7/12: Kate is waiting for buyer to review selections; |
|
|
-- |
-- |
7/12: Kate is waiting for buyer to review selections |
|
|
-- |
-- |
Remove large amount of drywall in small bedroom so room can be finished? |
|
|
-- |
-- |
Fridge in front hallway |
|
|
-- |
-- |
Silver door hinges throughout? |
A mix of black and silver |
|
-- |
-- |
This house only has an oven on site |
|
|
-- |
-- |
I am assuming that bonus room has luxury vinyl plank, but it does not appear to be noted in changes or upgrades |
|
|
-- |
-- |
Base trim needed in garage |
Trim, George |
|
-- |
-- |
Painting pantry? |
Let’s fix so shelving can be installed |
|
-- |
-- |
Large dent master shower |
Jill, Wed, Dec 27 |
|
-- |
-- |
CODED LOCKBOX 3939 |
|
|
-- |
-- |
Install attic cover |
|
|
-- |
-- |
Cable covers needed in garage |
|
|
-- |
-- |
Install screens |
Jill |
|
-- |
-- |
|
|
|
-- |
-- |
Paint touch up |
Painter |
|
-- |
-- |
Clean guest bath tub |
Lynn |
|
-- |
-- |
Repair scratch on cabinet by refrigerator |
Jill |
|
-- |
-- |
Adjust door to the deck where it rubs |
Tom |
|
-- |
-- |
Replace transition strip to stop of first set of steps |
Denny |
|
-- |
-- |
Sand near transition strip |
Painter |
|
-- |
-- |
Paint attic access cover |
Painter |
|
-- |
-- |
Add bracket to each hand rail |
George |
|
-- |
-- |
Push down door hinge pins |
Jill |
|
-- |
-- |
Patio door screen - instal |
|
|
-- |
-- |
Install patio door screen |
Jill |
|
-- |
-- |
Replace broken J channel above front porch |
Davenport |
|
-- |
-- |
Clean out garage |
Jill |
|
-- |
-- |
Pressure wash |
Jill |
|
-- |
-- |
Add additional 2x8 under deck |
Tom |
|
-- |
-- |
Add ceiling fan in living room |
Electrician. Needs installed 1/10 |
|
-- |
-- |
Re-clean high traffic areas after fan installation |
In process 1/10 |
|
-- |
-- |
Pressure washing |
|
|
-- |
-- |
Repair or replace screen door latch |
Contact is Zilda (3/12) |
|
-- |
-- |
Ratified Contract? (0)
05.08.2023 |
|
|
-- |
-- |
$2500 Deposit Received (0)
05.16.2023 |
|
|
-- |
-- |
Association Packet Requested (0)
05.08.2023 |
|
|
-- |
-- |
Association Packet Received (0)
05.11.2023 |
|
|
-- |
-- |
Selections Meeting (0)
07.22.2023 |
|
|
-- |
-- |
Selections Sheet Signed (0)
08.03.2023 |
8/1: Sent to the buyer for signatures; |
|
-- |
-- |
Amendment for Upgrades (B,S,L,T,BCP) (0)
08.26.2023 |
8/25: sent to Jerry to sign |
|
-- |
-- |
Deposit For Upgrades Received (0)
08.25.2023 |
|
|
-- |
-- |
Building Permit (30)
05.05.2023 |
|
|
-- |
-- |
Order Roof & Floor Trusses (1)
06.26.2023 |
|
|
-- |
-- |
Order Windows & Doors (0)
08.24.2023 |
|
|
-- |
-- |
Stake Out Home (1)
05.18.2023 |
|
|
-- |
-- |
Excavate (2)
05.18.2023 |
|
|
-- |
-- |
Inspection (Footers) (1)
05.18.2023 |
|
|
-- |
-- |
Inspection (Concrete Wall) (1)
05.18.2023 |
|
|
-- |
-- |
Pour Footers (1)
05.18.2023 |
|
|
-- |
-- |
Set Forms (2)
06.12.2023 |
|
|
-- |
-- |
Pour Foundation Walls (1)
06.12.2023 |
|
|
-- |
-- |
Plumb Slab (2)
06.12.2023 |
|
|
-- |
-- |
Inspection (Plumbing Under Slab) (1)
06.26.2023 |
|
|
-- |
-- |
Inspection (Conduit Under Slab) (1)
06.26.2023 |
|
|
-- |
-- |
Prepare Slab (1)
07.10.2023 |
|
|
-- |
-- |
Inspection (Slab) (1)
07.10.2023 |
|
|
-- |
-- |
Inspection (Drain Tile) (0)
10.05.2023 |
|
|
-- |
-- |
Pour Slab (1)
07.10.2023 |
|
|
-- |
-- |
Settlement Agent Confirmed (0)
09.01.2023 |
|
|
-- |
-- |
Framing I (9)
08.03.2023 |
|
|
-- |
-- |
Order Steps (0)
09.18.2023 |
|
|
-- |
-- |
Order Tubs / Showers (0)
09.18.2023 |
|
|
-- |
-- |
Framing II (8)
08.10.2023 |
|
|
-- |
-- |
Framing III (8)
08.23.2023 |
|
|
-- |
-- |
Verify Window & Roof Structure (0)
12.11.2023 |
|
|
-- |
-- |
Install Stairs (0)
09.18.2023 |
|
|
-- |
-- |
Windows & Doors (0)
10.11.2023 |
|
|
-- |
-- |
House Number and Status in Window (0)
09.20.2023 |
|
|
-- |
-- |
Roofing (0)
08.31.2023 |
|
|
-- |
-- |
Order Cabinets (0)
09.07.2023 |
|
|
-- |
-- |
Order Appliances (0)
09.11.2023 |
STANDARD SS |
|
-- |
-- |
Deck (0)
10.18.2023 |
12 x 18 DECK |
|
-- |
-- |
Gutters (0)
12.06.2023 |
|
|
-- |
-- |
Driveway (0)
12.03.2023 |
EXPANDED |
|
-- |
-- |
Patio (0)
11.15.2023 |
10 x 10 PATIO |
|
-- |
-- |
Privacy Divider / Fence (0)
12.03.2023 |
|
|
-- |
-- |
Sod / Seed / Landscaping (0)
01.03.2024 |
|
|
-- |
-- |
HVAC Rough In (4)
10.18.2023 |
|
|
-- |
-- |
Inspection (Rough In HVAC) (1)
09.30.2023 |
|
|
-- |
-- |
Rough In Microwave Vent (0)
12.11.2023 |
|
|
-- |
-- |
Plumbing Rough In (4)
09.23.2023 |
in process 9-17 |
|
-- |
-- |
Inspection (Rough In Plumbing) (1)
09.30.2023 |
|
|
-- |
-- |
Electric Rough In (4)
09.27.2023 |
|
|
-- |
-- |
Inspection (Rough In Electric) (1)
09.30.2023 |
|
|
-- |
-- |
Inspection (Deck Piers) (0)
10.30.2023 |
|
|
-- |
-- |
Inspection (Framing) (1)
10.04.2023 |
|
|
-- |
-- |
Exterior Vinyl (0)
12.03.2023 |
in process 11/25 |
|
-- |
-- |
Exterior Stone (0)
12.03.2023 |
|
|
-- |
-- |
Insulation (2)
09.30.2023 |
|
|
-- |
-- |
Inspection (Insulation) (1)
10.04.2023 |
|
|
-- |
-- |
Inspection (Electric Service) (0)
10.30.2023 |
|
|
-- |
-- |
Set Electric Meter (0)
12.11.2023 |
|
|
-- |
-- |
Inspection (Main Sewer Line) (0)
11.09.2023 |
|
|
-- |
-- |
Inspection (Main Water Line) (0)
11.09.2023 |
|
|
-- |
-- |
Order Interior Doors & Trim (0)
11.09.2023 |
|
|
-- |
-- |
Drywall (Hang) (4)
10.11.2023 |
In process 10/7 |
|
-- |
-- |
Loan Approval (0)
12.26.2023 |
|
|
-- |
-- |
Deed Preparation (0)
11.09.2023 |
|
|
-- |
-- |
Drywall (Tape, Block, Skim, Sand) (6)
10.28.2023 |
In process 10/25 |
|
-- |
-- |
Paint 1 (1)
10.28.2023 |
|
|
-- |
-- |
Garage Door (0)
11.25.2023 |
|
|
-- |
-- |
House Numbers (0)
12.13.2023 |
|
|
-- |
-- |
Mailbox (0)
12.21.2023 |
|
|
-- |
-- |
Cabinet Installation (2)
10.25.2023 |
|
|
-- |
-- |
Granite Installation (1)
11.08.2023 |
|
|
-- |
-- |
Interior Trim - Install (3)
11.12.2023 |
In process 11/8 |
|
-- |
-- |
Order Plumbing / Lighting Fixtures (0)
11.16.2023 |
|
|
-- |
-- |
Interior Trim - Paint (1)
11.25.2023 |
|
|
-- |
-- |
Luxury Vinyl Plank (3)
12.09.2023 |
In process 12/6 |
|
-- |
-- |
Luxury Vinyl Tile (0)
12.06.2023 |
|
|
-- |
-- |
Paint 2 (3)
12.03.2023 |
|
|
-- |
-- |
Cover Floors (1)
12.16.2023 |
|
|
-- |
-- |
Deliver Plumbing / Lighting Fixtures (0)
11.30.2023 |
|
|
-- |
-- |
Shoe Moulding (0)
12.16.2023 |
In process 12/13 |
|
-- |
-- |
Shelving, Door Knobs, Fire Extinguisher (0)
12.23.2023 |
Black accessories, Bonus. In process 12/16 |
|
-- |
-- |
Install Coded Lockbox (add extra keys) (0)
12.19.2023 |
|
|
-- |
-- |
Pay Water / Sewer Taps (0)
12.06.2023 |
|
|
-- |
-- |
Set Water Meter (0)
12.06.2023 |
|
|
-- |
-- |
Electric Trim Out (3)
12.23.2023 |
Black. In process 12/16 |
|
-- |
-- |
Ceiling Fans (0)
12.23.2023 |
NO UPGRADE |
|
-- |
-- |
HVAC Trim Out (1)
12.03.2023 |
|
|
-- |
-- |
Blower Door Test (1)
12.21.2023 |
|
|
-- |
-- |
Plumbing Trim Out (2)
12.16.2023 |
Black |
|
-- |
-- |
Install Appliances (0)
12.23.2023 |
One oven on site. Fridge in garage 12/20 |
|
-- |
-- |
Paint 3 (2)
12.03.2023 |
|
|
-- |
-- |
Carpet (2)
12.09.2023 |
|
|
-- |
-- |
Appraiser Confirms Construction Completion (0)
12.26.2023 |
|
|
-- |
-- |
Inspection (Final HVAC) (1)
12.28.2023 |
|
|
-- |
-- |
Inspection (Final Plumbing) (1)
12.28.2023 |
|
|
-- |
-- |
Inspection (Final Electric) (1)
12.28.2023 |
12/27/23 |
|
-- |
-- |
Inspection (Final Building) (2)
12.28.2023 |
Wed, Dec 27 |
|
-- |
-- |
Pre Walk Through (0)
12.26.2023 |
|
|
-- |
-- |
Stain Hardwood Stairs (1)
12.20.2023 |
In process 12/16 |
|
-- |
-- |
Cleaning (1)
12.28.2023 |
|
|
-- |
-- |
Certificate of Occupancy (1)
12.30.2023 |
|
|
-- |
-- |
C.O. to Lender (0)
12.30.2023 |
|
|
-- |
-- |
Schedule Closing (0)
01.02.2024 |
|
|
-- |
-- |
Buyer Walk Through (1)
12.28.2023 |
|
|
-- |
-- |
Payment for Upgrades (0)
12.26.2023 |
|
|
-- |
-- |
Keys to Settlement Agent (0)
12.19.2023 |
|
|
-- |
-- |
Review Settlement Statement (0)
01.02.2024 |
|
|
-- |
-- |
Jerry Signs Closing Documents (0)
01.04.2024 |
|
|
-- |
-- |
Request Trash Tote From POA Manager (0)
12.11.2023 |
|
|
-- |
-- |
Closing (1)
01.03.2024 |
Brittany @ West View Title |
|
-- |
-- |
Remove Coded Lockbox (0)
01.11.2024 |
|
|