37 ADDR
CONGERS-2 - 96  ::  1501 Palomino Trail
[ BUILD: 20221356 ]      
CRITICAL PATH   |   INSPECTIONS   |   FLOOR PLANS   |   SELECTIONS   |   SPECS   |   CHANGES   |   NHS
view photo archive
 
TO DO
---
UPGRADES
---
CRITICAL PATH
    Verify Window & Roof Structure (0)      
    Rough In Microwave Vent (0)      
    Order Plumbing / Lighting Fixtures (0)      
Tue    Feb 3      Blower Door Test (1)      
TO DO - COMPLETED OR DELETED
One handle missing on kitchen island Fred
Kitchen island door with hinge on wrong side Fred
Replace mailbox board that someone appears to have backed into Tom
Patch large crack in basement bonus room Tom. In process of repair 5/10
Remove drywall boards from back deck to prevent staining Jill
Cover carpet Jill
Ryan OOT May 24-28, Jun 17-29
Drywall repair near patio doors Drywaller
Unable to access upstairs due to step staining 5/10
Patch screw holes in powder bath Painter
Exterior electrical trim out Electrician. Exterior needs completed 5/17
Outlet covers needed in garage Electrician
A lot of paint all over the hardwood staircase Painter
Weatherstripping Jill
Whiteboard needed below patio doors in basement. All units Tom
White board back deck Tom
Vinyl missing electrical outlet on deck Jeremy, Davenport
Sing hvac covers living room
Missing hvac covers living room HVAC
Weatherstripping, needed patio door Sorry- deck door
Paint, Push attic cover into place Painter, Jill
CODED LOCKBOX 9696
Side landscaping needed Pettit
Side landscaping needed
Driveway staining
Clean front trim around garage and front door Jill
Clean out garage Jill
Clean off deck Lynn
Remove drywall mud from hall tub Jill
Paint touch up at front door Painter
Touch up cabinet door Painter
UPGRADES - COMPLETED
    Expanded Driveway  
    Garage Keypad  
    Amendment to increase price by $1,420  
CRITICAL PATH - COMPLETED
-- -- Ratified Contract? (0)  01.11.2023    
-- -- $2500 Deposit Received (0)  01.20.2023    
-- -- Association Packet Requested (0)  01.11.2023    
-- -- Association Packet Received (0)  01.14.2023    
-- -- Selections Meeting (0)  02.13.2023    
-- -- Selections Sheet Signed (0)  02.16.2023     2/12: sent to Ryan for signatures
-- -- Amendment for Upgrades (B,S,L,T,BCP) (0)  03.07.2023    
-- -- Deposit For Upgrades Received (0)  03.07.2023    
-- -- Building Permit (30) *   10.06.2022    
-- -- Order Roof & Floor Trusses (1)  11.03.2022    
-- -- Order Windows & Doors (0)  11.03.2022    
-- -- Stake Out Home (1)  10.06.2022    
-- -- Excavate (2)  10.06.2022    
-- -- Inspection (Footers) (1)  10.06.2022     9/30/22
-- -- Inspection (Concrete Wall) (1)  11.10.2022    
-- -- Pour Footers (1) *   10.06.2022    
-- -- Set Forms (2)  11.10.2022    
-- -- Pour Foundation Walls (1)  11.10.2022    
-- -- Plumb Slab (2)  11.10.2022    
-- -- Inspection (Plumbing Under Slab) (1)  11.10.2022    
-- -- Inspection (Conduit Under Slab) (1)  11.10.2022    
-- -- Prepare Slab (1)  11.17.2022    
-- -- Inspection (Slab) (1)  11.19.2022    
-- -- Inspection (Drain Tile) (0)  12.27.2022    
-- -- Pour Slab (1) *   11.19.2022    
-- -- Settlement Agent Confirmed (0)  01.13.2023    
-- -- Framing I (9)  12.05.2022    
-- -- Order Steps (0)  01.12.2023    
-- -- Order Tubs / Showers (0)  01.12.2023    
-- -- Framing II (8)  12.27.2022    
-- -- Framing III (8) *   01.02.2023    
-- -- Install Stairs (0) *   01.12.2023    
-- -- Windows & Doors (0) *   01.12.2023    
-- -- House Number and Status in Window (0)  02.23.2023    
-- -- Roofing (0) *   01.12.2023    
-- -- Order Cabinets (0)  02.23.2023    
-- -- Order Appliances (0)  05.06.2023     Standard SS
-- -- Deck (0)  04.15.2023    
-- -- Gutters (0)  04.11.2023    
-- -- Driveway (0) *   04.10.2023    
-- -- Patio (0)  04.10.2023    
-- -- Privacy Divider / Fence (0) *   05.06.2023    
-- -- Sod / Seed / Landscaping (0)  06.07.2023    
-- -- HVAC Rough In (4)  01.14.2023    
-- -- Plumbing Rough In (4)  02.01.2023     In process 1/28
-- -- Electric Rough In (4)  02.04.2023    
-- -- Inspection (Rough In HVAC) (1)  02.10.2023    
-- -- Inspection (Rough In Plumbing) (1)  02.10.2023    
-- -- Inspection (Rough In Electric) (1)  02.10.2023    
-- -- Inspection (Framing) (1) *   02.10.2023    
-- -- Inspection (Deck Piers) (0)  04.11.2023    
-- -- Exterior Vinyl (0) *   04.10.2023    
-- -- Exterior Stone (0)  05.13.2023     In process 5/6
-- -- Insulation (2) *   02.11.2023    
-- -- Inspection (Insulation) (1)  02.13.2023    
-- -- Inspection (Electric Service) (0)  06.01.2023    
-- -- Set Electric Meter (0) *   06.14.2023    
-- -- Inspection (Main Sewer Line) (0)  03.20.2023    
-- -- Inspection (Main Water Line) (0)  03.20.2023    
-- -- Order Interior Doors & Trim (0)  04.10.2023    
-- -- Drywall (Hang) (4) *   02.22.2023     In process 2/15
-- -- Loan Approval (0)  05.04.2023    
-- -- Deed Preparation (0)  05.04.2023    
-- -- Drywall (Tape, Block, Skim, Sand) (6) *   03.05.2023     In process 3/1. Needs sanding.
-- -- Paint 1 (1)  03.05.2023    
-- -- Garage Door (0)  04.11.2023    
-- -- House Numbers (0)  05.06.2023    
-- -- Mailbox (0)  05.06.2023    
-- -- Cabinet Installation (2) *   04.01.2023     Sat, April 1
-- -- Granite Installation (1) *   04.10.2023    
-- -- Interior Trim - Install (3) *   04.10.2023    
-- -- Interior Trim - Paint (1)  04.10.2023    
-- -- Luxury Vinyl Plank (3) *   04.19.2023    
-- -- Luxury Vinyl Tile (0)  04.19.2023    
-- -- Paint 2 (3)  03.15.2023    
-- -- Cover Floors (0)  05.06.2023    
-- -- Deliver Plumbing / Lighting Fixtures (0)  04.11.2023    
-- -- Shoe Moulding (0)  04.23.2023    
-- -- Shelving, Door Knobs, Fire Extinguisher (1) *   05.20.2023     Just needs shelving 5/17
-- -- Install Coded Lockbox (add extra keys) (0)  05.29.2023    
-- -- Pay Water / Sewer Taps (0)  05.01.2023    
-- -- Set Water Meter (1) *   05.08.2023    
-- -- Electric Trim Out (3) *   05.06.2023     Started 5/3
-- -- Ceiling Fans (0)  05.03.2023    
-- -- HVAC Trim Out (1) *   05.06.2023     Needs Al floor covers 5/3
-- -- Plumbing Trim Out (2) *   04.26.2023     In process 4/23
-- -- Install Appliances (0) *   05.13.2023    
-- -- Paint 3 (2) *   04.15.2023    
-- -- Carpet (2)  04.23.2023     In process 4/19
-- -- Appraiser Confirms Construction Completion (0)  06.14.2023    
-- -- Inspection (Final HVAC) (0)  06.19.2023    
-- -- Inspection (Final Plumbing) (0)  06.19.2023    
-- -- Inspection (Final Electric) (0)  06.19.2023    
-- -- Inspection (Final Building) (4) *   06.21.2023     Reinspect June 21
-- -- Pre Walk Through (0)  05.29.2023    
-- -- Stain Hardwood Stairs (1) *   05.13.2023     In process 5/10
-- -- Cleaning (1)  06.26.2023    
-- -- Certificate of Occupancy (1) *   06.22.2023    
-- -- C.O. to Lender (0)  06.22.2023    
-- -- Schedule Closing (0)  06.23.2023    
-- -- Buyer Walk Through (1) *   06.26.2023     Friday, June 23 at 9AM
-- -- Payment for Upgrades (0)  06.16.2023    
-- -- Keys to Settlement Agent (0)  06.21.2023    
-- -- Review Settlement Statement (0)  06.16.2023    
-- -- Jerry Signs Closing Documents (0)  05.11.2023    
-- -- Request Trash Tote From POA Manager (0)  06.22.2023    
-- -- Closing (1)  06.26.2023     Brittany @ West View Title
-- -- Remove Coded Lockbox (0)  07.10.2023