) |
|
|
Thu |
Nov 28 |
Blower Door Test (1) |
|
|
|
-- |
-- |
Expanded driveway? |
Add to changes, amend again |
|
-- |
-- |
Pantry roll outs uneven |
Fred |
|
-- |
-- |
Appliances delivered April 20 |
|
|
-- |
-- |
Island granite needed |
|
|
-- |
-- |
Lots of paint on kit cabinets |
Painter |
|
-- |
-- |
Cover carpet |
|
|
-- |
-- |
Needs refrigerator |
Leisa will find one |
|
-- |
-- |
Can we flip the hallway lights the other direction? |
Stairwell sconces, Electrician |
|
-- |
-- |
Electrical outlet cover needed in smaller bedroom |
Electrician |
|
-- |
-- |
CODED LOCKBOX 2929 |
|
|
-- |
-- |
Patch small hole in powder bath |
Painter |
|
-- |
-- |
Lightbulb needed in garage fixture |
And in bonus room, electrician |
|
-- |
-- |
Black cord sticking out of lr ceiling fan |
|
|
-- |
-- |
Install snaplight in foyer |
Electrician |
|
-- |
-- |
Attic cover needed |
Painter |
|
-- |
-- |
Clean paint off right Sconce stairwell |
Painter |
|
-- |
-- |
Paint touch up throughout home |
Painter |
|
-- |
-- |
Finish painting basement hall closet |
Painter |
|
-- |
-- |
Patch small hole in the garage fo |
|
|
-- |
-- |
Patch small hole in concrete of the garage floor |
Tom |
|
-- |
-- |
Remove the blue tape from garage door threshold on garage side |
Jill |
|
-- |
-- |
Couple small places to touch up with paint in the garage |
Painter |
|
-- |
-- |
Remove excess paint from all hinges, brackets, & door and cabinet handles throughout |
Painter |
|
-- |
-- |
Skin on the end of the island has a screw poking through and needs replaced |
Fred ordered it |
|
-- |
-- |
Missing 1 bulb in the chandelier |
|
|
-- |
-- |
Light switch cover in the kitchen is really crooked |
Electrician |
|
-- |
-- |
Make the chandelier 1 bar c |
|
|
-- |
-- |
Make the chandelier shorter by 1 rod |
Electrician |
|
-- |
-- |
Screen door doesn’t close all the way |
|
|
-- |
-- |
Baseboard underneath the banister at the top of the second set of stairs needs a crack filled in with wood filler |
Painter |
|
-- |
-- |
Paint drops on the carpet in a lot of rooms |
Painter |
|
-- |
-- |
Paint the little wall under the banister at the top of the second set of stairs |
Painter |
|
-- |
-- |
Sconce to left on the landing is crooked |
Electrician |
|
-- |
-- |
Paint on the sconce to the right on the landing |
|
|
-- |
-- |
Glue on the shower wall in the guest bathroom |
Jill |
|
-- |
-- |
Master bathroom door has a scuff mark on it |
Painter |
|
-- |
-- |
Finish scrapping the garage floor |
Jill |
|
-- |
-- |
Ratified Contract? (0) 09.18.2022 |
|
|
-- |
-- |
$2500 Deposit Received (0) 09.20.2022 |
|
|
-- |
-- |
Association Packet Requested (0) 09.18.2022 |
|
|
-- |
-- |
Association Packet Received (0) 09.21.2022 |
|
|
-- |
-- |
Selections Meeting (0) 10.14.2022 |
|
|
-- |
-- |
Selections Sheet Signed (0) 10.18.2022 |
10/14: Sent to Dee Dee for signatures |
|
-- |
-- |
Amendment for Upgrades (B,S,L,T,BCP) (0) 02.05.2023 |
new amendment 2/2/2023 |
|
-- |
-- |
Deposit For Upgrades Received (0) 10.20.2022 |
|
|
-- |
-- |
Building Permit (30) 08.15.2022 |
|
|
-- |
-- |
Order Roof & Floor Trusses (1) 11.03.2022 |
|
|
-- |
-- |
Order Windows & Doors (0) 11.03.2022 |
|
|
-- |
-- |
Stake Out Home (1) 09.26.2022 |
|
|
-- |
-- |
Excavate (2) 09.29.2022 |
|
|
-- |
-- |
Inspection (Footers) (1) 10.09.2022 |
|
|
-- |
-- |
Inspection (Concrete Wall) (1) 10.09.2022 |
|
|
-- |
-- |
Pour Footers (1) 10.09.2022 |
|
|
-- |
-- |
Set Forms (2) 10.31.2022 |
|
|
-- |
-- |
Pour Foundation Walls (1) 11.03.2022 |
|
|
-- |
-- |
Plumb Slab (2) 12.01.2022 |
|
|
-- |
-- |
Inspection (Plumbing Under Slab) (1) 12.05.2022 |
|
|
-- |
-- |
Inspection (Conduit Under Slab) (1) 12.08.2022 |
|
|
-- |
-- |
Prepare Slab (1) 12.08.2022 |
|
|
-- |
-- |
Inspection (Slab) (1) 12.27.2022 |
|
|
-- |
-- |
Inspection (Drain Tile) (0) 12.27.2022 |
|
|
-- |
-- |
Pour Slab (1) * 12.27.2022 |
|
|
-- |
-- |
Settlement Agent Confirmed (0) 11.18.2022 |
|
|
-- |
-- |
Framing I (9) 01.05.2023 |
|
|
-- |
-- |
Order Steps (0) 02.02.2023 |
|
|
-- |
-- |
Order Tubs / Showers (0) 02.18.2023 |
|
|
-- |
-- |
Framing II (8) 01.12.2023 |
|
|
-- |
-- |
Framing III (8) * 01.30.2023 |
|
|
-- |
-- |
Install Stairs (0) 02.02.2023 |
|
|
-- |
-- |
Windows & Doors (0) 02.20.2023 |
|
|
-- |
-- |
House Number and Status in Window (0) 02.22.2023 |
|
|
-- |
-- |
Roofing (0) 02.20.2023 |
|
|
-- |
-- |
Order Cabinets (0) 03.02.2023 |
|
|
-- |
-- |
Order Appliances (0) 05.15.2023 |
Standard SS |
|
-- |
-- |
Deck (0) 03.06.2023 |
NONE |
|
-- |
-- |
Gutters (0) 04.11.2023 |
|
|
-- |
-- |
Driveway (0) 04.26.2023 |
Standard |
|
-- |
-- |
Patio (0) 03.15.2023 |
Standard |
|
-- |
-- |
Privacy Divider / Fence (0) 06.11.2023 |
|
|
-- |
-- |
Sod / Seed / Landscaping (0) 06.28.2023 |
|
|
-- |
-- |
HVAC Rough In (4) 02.22.2023 |
In process 2/18 |
|
-- |
-- |
Inspection (Rough In HVAC) (1) 03.08.2023 |
|
|
-- |
-- |
Plumbing Rough In (4) 02.22.2023 |
In process 2/18 |
|
-- |
-- |
Inspection (Rough In Plumbing) (1) 03.08.2023 |
|
|
-- |
-- |
Electric Rough In (4) 03.05.2023 |
In process 3/1 |
|
-- |
-- |
Inspection (Rough In Electric) (1) 03.08.2023 |
|
|
-- |
-- |
Inspection (Deck Piers) (0) 05.15.2023 |
|
|
-- |
-- |
Inspection (Framing) (1) 03.08.2023 |
|
|
-- |
-- |
Exterior Vinyl (0) * 04.11.2023 |
|
|
-- |
-- |
Exterior Stone (0) 04.03.2023 |
|
|
-- |
-- |
Insulation (2) 03.08.2023 |
|
|
-- |
-- |
Inspection (Insulation) (1) 03.15.2023 |
|
|
-- |
-- |
Inspection (Electric Service) (0) 06.16.2023 |
|
|
-- |
-- |
Set Electric Meter (0) 06.14.2023 |
|
|
-- |
-- |
Inspection (Main Sewer Line) (0) 03.20.2023 |
|
|
-- |
-- |
Inspection (Main Water Line) (0) 03.20.2023 |
|
|
-- |
-- |
Order Interior Doors & Trim (0) 04.19.2023 |
|
|
-- |
-- |
Drywall (Hang) (4) * 03.15.2023 |
NONE |
|
-- |
-- |
Loan Approval (0) 10.12.2022 |
|
|
-- |
-- |
Deed Preparation (0) 06.01.2023 |
|
|
-- |
-- |
Drywall (Tape, Block, Skim, Sand) (6) * 04.01.2023 |
In process 3/29 |
|
-- |
-- |
Paint 1 (1) 04.10.2023 |
|
|
-- |
-- |
Garage Door (0) 04.23.2023 |
|
|
-- |
-- |
House Numbers (0) 05.06.2023 |
|
|
-- |
-- |
Mailbox (0) 05.20.2023 |
|
|
-- |
-- |
Cabinet Installation (2) * 04.12.2023 |
Wed, Apr 5. In process 4/5 |
|
-- |
-- |
Granite Installation (1) * 04.15.2023 |
|
|
-- |
-- |
Interior Trim - Install (3) 04.29.2023 |
In process 4/23 |
|
-- |
-- |
Interior Trim - Paint (1) 05.03.2023 |
|
|
-- |
-- |
Luxury Vinyl Plank (3) * 05.06.2023 |
In process 5/3 |
|
-- |
-- |
Luxury Vinyl Tile (0) 05.06.2023 |
In process 5/3 |
|
-- |
-- |
Paint 2 (3) 04.15.2023 |
In process 4/12 |
|
-- |
-- |
Cover Floors (1) 05.13.2023 |
|
|
-- |
-- |
Deliver Plumbing / Lighting Fixtures (0) 04.27.2023 |
|
|
-- |
-- |
Shoe Moulding (0) 05.10.2023 |
|
|
-- |
-- |
Shelving, Door Knobs, Fire Extinguisher (0) 05.31.2023 |
In process 5/24. Partially completed 5/28 |
|
-- |
-- |
Install Coded Lockbox (add extra keys) (0) 05.31.2023 |
|
|
-- |
-- |
Pay Water / Sewer Taps (0) 05.01.2023 |
|
|
-- |
-- |
Set Water Meter (0) 05.11.2023 |
|
|
-- |
-- |
Electric Trim Out (3) 05.28.2023 |
In process 5/24 |
|
-- |
-- |
Ceiling Fans (0) 05.28.2023 |
|
|
-- |
-- |
HVAC Trim Out (1) 06.11.2023 |
Needs floor registers |
|
-- |
-- |
Plumbing Trim Out (2) 05.24.2023 |
In process 5/20 |
|
-- |
-- |
Install Appliances (0) * 05.20.2023 |
Delivery date 4/28. In process 5/10 |
|
-- |
-- |
Paint 3 (2) * 05.17.2023 |
|
|
-- |
-- |
Carpet (2) 05.13.2023 |
In process 5/10 |
|
-- |
-- |
Appraiser Confirms Construction Completion (0) 06.22.2023 |
|
|
-- |
-- |
Inspection (Final HVAC) (1) 06.16.2023 |
|
|
-- |
-- |
Inspection (Final Plumbing) (1) 06.16.2023 |
|
|
-- |
-- |
Inspection (Final Electric) (1) 06.16.2023 |
|
|
-- |
-- |
Inspection (Final Building) (2) * 06.16.2023 |
|
|
-- |
-- |
Pre Walk Through (0) 06.19.2023 |
|
|
-- |
-- |
Stain Hardwood Stairs (1) 05.31.2023 |
In process 5/24 |
|
-- |
-- |
Cleaning (1) 06.21.2023 |
|
|
-- |
-- |
Certificate of Occupancy (1) * 06.22.2023 |
Tue, June 20? |
|
-- |
-- |
C.O. to Lender (0) 06.22.2023 |
|
|
-- |
-- |
Schedule Closing (0) 06.22.2023 |
|
|
-- |
-- |
Buyer Walk Through (1) 06.22.2023 |
Wed, June 21, 6PM |
|
-- |
-- |
Payment for Upgrades (0) 06.19.2023 |
|
|
-- |
-- |
Keys to Settlement Agent (0) 06.22.2023 |
|
|
-- |
-- |
Review Settlement Statement (0) 06.23.2023 |
|
|
-- |
-- |
Jerry Signs Closing Documents (0) 03.10.2023 |
|
|
-- |
-- |
Request Trash Tote From POA Manager (0) 06.22.2023 |
|
|
-- |
-- |
Closing (1) 06.26.2023 |
Brittany @ West View Title |
|
-- |
-- |
Remove Coded Lockbox (0) 07.10.2023 |
|
|