CONGERS-2 - 40  ::  1554 Palomino Trail
[ BUILD: 20230690 ]      
CRITICAL PATH   |   INSPECTIONS   |   FLOOR PLANS   |   SELECTIONS   |   SPECS   |   CHANGES   |   NHS
view photo archive
 
--   --   Is electric complete? Various wires in living room
--   --   Really needs to close by mid December if at all possible
--   --   Relatively large hump at the top of the first staircase
--   --   Cover tubs
--   --   Fridge door in this unit is dented…
--   --   Appliances are here- can we cover or move them? Jill
--   --   Settlement Goal = Dec 15
--   --   Paint interior of garage
--   --   Remove siding from garage ASAP
--   --   Plumber arriving Wednesday 12/6
--   --   Cover carpets ASAP
--   --   Shower rod, needed and basement bathroom. On site but needs installed. Paul
--   --   Powder bath mirror needs installed Paul
--   --   Touchup ceiling in small bedroom Painter
--   --   Plumbing needs completed and hall bathroom
--   --   Attic, cover needed Painter
--   --   Master bathroom door does not close. Possible hinge issue? Tom
--   --   Install wire racks in master bathroom Paul
--   --   Coded lockbox 4040
--   --   The kitchen pendant lights seem abnormally high
--   --   Oven needs pushed back into place. Electrician has completed outlet.
--   --   Install hand, towel rack Just hand rack is needed. Hall bath. Paul, Savannah
--   --   Install light cover in the hall bathroom
--   --   Missing globe in master bathroom, light fixture
--   --   Powder bath light needed
--   --   Bonus bathroom needs a light
--   --   Trim utility room door as it does not open or close easily due to carpet Trim, George
--   --   Base trim, needed and garage Trim, George
--   --   Mailbox Tom
--   --   Patch master bedroom escutcheon Painter
--   --   Paint the front door frame Painter
--   --   Remove appliances from garage Jill
--   --   Send it back drywall patch in bonus room Sand and paint, painter
--   --   splash blocks needed off of gutters Tom
--   --   Bath fan repair needed Drywall, Painter
--   --   Smoke detector in upstairs hallway needs repaired Electrician
--   --   Paint attic door cover Painter
--   --   Shower dent in master bathroom Jill
--   --   Paint touch up in a few spots that are pretty large Painter
--   --   $1,000 escrow for landscaping
--   --   Paint the top and bottom of all doors Painters
--   --   Do you places to touch up with paint in the hall Bath
--   --   Paint touch up throughout Painters
--   --   The small window in the bedroom to the left does not close right Tom?
--   --   Screen doors need installed on both doors jill
--   --   There are a lot of paint drips on the force they need removed
--   --   3 screens needed in the basement bonus ring windows
--   --   Pressure wash outfront in backtown house
--   --   Landscaping needs to be finished outside
--   --   Saying the edges of all the doors that are rough feeling throughout town home
--   --   Remove the strip from the patio door threshold
--   --   Clean the frame around the patio door window
--   --   The transition strip on the top of the first set of steps needs to be replaced Denny has been notified. Friday or Tuesday to replace.
--   --   Push all hinges down
--   --   Make sure all the trim throughout the home is clean
--   --   Replace broken water supply line to the refrigerator
--   --   Pocket door on the pantry does not open or close easily it makes a noise
--   --   Silicone around The Wire coming up through the bottom of the cabinets on the island, both ends Tom
--   --   Wipe the freezer and frigerator out a little bit Jill. Fridge is done 12/20
--   --   Fred- Is it possible that we could smooth down the edges of some of the cabinets that are really sharp billing?
--   --   Sand the corners and edges of all the doors throughout the home that are rough
--   --   Pressure wash front
--   --   Lower dining room chandelier, down three links Electrician
--   --   Adjust window in living room
--   --   Adjust master bath door - add pin
--   --   Missing small front piece of gutter downspout Tom
--   --   $1,200 escrow for landscaping
--   --   Double escrow hold back?
-- -- Ratified Contract? (0)  05.04.2023    
-- -- $2500 Deposit Received (0)  05.09.2023    
-- -- Association Packet Requested (0)  05.04.2023    
-- -- Association Packet Received (0)  05.06.2023    
-- -- Selections Meeting (0)  05.26.2023    
-- -- Selections Sheet Signed (0)  06.07.2023     5/26: Sent to Matt
-- -- Amendment for Upgrades (B,S,L,T,BCP) (0)  10.19.2023     6/6: sent to Matt for signature
-- -- Deposit For Upgrades Received (0)  06.07.2023    
-- -- Building Permit (30)  05.05.2023    
-- -- Order Roof & Floor Trusses (1)  06.26.2023    
-- -- Order Windows & Doors (0)  08.24.2023    
-- -- Stake Out Home (1)  05.18.2023    
-- -- Excavate (2)  05.18.2023    
-- -- Inspection (Footers) (1)  05.18.2023    
-- -- Inspection (Concrete Wall) (1)  05.18.2023    
-- -- Pour Footers (1)  05.18.2023    
-- -- Set Forms (2)  06.12.2023    
-- -- Pour Foundation Walls (1)  06.12.2023    
-- -- Plumb Slab (2)  06.12.2023    
-- -- Inspection (Plumbing Under Slab) (1)  06.26.2023    
-- -- Inspection (Conduit Under Slab) (1)  06.26.2023    
-- -- Prepare Slab (1)  07.10.2023    
-- -- Inspection (Slab) (1)  07.10.2023    
-- -- Inspection (Drain Tile) (0)  10.05.2023    
-- -- Pour Slab (1)  07.10.2023    
-- -- Settlement Agent Confirmed (0)  10.21.2023    
-- -- Framing I (9)  08.03.2023    
-- -- Order Steps (0)  09.18.2023    
-- -- Order Tubs / Showers (0)  09.18.2023    
-- -- Framing II (8)  08.10.2023    
-- -- Framing III (8)  08.23.2023    
-- -- Verify Window & Roof Structure (0)  12.11.2023    
-- -- Install Stairs (0)  09.18.2023    
-- -- Windows & Doors (0)  10.04.2023    
-- -- House Number and Status in Window (0)  09.20.2023    
-- -- Roofing (0)  08.31.2023    
-- -- Order Cabinets (0)  09.07.2023    
-- -- Order Appliances (0)  09.14.2023     STANDARD SS
-- -- Deck (0)  10.21.2023     In process 10/7
-- -- Gutters (0)  12.06.2023    
-- -- Driveway (0)  12.03.2023     NO UPGRADE
-- -- Patio (0)  11.15.2023     NO UPGRADE
-- -- Privacy Divider / Fence (0)  12.03.2023    
-- -- Sod / Seed / Landscaping (0)  11.06.2023    
-- -- HVAC Rough In (4)  09.16.2023    
-- -- Inspection (Rough In HVAC) (1)  10.04.2023    
-- -- Rough In Microwave Vent (0)  12.11.2023    
-- -- Plumbing Rough In (4)  09.30.2023    
-- -- Inspection (Rough In Plumbing) (1)  10.04.2023    
-- -- Electric Rough In (4)  09.30.2023    
-- -- Inspection (Rough In Electric) (1)  10.04.2023    
-- -- Inspection (Deck Piers) (0)  10.30.2023    
-- -- Inspection (Framing) (1)  10.04.2023    
-- -- Exterior Vinyl (0)  11.30.2023     Almost completed 11/25
-- -- Exterior Stone (0)  12.06.2023     In process December 3
-- -- Insulation (2)  10.07.2023    
-- -- Inspection (Insulation) (1)  10.09.2023    
-- -- Inspection (Electric Service) (0)  10.30.2023    
-- -- Set Electric Meter (0)  12.11.2023    
-- -- Inspection (Main Sewer Line) (0)  11.09.2023    
-- -- Inspection (Main Water Line) (0)  11.09.2023    
-- -- Order Interior Doors & Trim (0)  11.09.2023    
-- -- Drywall (Hang) (4)  10.14.2023     Bonus Room, Bonus Bath
-- -- Loan Approval (0)  12.06.2023    
-- -- Deed Preparation (0)  11.09.2023    
-- -- Drywall (Tape, Block, Skim, Sand) (6)  10.28.2023     In process 10/25
-- -- Paint 1 (1)  11.01.2023     In process 10/28
-- -- Garage Door (0)  11.25.2023    
-- -- House Numbers (0)  12.14.2023     Jill
-- -- Mailbox (0)  12.21.2023     in process 12/20
-- -- Cabinet Installation (2)  11.04.2023     In process 11/1
-- -- Granite Installation (1)  11.08.2023    
-- -- Interior Trim - Install (3)  11.25.2023     In process 11/15
-- -- Order Plumbing / Lighting Fixtures (0)  11.16.2023    
-- -- Interior Trim - Paint (1)  11.29.2023    
-- -- Luxury Vinyl Plank (3)  12.03.2023     Was ready November 28, but Denny is on another job. Starting as soon as he’s finished.
-- -- Luxury Vinyl Tile (0)  12.03.2023    
-- -- Paint 2 (3)  12.09.2023     In process 12/6
-- -- Cover Floors (1)  12.13.2023    
-- -- Deliver Plumbing / Lighting Fixtures (0)  11.30.2023    
-- -- Shoe Moulding (0)  12.06.2023    
-- -- Shelving, Door Knobs, Fire Extinguisher (0)  12.09.2023     BRUSHED NICKEL, BONUS. In process 12/6
-- -- Install Coded Lockbox (add extra keys) (0)  12.09.2023    
-- -- Pay Water / Sewer Taps (0)  12.06.2023    
-- -- Set Water Meter (0)  12.06.2023    
-- -- Electric Trim Out (3)  12.15.2023     BRUSHED NICKEL. In process. Mostly basement needs completed
-- -- Ceiling Fans (0)  12.13.2023     NO UPGRADE
-- -- HVAC Trim Out (1)  12.06.2023    
-- -- Blower Door Test (1)  12.15.2023     Mon, Dec 11 or Tue, Dec 12
-- -- Plumbing Trim Out (2)  12.09.2023     BRUSHED NICKEL. In process 12/6
-- -- Install Appliances (0)  12.09.2023    
-- -- Paint 3 (2)  12.09.2023    
-- -- Carpet (2)  12.06.2023     being installed 12/4
-- -- Appraiser Confirms Construction Completion (0)  12.19.2023    
-- -- Inspection (Final HVAC) (1)  12.18.2023    
-- -- Inspection (Final Plumbing) (1)  12.18.2023    
-- -- Inspection (Final Electric) (1)  12.18.2023    
-- -- Inspection (Final Building) (2)  12.18.2023     Mon, Dec 18
-- -- Pre Walk Through (0)  12.19.2023    
-- -- Stain Hardwood Stairs (1)  12.16.2023     In process 12/13
-- -- Cleaning (1)  12.20.2023    
-- -- Certificate of Occupancy (1)  12.19.2023    
-- -- C.O. to Lender (0)  12.19.2023    
-- -- Schedule Closing (0)  12.20.2023    
-- -- Buyer Walk Through (1)  12.20.2023     Tuesday, Dec 19, 9AM
-- -- Payment for Upgrades (0)  12.11.2023    
-- -- Keys to Settlement Agent (0)  12.19.2023    
-- -- Review Settlement Statement (0)  12.20.2023    
-- -- Jerry Signs Closing Documents (0)  11.28.2023    
-- -- Request Trash Tote From POA Manager (0)  12.11.2023     We have one extra already!
-- -- Closing (1)  12.26.2023     Brittany @ West View Title - Fri, Dec 22
-- -- Remove Coded Lockbox (0)  01.15.2024     Leaving for repairs