Few missing boards in m bath framing |
|
|
-- |
-- |
Cover hardwood treads to 2nd level |
And 1st level |
|
-- |
-- |
Cover stairs |
|
|
-- |
-- |
Cover countertops |
|
|
-- |
-- |
Missing oven? I’m assuming it’s now in 86 |
|
|
-- |
-- |
A few dents in the refrigerator at 38 |
CJ can swap out for Tue, Jan 9 |
|
-- |
-- |
Black shower drain needed |
Plumber |
|
-- |
-- |
Black dining light needed |
|
|
-- |
-- |
Silver hall lights need removed |
should be black |
|
-- |
-- |
Silver dining light needs swapped out for black |
should be black |
|
-- |
-- |
missing oven |
CJ, Leisa |
|
-- |
-- |
Trim needed garage |
Trim, George |
|
-- |
-- |
Shoe molding needs completed in the master bathroom |
Trim, George |
|
-- |
-- |
Trim needed in front of bathtubs |
Trim, George |
|
-- |
-- |
I hope sharpie comes off bathtubs-hall bath |
Jill |
|
-- |
-- |
Hall bath light switch cover |
Electrician |
|
-- |
-- |
CODED LOCKBOX 3838 |
|
|
-- |
-- |
Some shelving and mirrors missing |
|
|
-- |
-- |
Remove items from the garage |
|
|
-- |
-- |
Few door knobs missing |
|
|
-- |
-- |
Install patio screen doors, and window screens |
Jill |
|
-- |
-- |
Clean glue off transition strip at landing |
|
|
-- |
-- |
Pressure wash back of house |
|
|
-- |
-- |
Weatherstripping needed basement patio door |
|
|
-- |
-- |
Remove saw an extra electrical supplies from house |
|
|
-- |
-- |
Pressure wash outfront in backtown house |
|
|
-- |
-- |
remove plastic and blue tape from front door threshold |
|
|
-- |
-- |
reclean surfaces and floors after punch is completed. |
|
|
-- |
-- |
Dent in freezer |
1/10 - CJ will swap out 1/11, Leisa |
|
-- |
-- |
Ratified Contract? (0)
06.09.2023 |
|
|
-- |
-- |
$2500 Deposit Received (0)
06.14.2023 |
|
|
-- |
-- |
Association Packet Requested (0)
06.09.2023 |
|
|
-- |
-- |
Association Packet Received (0)
06.14.2023 |
|
|
-- |
-- |
Selections Meeting (0)
08.15.2023 |
8/7 at 11:00 AM |
|
-- |
-- |
Selections Sheet Signed (0)
08.22.2023 |
8/15: Waiting on buyers to sign; |
|
-- |
-- |
Amendment for Upgrades (B,S,L,T,BCP) (0)
08.23.2023 |
8/22: Sent to Jerry to sign; |
|
-- |
-- |
Deposit For Upgrades Received (0)
08.22.2023 |
|
|
-- |
-- |
Building Permit (30)
05.05.2023 |
|
|
-- |
-- |
Order Roof & Floor Trusses (1)
06.26.2023 |
|
|
-- |
-- |
Order Windows & Doors (0)
08.24.2023 |
|
|
-- |
-- |
Stake Out Home (1)
05.18.2023 |
|
|
-- |
-- |
Excavate (2)
05.18.2023 |
|
|
-- |
-- |
Inspection (Footers) (1)
05.18.2023 |
|
|
-- |
-- |
Inspection (Concrete Wall) (1)
05.18.2023 |
|
|
-- |
-- |
Pour Footers (1)
05.18.2023 |
|
|
-- |
-- |
Set Forms (2)
06.05.2023 |
|
|
-- |
-- |
Pour Foundation Walls (1)
06.12.2023 |
|
|
-- |
-- |
Plumb Slab (2)
06.12.2023 |
|
|
-- |
-- |
Inspection (Plumbing Under Slab) (1)
06.26.2023 |
|
|
-- |
-- |
Inspection (Conduit Under Slab) (1)
06.26.2023 |
|
|
-- |
-- |
Prepare Slab (1)
07.10.2023 |
|
|
-- |
-- |
Inspection (Slab) (1)
07.10.2023 |
|
|
-- |
-- |
Inspection (Drain Tile) (0)
10.05.2023 |
|
|
-- |
-- |
Pour Slab (1)
07.10.2023 |
|
|
-- |
-- |
Settlement Agent Confirmed (0)
08.25.2023 |
|
|
-- |
-- |
Framing I (9)
08.03.2023 |
starting Wednesday, July 26 |
|
-- |
-- |
Order Steps (0)
09.18.2023 |
|
|
-- |
-- |
Order Tubs / Showers (0)
09.18.2023 |
|
|
-- |
-- |
Framing II (8)
08.10.2023 |
|
|
-- |
-- |
Framing III (8)
08.23.2023 |
|
|
-- |
-- |
Verify Window & Roof Structure (0)
12.11.2023 |
|
|
-- |
-- |
Install Stairs (0)
09.18.2023 |
|
|
-- |
-- |
Windows & Doors (0)
10.07.2023 |
Missing window bonus room |
|
-- |
-- |
House Number and Status in Window (0)
09.20.2023 |
|
|
-- |
-- |
Roofing (0)
08.31.2023 |
|
|
-- |
-- |
Order Cabinets (0)
09.07.2023 |
|
|
-- |
-- |
Order Appliances (0)
09.11.2023 |
STANDARD SS |
|
-- |
-- |
Deck (0)
10.25.2023 |
12 x 12 DECK |
|
-- |
-- |
Gutters (0)
12.06.2023 |
|
|
-- |
-- |
Driveway (0)
12.03.2023 |
EXPANDED |
|
-- |
-- |
Patio (0)
11.15.2023 |
10 X 10 PATIO |
|
-- |
-- |
Privacy Divider / Fence (0)
12.03.2023 |
10 x 10 PATIO |
|
-- |
-- |
Sod / Seed / Landscaping (0)
01.07.2024 |
|
|
-- |
-- |
HVAC Rough In (4)
09.10.2023 |
|
|
-- |
-- |
Inspection (Rough In HVAC) (1)
09.30.2023 |
|
|
-- |
-- |
Rough In Microwave Vent (0)
12.11.2023 |
|
|
-- |
-- |
Plumbing Rough In (4)
09.23.2023 |
In process 9/16 |
|
-- |
-- |
Inspection (Rough In Plumbing) (1)
09.30.2023 |
|
|
-- |
-- |
Electric Rough In (4)
09.27.2023 |
In process 9/23 |
|
-- |
-- |
Inspection (Rough In Electric) (1)
09.30.2023 |
|
|
-- |
-- |
Inspection (Deck Piers) (0)
10.30.2023 |
|
|
-- |
-- |
Inspection (Framing) (1)
10.04.2023 |
|
|
-- |
-- |
Exterior Vinyl (0)
12.03.2023 |
in process 11/25 |
|
-- |
-- |
Exterior Stone (0)
12.20.2023 |
In process 12/16 |
|
-- |
-- |
Insulation (2)
09.30.2023 |
|
|
-- |
-- |
Inspection (Insulation) (1)
10.04.2023 |
|
|
-- |
-- |
Inspection (Electric Service) (0)
10.30.2023 |
|
|
-- |
-- |
Set Electric Meter (0)
12.09.2023 |
|
|
-- |
-- |
Inspection (Main Sewer Line) (0)
11.09.2023 |
|
|
-- |
-- |
Inspection (Main Water Line) (0)
11.09.2023 |
|
|
-- |
-- |
Order Interior Doors & Trim (0)
11.09.2023 |
|
|
-- |
-- |
Drywall (Hang) (4)
10.07.2023 |
Bonus Room, Bonus Bath. Stocked 10/4 |
|
-- |
-- |
Loan Approval (0)
12.18.2023 |
|
|
-- |
-- |
Deed Preparation (0)
12.18.2023 |
|
|
-- |
-- |
Drywall (Tape, Block, Skim, Sand) (6)
10.21.2023 |
In process 10/18 |
|
-- |
-- |
Paint 1 (1)
10.25.2023 |
|
|
-- |
-- |
Garage Door (0)
11.25.2023 |
|
|
-- |
-- |
House Numbers (0)
12.13.2023 |
|
|
-- |
-- |
Mailbox (0)
12.21.2023 |
|
|
-- |
-- |
Cabinet Installation (2)
10.25.2023 |
|
|
-- |
-- |
Granite Installation (1)
10.28.2023 |
|
|
-- |
-- |
Interior Trim - Install (3)
11.04.2023 |
In process 11/1 |
|
-- |
-- |
Order Plumbing / Lighting Fixtures (0)
11.16.2023 |
|
|
-- |
-- |
Interior Trim - Paint (1)
11.12.2023 |
|
|
-- |
-- |
Luxury Vinyl Plank (3)
11.15.2023 |
|
|
-- |
-- |
Luxury Vinyl Tile (0)
11.15.2023 |
|
|
-- |
-- |
Paint 2 (3)
11.25.2023 |
|
|
-- |
-- |
Cover Floors (1)
11.25.2023 |
|
|
-- |
-- |
Deliver Plumbing / Lighting Fixtures (0)
11.30.2023 |
|
|
-- |
-- |
Shoe Moulding (0)
11.29.2023 |
|
|
-- |
-- |
Shelving, Door Knobs, Fire Extinguisher (0)
12.23.2023 |
Black accessories, Bonus. In process 12/20. Basement shelving and two mirrors missing. |
|
-- |
-- |
Install Coded Lockbox (add extra keys) (0)
12.19.2023 |
|
|
-- |
-- |
Pay Water / Sewer Taps (0)
12.06.2023 |
|
|
-- |
-- |
Set Water Meter (0)
12.06.2023 |
|
|
-- |
-- |
Electric Trim Out (3)
12.09.2023 |
Black |
|
-- |
-- |
Ceiling Fans (0)
12.09.2023 |
NO UPGRADE |
|
-- |
-- |
HVAC Trim Out (1)
12.03.2023 |
|
|
-- |
-- |
Blower Door Test (1)
12.18.2023 |
|
|
-- |
-- |
Plumbing Trim Out (2)
12.06.2023 |
Black. Upstairs plumbing fixtures need installed 12/3 |
|
-- |
-- |
Install Appliances (0)
12.13.2023 |
|
|
-- |
-- |
Paint 3 (2)
11.29.2023 |
|
|
-- |
-- |
Carpet (2)
11.25.2023 |
|
|
-- |
-- |
Appraiser Confirms Construction Completion (0)
12.26.2023 |
|
|
-- |
-- |
Inspection (Final HVAC) (1)
12.26.2023 |
Final Inspection scheduled for 12/21, 12/27/23 |
|
-- |
-- |
Inspection (Final Plumbing) (1)
12.26.2023 |
12/27/23 |
|
-- |
-- |
Inspection (Final Electric) (1)
12.26.2023 |
12/27/23 |
|
-- |
-- |
Inspection (Final Building) (2)
12.28.2023 |
Reinspect, Wed, Dec 27 |
|
-- |
-- |
Pre Walk Through (0)
12.28.2023 |
|
|
-- |
-- |
Stain Hardwood Stairs (1)
12.16.2023 |
|
|
-- |
-- |
Cleaning (1)
12.28.2023 |
Started 12/23 |
|
-- |
-- |
Certificate of Occupancy (1)
12.30.2023 |
|
|
-- |
-- |
C.O. to Lender (0)
12.30.2023 |
|
|
-- |
-- |
Schedule Closing (0)
01.17.2024 |
|
|
-- |
-- |
Buyer Walk Through (1)
01.06.2024 |
|
|
-- |
-- |
Payment for Upgrades (0)
01.02.2024 |
|
|
-- |
-- |
Keys to Settlement Agent (0)
12.21.2023 |
|
|
-- |
-- |
Review Settlement Statement (0)
11.29.2023 |
|
|
-- |
-- |
Jerry Signs Closing Documents (0)
11.28.2023 |
|
|
-- |
-- |
Request Trash Tote From POA Manager (0)
12.11.2023 |
|
|
-- |
-- |
Closing (1)
01.17.2024 |
Brittany @ West View Title |
|
-- |
-- |
Remove Coded Lockbox (0)
01.18.2024 |
|
|