CONGERS-2 - 37  ::  1536 Palomino Trail
[ BUILD: 20221352 ]      
CRITICAL PATH   |   INSPECTIONS   |   FLOOR PLANS   |   SELECTIONS   |   SPECS   |   CHANGES   |   NHS


Sunday (Sep 15)    show all photos
--   --   New sod by glo fiber box after temp meter is gone Pettit
--   --   Broken front window Living room - top sash - on order
--   --   Bump out window siding issues Davenport
--   --   Siding issue at bottom of bump out as seen from deck below Davenport
--   --   Garage door 92, 35-37
--   --   Buyers are asking about price for LVP in room behind garage Kate waiting to see if Eric has enough LVP in stock to upgrade.
--   --   Fix gutter on front left side
--   --   Dormer is fixed but hole/gap below
--   --   Finish downspout on front of townhouse at rock Davenport
--   --   Piece of siding missing under window bump out above main level door to deck Davenport
--   --   Heat pump not level Jason
--   --   glue potentially needed under island Jill can you take a look
--   --   Trim garage once cleaned out George
--   --   Piece of trim loose on stairs leading to main level George
--   --   Dishwasher needs set and fridge installed 9/3 Jill contacting CJ
--   --   Granite scratches kitchen island Jill will call Greg H
--   --   Hall bath electric cover needed Electrician
--   --   Bulbs needed in dining light Electrician
--   --   House number missing Jill
--   --   Caulk under kitchen island Greg H
--   --   CODED LOCKBOX 3737
--   --   Powder bath light needed
--   --   HVAC covers
--   --   Black shower drain
--   --   Paint overspray on front door Painters
--   --   Micro vent not working 9/16 CJ needs to vent it
--   --   Kitchen island trim missing on right side George
--   --   Floor repair in laundry room? Eagle
--   --   shower door installed 9/18 or 9/19 In process 9/20
--   --   Home Inspection - Thursday, Sep 21 at 9AM
--   --   2 towel bars in bonus room. 1 in others…
--   --   Dented fridge CJ has ordered new doors, hopefully coming soon 10/16
--   --   Touch up trim in laundry room George needs painted
--   --   Bent/damaged drop edger on right side of home Drip edge - roofer
--   --   downspout is buried on front right corner of home
--   --   loose aluminum wrapping on corners of basement door overhand
--   --   loose aluminum wrapping on corners of basement door overhang Davenport
--   --   Clean scuffs off tub in basement Jill
--   --   exhaust fan in basement bathroom not functioning Electrician
--   --   install all screens Jill
--   --   cosmetic items need addressed Painter
--   --   missing attic cover Jill
--   --   loose trim under kitchen island George
--   --   remove paint from all door hinges Painter
--   --   master bathroom window frame not painted/finished Painter
--   --   front door frame has a lot of wiggle room/doesnt lock correctly needs weather stripping
--   --   damaged/warped siding on the base of the townhouse near heat pump Davenport
--   --   bathtub on/off spouts lean down Plumber
--   --   Caulk trim in hall bath tub Painter
--   --   Stone loose on end of first retaining wall Stone guys
--   --   Vinyl under master bath window is bowing out Davenport
--   --   Vinyl under kitchen window bowing out Davenport
--   --   corner of vinyl to be fixed right edge bump out window Davenport
--   --   Replace back panel kitchen island Fred- Kate requested 9/28
--   --   paint scratches on near receptacle kitchen isladn Jill
--   --   Clean overspray off all door knobs and bath accessories Painter
--   --   make sure all towel bars are straight Joe
--   --   bath faucets loose- need to be tightened Plumber
--   --   Trim piece needed on both sides of kitchen sink Fred- Kate requested 9/28
--   --   Weather stripping garage door Jill
--   --   Clean out garage and clean floors Jill
--   --   adjust doors on both smaller bedrooms George
--   --   Crack in tub Maybe Tuesday, Oct 17
--   --   Paint sides of townhouse Painter
--   --   Loose trim on steps Painter
--   --   Areas of “ sloppy or dripping paint” Painter - after Thanksgiving
--   --   Glue on patio door Jill
--   --   the rain gutter over the patio door that leaks, Davenport
--   --   bonus room mirror needs replaced, Paul
--   --   Garage keypad to be installed Jeff, Davenport
--   --   Granite issue - Tom calling Fenco Kate approved slab. Installing 1/5
--   --   Will stormwater flow between townhouses? Will it affect foundation?
--   --   Water pooling in backyard
--   --   Water pooling in backyard Tom will talk to Bub
--   --   Owners say they were told they would get fresh mulch this spring Curb Appeal
--   --   The boards under the patio are showing
--   --   Weather stripping under bottom of patio door Tom (we have it)
--   --   Replace piece of siding damaged by lawn care company Davenport
--   --   Is there still a temporary meter here? SVEC needs to remove it
--   --   Glo Fiber box can we adjust it?
-- -- Ratified Contract? (0)  02.21.2023    
-- -- $2500 Deposit Received (0)  02.23.2023    
-- -- Association Packet Requested (0)  02.21.2023    
-- -- Association Packet Received (0)  02.23.2023    
-- -- Selections Meeting (0)  03.07.2023    
-- -- Selections Sheet Signed (0)  03.22.2023     3/7: sent to Katie
-- -- Amendment for Upgrades (B,S,L,T,BCP) (0)  08.13.2023     8/12: Sent to Jerry to sign
-- -- Deposit For Upgrades Received (0)  03.25.2023    
-- -- Building Permit (30)  11.07.2022    
-- -- Order Roof & Floor Trusses (1)  05.01.2023    
-- -- Order Windows & Doors (0)  05.01.2023    
-- -- Stake Out Home (1)  01.02.2023    
-- -- Excavate (2)  01.02.2023    
-- -- Inspection (Footers) (1)  01.02.2023    
-- -- Inspection (Concrete Wall) (1)  01.31.2023    
-- -- Pour Footers (1)  01.02.2023    
-- -- Set Forms (2)  01.31.2023    
-- -- Pour Foundation Walls (1)  01.31.2023    
-- -- Plumb Slab (2)  03.23.2023    
-- -- Inspection (Plumbing Under Slab) (1)  03.23.2023    
-- -- Inspection (Conduit Under Slab) (1)  03.23.2023    
-- -- Prepare Slab (1)  03.23.2023    
-- -- Inspection (Slab) (1)  03.23.2023    
-- -- Inspection (Drain Tile) (0)  03.23.2023    
-- -- Pour Slab (1)  03.23.2023    
-- -- Settlement Agent Confirmed (0)  02.22.2023    
-- -- Framing I (9)  04.27.2023    
-- -- Order Steps (0)  05.01.2023    
-- -- Order Tubs / Showers (0)  05.20.2023    
-- -- Framing II (8)  04.27.2023    
-- -- Framing III (8)  05.11.2023    
-- -- Verify Window & Roof Structure (0)  12.11.2023    
-- -- Install Stairs (0)  05.17.2023    
-- -- Windows & Doors (0)  05.24.2023    
-- -- House Number and Status in Window (0)  06.14.2023    
-- -- Roofing (0)  05.24.2023    
-- -- Order Cabinets (0)  06.06.2023    
-- -- Order Appliances (0)  07.31.2023    
-- -- Deck (0)  06.12.2023    
-- -- Gutters (0)  08.02.2023    
-- -- Driveway (0)  08.19.2023    
-- -- Patio (0)  08.02.2023    
-- -- Privacy Divider / Fence (0)  09.13.2023    
-- -- Sod / Seed / Landscaping (0)  09.27.2023     front landscaping needed
-- -- HVAC Rough In (4)  06.14.2023    
-- -- Inspection (Rough In HVAC) (1)  06.22.2023    
-- -- Rough In Microwave Vent (0)  12.11.2023    
-- -- Plumbing Rough In (4)  06.22.2023     In process 6/14
-- -- Inspection (Rough In Plumbing) (1)  06.22.2023    
-- -- Electric Rough In (4)  06.22.2023    
-- -- Inspection (Rough In Electric) (1)  06.26.2023    
-- -- Inspection (Deck Piers) (0)  06.26.2023    
-- -- Inspection (Framing) (1)  06.26.2023    
-- -- Exterior Vinyl (0)  07.22.2023     in process 7/16
-- -- Exterior Stone (0)  08.05.2023     in process 8/2
-- -- Insulation (2)  06.26.2023    
-- -- Inspection (Insulation) (1)  06.28.2023    
-- -- Inspection (Electric Service) (0)  08.21.2023    
-- -- Set Electric Meter (0)  09.14.2023    
-- -- Inspection (Main Sewer Line) (0)  03.20.2023    
-- -- Inspection (Main Water Line) (0)  03.20.2023    
-- -- Order Interior Doors & Trim (0)  07.31.2023    
-- -- Drywall (Hang) (4)  07.01.2023     In process 6/28
-- -- Loan Approval (0)  09.21.2023    
-- -- Deed Preparation (0)  08.28.2023    
-- -- Drywall (Tape, Block, Skim, Sand) (6)  07.09.2023     In process 7/1
-- -- Paint 1 (1)  07.12.2023    
-- -- Garage Door (0)  08.23.2023    
-- -- House Numbers (0)  08.30.2023    
-- -- Mailbox (0)  09.24.2023    
-- -- Cabinet Installation (2)  07.22.2023     7/17
-- -- Granite Installation (1)  08.05.2023     8/4
-- -- Interior Trim - Install (3)  08.05.2023     In process 8/2
-- -- Order Plumbing / Lighting Fixtures (0)  08.05.2023    
-- -- Interior Trim - Paint (1)  08.09.2023    
-- -- Luxury Vinyl Plank (3)  08.16.2023    
-- -- Luxury Vinyl Tile (0)  08.16.2023    
-- -- Paint 2 (3)  08.09.2023    
-- -- Cover Floors (1)  08.19.2023    
-- -- Deliver Plumbing / Lighting Fixtures (0)  08.16.2023    
-- -- Shoe Moulding (0)  08.30.2023    
-- -- Shelving, Door Knobs, Fire Extinguisher (0)  09.18.2023     In process 9/13. Needs shelving and mirrors.
-- -- Install Coded Lockbox (add extra keys) (0)  09.13.2023    
-- -- Pay Water / Sewer Taps (0)  08.21.2023    
-- -- Set Water Meter (0)  08.28.2023    
-- -- Electric Trim Out (3)  09.06.2023     In process 9/3
-- -- Ceiling Fans (0)  08.26.2023    
-- -- HVAC Trim Out (1)  09.18.2023     Needs vent covers
-- -- Blower Door Test (1)  10.27.2023    
-- -- Plumbing Trim Out (2)  09.18.2023     Finishing 9/13
-- -- Install Appliances (0)  08.31.2023     Delivery 8/10
-- -- Paint 3 (2)  08.30.2023     In process 8/26
-- -- Carpet (2)  08.19.2023     In process 8/16
-- -- Appraiser Confirms Construction Completion (0)  09.25.2023     9/18 or 9/19
-- -- Inspection (Final HVAC) (1)  09.20.2023    
-- -- Inspection (Final Plumbing) (1)  09.20.2023    
-- -- Inspection (Final Electric) (1)  09.20.2023    
-- -- Inspection (Final Building) (2)  09.20.2023    
-- -- Pre Walk Through (0)  09.25.2023    
-- -- Stain Hardwood Stairs (1)  09.13.2023     In process 9/3
-- -- Cleaning (1)  09.27.2023    
-- -- Certificate of Occupancy (1)  09.27.2023    
-- -- C.O. to Lender (0)  09.27.2023    
-- -- Schedule Closing (0)  09.24.2023    
-- -- Buyer Walk Through (1)  09.28.2023     Wed, Sep 27?
-- -- Payment for Upgrades (0)  09.25.2023    
-- -- Keys to Settlement Agent (0)  09.21.2023    
-- -- Review Settlement Statement (0)  09.27.2023    
-- -- Jerry Signs Closing Documents (0)  08.16.2023    
-- -- Request Trash Tote From POA Manager (0)  09.25.2023    
-- -- Closing (1)  10.02.2023     Brittany @ West View Title (Fri, Sep 29)
-- -- Remove Coded Lockbox (0)  10.07.2023