Few missing boards in m bath framing |
|
|
-- |
-- |
Cover hardwood treads to 2nd level |
And 1st level |
|
-- |
-- |
Cover stairs |
|
|
-- |
-- |
Cover countertops |
|
|
-- |
-- |
Missing oven? I’m assuming it’s now in 86 |
|
|
-- |
-- |
A few dents in the refrigerator at 38 |
CJ can swap out for Tue, Jan 9 |
|
-- |
-- |
Black shower drain needed |
Plumber |
|
-- |
-- |
Black dining light needed |
|
|
-- |
-- |
Silver hall lights need removed |
should be black |
|
-- |
-- |
Silver dining light needs swapped out for black |
should be black |
|
-- |
-- |
missing oven |
CJ, Leisa |
|
-- |
-- |
Trim needed garage |
Trim, George |
|
-- |
-- |
Shoe molding needs completed in the master bathroom |
Trim, George |
|
-- |
-- |
Trim needed in front of bathtubs |
Trim, George |
|
-- |
-- |
I hope sharpie comes off bathtubs-hall bath |
Jill |
|
-- |
-- |
Hall bath light switch cover |
Electrician |
|
-- |
-- |
CODED LOCKBOX 3838 |
|
|
-- |
-- |
Some shelving and mirrors missing |
|
|
-- |
-- |
Remove items from the garage |
|
|
-- |
-- |
Few door knobs missing |
|
|
-- |
-- |
Install patio screen doors, and window screens |
Jill |
|
-- |
-- |
Clean glue off transition strip at landing |
|
|
-- |
-- |
Pressure wash back of house |
|
|
-- |
-- |
Weatherstripping needed basement patio door |
|
|
-- |
-- |
Remove saw an extra electrical supplies from house |
|
|
-- |
-- |
Pressure wash outfront in backtown house |
|
|
-- |
-- |
remove plastic and blue tape from front door threshold |
|
|
-- |
-- |
reclean surfaces and floors after punch is completed. |
|
|
-- |
-- |
Dent in freezer |
1/10 - CJ will swap out 1/11, Leisa |
|
-- |
-- |
Ratified Contract? (0) 06.09.2023 |
|
|
-- |
-- |
$2500 Deposit Received (0) 06.14.2023 |
|
|
-- |
-- |
Association Packet Requested (0) 06.09.2023 |
|
|
-- |
-- |
Association Packet Received (0) 06.14.2023 |
|
|
-- |
-- |
Selections Meeting (0) 08.15.2023 |
8/7 at 11:00 AM |
|
-- |
-- |
Selections Sheet Signed (0) 08.22.2023 |
8/15: Waiting on buyers to sign; |
|
-- |
-- |
Amendment for Upgrades (B,S,L,T,BCP) (0) 08.23.2023 |
8/22: Sent to Jerry to sign; |
|
-- |
-- |
Deposit For Upgrades Received (0) 08.22.2023 |
|
|
-- |
-- |
Building Permit (30) 05.05.2023 |
|
|
-- |
-- |
Order Roof & Floor Trusses (1) 06.26.2023 |
|
|
-- |
-- |
Order Windows & Doors (0) 08.24.2023 |
|
|
-- |
-- |
Stake Out Home (1) 05.18.2023 |
|
|
-- |
-- |
Excavate (2) 05.18.2023 |
|
|
-- |
-- |
Inspection (Footers) (1) 05.18.2023 |
|
|
-- |
-- |
Inspection (Concrete Wall) (1) 05.18.2023 |
|
|
-- |
-- |
Pour Footers (1) 05.18.2023 |
|
|
-- |
-- |
Set Forms (2) 06.05.2023 |
|
|
-- |
-- |
Pour Foundation Walls (1) 06.12.2023 |
|
|
-- |
-- |
Plumb Slab (2) 06.12.2023 |
|
|
-- |
-- |
Inspection (Plumbing Under Slab) (1) 06.26.2023 |
|
|
-- |
-- |
Inspection (Conduit Under Slab) (1) 06.26.2023 |
|
|
-- |
-- |
Prepare Slab (1) 07.10.2023 |
|
|
-- |
-- |
Inspection (Slab) (1) 07.10.2023 |
|
|
-- |
-- |
Inspection (Drain Tile) (0) 10.05.2023 |
|
|
-- |
-- |
Pour Slab (1) * 07.10.2023 |
|
|
-- |
-- |
Settlement Agent Confirmed (0) 08.25.2023 |
|
|
-- |
-- |
Framing I (9) 08.03.2023 |
starting Wednesday, July 26 |
|
-- |
-- |
Order Steps (0) 09.18.2023 |
|
|
-- |
-- |
Order Tubs / Showers (0) 09.18.2023 |
|
|
-- |
-- |
Framing II (8) 08.10.2023 |
|
|
-- |
-- |
Framing III (8) * 08.23.2023 |
|
|
-- |
-- |
Verify Window & Roof Structure (0) 12.11.2023 |
|
|
-- |
-- |
Install Stairs (0) 09.18.2023 |
|
|
-- |
-- |
Windows & Doors (0) 10.07.2023 |
Missing window bonus room |
|
-- |
-- |
House Number and Status in Window (0) 09.20.2023 |
|
|
-- |
-- |
Roofing (0) 08.31.2023 |
|
|
-- |
-- |
Order Cabinets (0) 09.07.2023 |
|
|
-- |
-- |
Order Appliances (0) 09.11.2023 |
STANDARD SS |
|
-- |
-- |
Deck (0) 10.25.2023 |
12 x 12 DECK |
|
-- |
-- |
Gutters (0) 12.06.2023 |
|
|
-- |
-- |
Driveway (0) 12.03.2023 |
EXPANDED |
|
-- |
-- |
Patio (0) 11.15.2023 |
10 X 10 PATIO |
|
-- |
-- |
Privacy Divider / Fence (0) 12.03.2023 |
10 x 10 PATIO |
|
-- |
-- |
Sod / Seed / Landscaping (0) 01.07.2024 |
|
|
-- |
-- |
HVAC Rough In (4) 09.10.2023 |
|
|
-- |
-- |
Inspection (Rough In HVAC) (1) 09.30.2023 |
|
|
-- |
-- |
Rough In Microwave Vent (0) 12.11.2023 |
|
|
-- |
-- |
Plumbing Rough In (4) 09.23.2023 |
In process 9/16 |
|
-- |
-- |
Inspection (Rough In Plumbing) (1) 09.30.2023 |
|
|
-- |
-- |
Electric Rough In (4) 09.27.2023 |
In process 9/23 |
|
-- |
-- |
Inspection (Rough In Electric) (1) 09.30.2023 |
|
|
-- |
-- |
Inspection (Deck Piers) (0) 10.30.2023 |
|
|
-- |
-- |
Inspection (Framing) (1) 10.04.2023 |
|
|
-- |
-- |
Exterior Vinyl (0) * 12.03.2023 |
in process 11/25 |
|
-- |
-- |
Exterior Stone (0) 12.20.2023 |
In process 12/16 |
|
-- |
-- |
Insulation (2) 09.30.2023 |
|
|
-- |
-- |
Inspection (Insulation) (1) 10.04.2023 |
|
|
-- |
-- |
Inspection (Electric Service) (0) 10.30.2023 |
|
|
-- |
-- |
Set Electric Meter (0) 12.09.2023 |
|
|
-- |
-- |
Inspection (Main Sewer Line) (0) 11.09.2023 |
|
|
-- |
-- |
Inspection (Main Water Line) (0) 11.09.2023 |
|
|
-- |
-- |
Order Interior Doors & Trim (0) 11.09.2023 |
|
|
-- |
-- |
Drywall (Hang) (4) * 10.07.2023 |
Bonus Room, Bonus Bath. Stocked 10/4 |
|
-- |
-- |
Loan Approval (0) 12.18.2023 |
|
|
-- |
-- |
Deed Preparation (0) 12.18.2023 |
|
|
-- |
-- |
Drywall (Tape, Block, Skim, Sand) (6) * 10.21.2023 |
In process 10/18 |
|
-- |
-- |
Paint 1 (1) 10.25.2023 |
|
|
-- |
-- |
Garage Door (0) 11.25.2023 |
|
|
-- |
-- |
House Numbers (0) 12.13.2023 |
|
|
-- |
-- |
Mailbox (0) 12.21.2023 |
|
|
-- |
-- |
Cabinet Installation (2) * 10.25.2023 |
|
|
-- |
-- |
Granite Installation (1) * 10.28.2023 |
|
|
-- |
-- |
Interior Trim - Install (3) 11.04.2023 |
In process 11/1 |
|
-- |
-- |
Order Plumbing / Lighting Fixtures (0) 11.16.2023 |
|
|
-- |
-- |
Interior Trim - Paint (1) 11.12.2023 |
|
|
-- |
-- |
Luxury Vinyl Plank (3) * 11.15.2023 |
|
|
-- |
-- |
Luxury Vinyl Tile (0) 11.15.2023 |
|
|
-- |
-- |
Paint 2 (3) 11.25.2023 |
|
|
-- |
-- |
Cover Floors (1) 11.25.2023 |
|
|
-- |
-- |
Deliver Plumbing / Lighting Fixtures (0) 11.30.2023 |
|
|
-- |
-- |
Shoe Moulding (0) 11.29.2023 |
|
|
-- |
-- |
Shelving, Door Knobs, Fire Extinguisher (0) 12.23.2023 |
Black accessories, Bonus. In process 12/20. Basement shelving and two mirrors missing. |
|
-- |
-- |
Install Coded Lockbox (add extra keys) (0) 12.19.2023 |
|
|
-- |
-- |
Pay Water / Sewer Taps (0) 12.06.2023 |
|
|
-- |
-- |
Set Water Meter (0) 12.06.2023 |
|
|
-- |
-- |
Electric Trim Out (3) 12.09.2023 |
Black |
|
-- |
-- |
Ceiling Fans (0) 12.09.2023 |
NO UPGRADE |
|
-- |
-- |
HVAC Trim Out (1) 12.03.2023 |
|
|
-- |
-- |
Blower Door Test (1) 12.18.2023 |
|
|
-- |
-- |
Plumbing Trim Out (2) 12.06.2023 |
Black. Upstairs plumbing fixtures need installed 12/3 |
|
-- |
-- |
Install Appliances (0) * 12.13.2023 |
|
|
-- |
-- |
Paint 3 (2) * 11.29.2023 |
|
|
-- |
-- |
Carpet (2) 11.25.2023 |
|
|
-- |
-- |
Appraiser Confirms Construction Completion (0) 12.26.2023 |
|
|
-- |
-- |
Inspection (Final HVAC) (1) 12.26.2023 |
Final Inspection scheduled for 12/21, 12/27/23 |
|
-- |
-- |
Inspection (Final Plumbing) (1) 12.26.2023 |
12/27/23 |
|
-- |
-- |
Inspection (Final Electric) (1) 12.26.2023 |
12/27/23 |
|
-- |
-- |
Inspection (Final Building) (2) * 12.28.2023 |
Reinspect, Wed, Dec 27 |
|
-- |
-- |
Pre Walk Through (0) 12.28.2023 |
|
|
-- |
-- |
Stain Hardwood Stairs (1) 12.16.2023 |
|
|
-- |
-- |
Cleaning (1) 12.28.2023 |
Started 12/23 |
|
-- |
-- |
Certificate of Occupancy (1) * 12.30.2023 |
|
|
-- |
-- |
C.O. to Lender (0) 12.30.2023 |
|
|
-- |
-- |
Schedule Closing (0) 01.17.2024 |
|
|
-- |
-- |
Buyer Walk Through (1) 01.06.2024 |
|
|
-- |
-- |
Payment for Upgrades (0) 01.02.2024 |
|
|
-- |
-- |
Keys to Settlement Agent (0) 12.21.2023 |
|
|
-- |
-- |
Review Settlement Statement (0) 11.29.2023 |
|
|
-- |
-- |
Jerry Signs Closing Documents (0) 11.28.2023 |
|
|
-- |
-- |
Request Trash Tote From POA Manager (0) 12.11.2023 |
|
|
-- |
-- |
Closing (1) 01.17.2024 |
Brittany @ West View Title |
|
-- |
-- |
Remove Coded Lockbox (0) 01.18.2024 |
|
|