1 28 33 37 45 46 47 48 71 52 70 69 67 53 54 55 56 59 58 57 66 65 64 60 61 62 63 ADDR
CONGERS-2 - 32  ::  1500 Palomino Trail
[ BUILD: 20221534 ]      
CRITICAL PATH   |   INSPECTIONS   |   FLOOR PLANS   |   SELECTIONS   |   SPECS   |   CHANGES   |   NHS
view photo archive
 
Fri    Sep 20      Verify Window & Roof Structure (0)      
Fri    Sep 20      Rough In Microwave Vent (0)      
Fri    Sep 20      Blower Door Test (1)      
--   --   Possibly removing oak treads to bedroom level
--   --   Board missing in master bathroom
--   --   Lender requests amendment with closing date
--   --   Appliances delivered May 11
--   --   Drywallers need to sweep up/toss trash before paint 1
--   --   Vanity tops needed 5/10
--   --   Piece of drywall missing on the end of upstairs stairwell George
--   --   Needs lots of lightbulbs Electrician. Just dining light 7/12
--   --   Confirm if there is an upgraded fridge or not
--   --   Cover carpet
--   --   Swap fridge - should not be French style upgraded fridge
--   --   Rebelled needed
--   --   Doorbell needed Electrician
--   --   Attic cover After inspection
--   --   Paint touchup needed around master bathroom fan Painter
--   --   Few bulbs outdoor light needed Electrician
--   --   Piece of trim needed on stairs Trim guy, George
--   --   Small hole powder bath needs patching Painter
--   --   CODED LOCKBOX 3232
--   --   Clean out garage and add trim Trim guy
--   --   Install handrails Trim guy
--   --   Patch trim holes at dormer Davenport
--   --   HVAC drain needs lined up at drain better Tom
--   --   Bugs in kitchen light Jill
--   --   Glue in tub (hall) Jill
--   --   Supports to be installed in kitchen pantry Joe, Paul
--   --   Install window screens Jill
--   --   Two shelves to be installed in master closet Joe, Paul
--   --   Green wire in front yard Tom
--   --   Few cabinet touchups needed Jill
--   --   Raise Pendants and chandelier Electrician
--   --   remove floors and remove paint spots remop - Jill
--   --   repaint black treads Painters
--   --   Box over hot/cold water valves in laundry Plastic valve cover needed - Tom
--   --   Adjust back [atio door Framer
--   --   tighten up exterior trim around bump out window Davenport
--   --   wash off front door Jill
--   --   paint touch up throughout Painter
--   --   The walls and ceilings were scanned with a thermal camera. The scan revealed areas of misplaced or missing insulation which is evident by the bright orange/yellow color. Make corrections in the attic. (2.2) above attic access panel - Jill
--   --   2.The dishwasher drain line did not have a high loop. Re-route the drain line and create a high loop to prevent back up water from entering the dishwasher. (3.0) CJ will fix this
--   --   Replace dirty air filters. (5.6) Jill
--   --   The condensation drain line is not depositing the condensation into the floor drain. Make adjustments to prevent water accumulation and damage. (5.7)
--   --   Patio door has been adjusted but touch up paint is needed and floors need to be cleaned
--   --   Touch up paint - patio door
--   --   Remove stickers from dormer windows
--   --   still needed 9/16
-- -- Ratified Contract? (0)  11.10.2022    
-- -- $2500 Deposit Received (0)  11.16.2022    
-- -- Association Packet Requested (0)  11.10.2022    
-- -- Association Packet Received (0)  11.13.2022    
-- -- Selections Meeting (0)  01.17.2023    
-- -- Selections Sheet Signed (0)  02.09.2023     2/7: sending new version to Lisa
-- -- Amendment for Upgrades (B,S,L,T,BCP) (0)  02.15.2023     2/14: sent to Jerry for signatures
-- -- Deposit For Upgrades Received (0)  06.01.2023    
-- -- Building Permit (30)  10.08.2022    
-- -- Order Roof & Floor Trusses (1)  11.03.2022    
-- -- Order Windows & Doors (0)  03.06.2023    
-- -- Stake Out Home (1)  10.17.2022    
-- -- Excavate (2)  10.17.2022    
-- -- Inspection (Footers) (1)  10.17.2022    
-- -- Inspection (Concrete Wall) (1)  11.10.2022     11/4/22
-- -- Pour Footers (1)  10.17.2022    
-- -- Set Forms (2)  11.10.2022    
-- -- Pour Foundation Walls (1)  11.10.2022    
-- -- Plumb Slab (2)  12.08.2022    
-- -- Inspection (Plumbing Under Slab) (1)  12.08.2022    
-- -- Inspection (Conduit Under Slab) (1)  12.08.2022    
-- -- Prepare Slab (1)  01.31.2023    
-- -- Inspection (Slab) (1)  01.31.2023    
-- -- Inspection (Drain Tile) (0)  01.31.2023    
-- -- Pour Slab (1)  01.31.2023    
-- -- Settlement Agent Confirmed (0)  02.18.2023    
-- -- Framing I (9)  01.31.2023    
-- -- Order Steps (0)  03.06.2023    
-- -- Order Tubs / Showers (0)  03.22.2023    
-- -- Framing II (8)  02.23.2023    
-- -- Framing III (8)  03.06.2023    
-- -- Install Stairs (0)  03.22.2023    
-- -- Windows & Doors (0)  03.06.2023    
-- -- House Number and Status in Window (0)  04.05.2023    
-- -- Roofing (0)  03.06.2023    
-- -- Order Cabinets (0)  04.04.2023    
-- -- Order Appliances (0)  06.11.2023     Standard SS
-- -- Deck (0)  04.11.2023    
-- -- Gutters (0)  05.20.2023    
-- -- Driveway (0)  06.07.2023    
-- -- Patio (0)  05.17.2023    
-- -- Privacy Divider / Fence (0)  07.12.2023    
-- -- Sod / Seed / Landscaping (0)  07.19.2023    
-- -- HVAC Rough In (4)  03.22.2023     In process. 3/18
-- -- Inspection (Rough In HVAC) (1)  04.06.2023    
-- -- Plumbing Rough In (4)  04.01.2023     In process 3/25
-- -- Inspection (Rough In Plumbing) (1)  04.06.2023    
-- -- Electric Rough In (4)  04.01.2023    
-- -- Inspection (Rough In Electric) (1)  04.06.2023    
-- -- Inspection (Deck Piers) (0)  06.11.2023    
-- -- Inspection (Framing) (1)  04.06.2023    
-- -- Exterior Vinyl (0)  05.20.2023     In process 4/26
-- -- Exterior Stone (0)  05.31.2023    
-- -- Insulation (2)  04.10.2023    
-- -- Inspection (Insulation) (1)  04.13.2023    
-- -- Inspection (Electric Service) (0)  06.28.2023     Tuesday, June 27
-- -- Set Electric Meter (0)  07.08.2023    
-- -- Inspection (Main Sewer Line) (0)  03.20.2023    
-- -- Inspection (Main Water Line) (0)  03.20.2023    
-- -- Order Interior Doors & Trim (0)  05.17.2023    
-- -- Drywall (Hang) (4)  04.15.2023    
-- -- Loan Approval (0)  06.19.2023    
-- -- Deed Preparation (0)  06.19.2023    
-- -- Drywall (Tape, Block, Skim, Sand) (6)  04.26.2023     In process 4/23
-- -- Paint 1 (1)  04.29.2023    
-- -- Garage Door (0)  05.06.2023    
-- -- House Numbers (0)  05.25.2023    
-- -- Mailbox (0)  06.12.2023    
-- -- Cabinet Installation (2)  05.10.2023     Cabinets on site 4/26
-- -- Granite Installation (1)  05.10.2023    
-- -- Interior Trim - Install (3)  05.20.2023     In process 5/17
-- -- Order Plumbing / Lighting Fixtures (0)  07.26.2023    
-- -- Interior Trim - Paint (1)  05.24.2023    
-- -- Luxury Vinyl Plank (3)  06.07.2023     In process 6/3
-- -- Luxury Vinyl Tile (0)  06.03.2023    
-- -- Paint 2 (3)  05.24.2023     In process 5/20
-- -- Cover Floors (1)  06.22.2023    
-- -- Deliver Plumbing / Lighting Fixtures (0)  06.01.2023    
-- -- Shoe Moulding (0)  06.07.2023    
-- -- Shelving, Door Knobs, Fire Extinguisher (0)  06.26.2023    
-- -- Install Coded Lockbox (add extra keys) (0)  07.01.2023    
-- -- Pay Water / Sewer Taps (0)  06.19.2023    
-- -- Set Water Meter (0)  07.12.2023    
-- -- Electric Trim Out (3)  07.01.2023     Needs bulbs. Outdoor trim out.
-- -- Ceiling Fans (0)  06.07.2023    
-- -- HVAC Trim Out (1)  06.28.2023     Needs thermostat
-- -- Plumbing Trim Out (2)  06.28.2023    
-- -- Install Appliances (0)  06.15.2023     Delivery 5/23
-- -- Paint 3 (2)  05.31.2023     In process 5/24
-- -- Carpet (2)  06.07.2023    
-- -- Appraiser Confirms Construction Completion (0)  08.07.2023     Mike Shirfey, Monday, July 31
-- -- Inspection (Final HVAC) (1)  07.19.2023    
-- -- Inspection (Final Plumbing) (1)  07.19.2023    
-- -- Inspection (Final Electric) (1)  07.19.2023    
-- -- Inspection (Final Building) (2)  07.19.2023     Reinspect - Tue, Jul 18
-- -- Pre Walk Through (0)  07.17.2023    
-- -- Stain Hardwood Stairs (1)  06.28.2023    
-- -- Cleaning (1)  07.19.2023    
-- -- Certificate of Occupancy (1)  07.20.2023    
-- -- C.O. to Lender (0)  07.20.2023    
-- -- Schedule Closing (0)  09.05.2023    
-- -- Buyer Walk Through (1)  07.27.2023     Kate awaiting response
-- -- Payment for Upgrades (0)  07.17.2023    
-- -- Keys to Settlement Agent (0)  07.17.2023    
-- -- Review Settlement Statement (0)  09.05.2023    
-- -- Jerry Signs Closing Documents (0)  08.16.2023    
-- -- Request Trash Tote From POA Manager (0)  07.17.2023    
-- -- Closing (1)  09.07.2023     Brittany @ West View Title
-- -- Remove Coded Lockbox (0)  09.07.2023