| TO DO | ||||
| --- | ||||
| UPGRADES | ||||
| --- | ||||
| CRITICAL PATH | ||||
| --- | ||||
| TO DO - COMPLETED OR DELETED | ||||
| UPGRADES - COMPLETED | ||||
| Expanded 12 x 18 Deck | ||||
| White Kitchen Cabinetry | ||||
| LVP Upstairs hallway and Bedrooms | ||||
| Painted Stairs to bedroom level | ||||
| White Painted Bathroom Cabinetry | ||||
| Microwave vented to exterior | ||||
| 3 Drawer Stack in B36 | ||||
| Amendment to increase price by $9,335 | ||||
| CRITICAL PATH - COMPLETED | ||||
| -- | -- | Inspection (Footers) (1) 11.10.2022 | ||
| -- | -- | Inspection (Concrete Wall) (1) 11.10.2022 | ||
| -- | -- | Inspection (Plumbing Under Slab) (1) 02.10.2023 | ||
| -- | -- | Inspection (Conduit Under Slab) (1) 03.02.2023 | ||
| -- | -- | Inspection (Slab) (1) 03.02.2023 | ||
| -- | -- | Inspection (Drain Tile) (0) 04.17.2023 | ||
| -- | -- | Inspection (Rough In HVAC) (1) 05.08.2023 | ||
| -- | -- | Inspection (Rough In Plumbing) (1) 05.08.2023 | ||
| -- | -- | Inspection (Rough In Electric) (1) 05.08.2023 | ||
| -- | -- | Inspection (Framing) (1) * 05.08.2023 | ||
| -- | -- | Inspection (Deck Piers) (0) 06.26.2023 | ||
| -- | -- | Inspection (Insulation) (1) 05.18.2023 | ||
| -- | -- | Inspection (Electric Service) (0) 07.20.2023 | Mon, July 17 | |
| -- | -- | Inspection (Main Sewer Line) (0) 03.20.2023 | ||
| -- | -- | Inspection (Main Water Line) (0) 03.20.2023 | ||
| -- | -- | Inspection (Final HVAC) (0) 08.04.2023 | ||
| -- | -- | Inspection (Final Plumbing) (0) 08.04.2023 | ||
| -- | -- | Inspection (Final Electric) (0) 08.04.2023 | ||
| -- | -- | Inspection (Final Building) (4) * 08.04.2023 | ||