Is electric complete? Various wires in living room |
|
|
-- |
-- |
Really needs to close by mid December if at all possible |
|
|
-- |
-- |
Relatively large hump at the top of the first staircase |
|
|
-- |
-- |
Cover tubs |
|
|
-- |
-- |
Fridge door in this unit |
is dented… |
|
-- |
-- |
Appliances are here- can we cover or move them? |
Jill |
|
-- |
-- |
Settlement Goal = Dec 15 |
|
|
-- |
-- |
Paint interior of garage |
|
|
-- |
-- |
Remove siding from garage |
ASAP |
|
-- |
-- |
Plumber arriving Wednesday 12/6 |
|
|
-- |
-- |
Cover carpets ASAP |
|
|
-- |
-- |
Shower rod, needed and basement bathroom. On site but needs installed. |
Paul |
|
-- |
-- |
Powder bath mirror needs installed |
Paul |
|
-- |
-- |
Touchup ceiling in small bedroom |
Painter |
|
-- |
-- |
Plumbing needs completed and hall bathroom |
|
|
-- |
-- |
Attic, cover needed |
Painter |
|
-- |
-- |
Master bathroom door does not close. Possible hinge issue? |
Tom |
|
-- |
-- |
Install wire racks in master bathroom |
Paul |
|
-- |
-- |
Coded lockbox 4040 |
|
|
-- |
-- |
The kitchen pendant lights seem abnormally high |
|
|
-- |
-- |
Oven needs pushed back into place. Electrician has completed outlet. |
|
|
-- |
-- |
Install hand, towel rack |
Just hand rack is needed. Hall bath. Paul, Savannah |
|
-- |
-- |
Install light cover in the hall bathroom |
|
|
-- |
-- |
Missing globe in master bathroom, light fixture |
|
|
-- |
-- |
Powder bath light needed |
|
|
-- |
-- |
Bonus bathroom needs a light |
|
|
-- |
-- |
Trim utility room door as it does not open or close easily due to carpet |
Trim, George |
|
-- |
-- |
Base trim, needed and garage |
Trim, George |
|
-- |
-- |
Mailbox |
Tom |
|
-- |
-- |
Patch master bedroom escutcheon |
Painter |
|
-- |
-- |
Paint the front door frame |
Painter |
|
-- |
-- |
Remove appliances from garage |
Jill |
|
-- |
-- |
Send it back drywall patch in bonus room |
Sand and paint, painter |
|
-- |
-- |
splash blocks needed off of gutters |
Tom |
|
-- |
-- |
Bath fan repair needed |
Drywall, Painter |
|
-- |
-- |
Smoke detector in upstairs hallway needs repaired |
Electrician |
|
-- |
-- |
Paint attic door cover |
Painter |
|
-- |
-- |
Shower dent in master bathroom |
Jill |
|
-- |
-- |
Paint touch up in a few spots that are pretty large |
Painter |
|
-- |
-- |
$1,000 escrow for landscaping |
|
|
-- |
-- |
Paint the top and bottom of all doors |
Painters |
|
-- |
-- |
Do you places to touch up with paint in the hall Bath |
|
|
-- |
-- |
Paint touch up throughout |
Painters |
|
-- |
-- |
The small window in the bedroom to the left does not close right |
Tom? |
|
-- |
-- |
Screen doors need installed on both doors |
jill |
|
-- |
-- |
There are a lot of paint drips on the force they need removed |
|
|
-- |
-- |
3 screens needed in the basement bonus ring windows |
|
|
-- |
-- |
Pressure wash outfront in backtown house |
|
|
-- |
-- |
Landscaping needs to be finished outside |
|
|
-- |
-- |
Saying the edges of all the doors that are rough feeling throughout town home |
|
|
-- |
-- |
Remove the strip from the patio door threshold |
|
|
-- |
-- |
Clean the frame around the patio door window |
|
|
-- |
-- |
The transition strip on the top of the first set of steps needs to be replaced |
Denny has been notified. Friday or Tuesday to replace. |
|
-- |
-- |
Push all hinges down |
|
|
-- |
-- |
Make sure all the trim throughout the home is clean |
|
|
-- |
-- |
Replace broken water supply line to the refrigerator |
|
|
-- |
-- |
Pocket door on the pantry does not open or close easily it makes a noise |
|
|
-- |
-- |
Silicone around The Wire coming up through the bottom of the cabinets on the island, both ends |
Tom |
|
-- |
-- |
Wipe the freezer and frigerator out a little bit |
Jill. Fridge is done 12/20 |
|
-- |
-- |
Fred- Is it possible that we could smooth down the edges of some of the cabinets that are really sharp billing? |
|
|
-- |
-- |
Sand the corners and edges of all the doors throughout the home that are rough |
|
|
-- |
-- |
Pressure wash front |
|
|
-- |
-- |
Lower dining room chandelier, down three links |
Electrician |
|
-- |
-- |
Adjust window in living room |
|
|
-- |
-- |
Adjust master bath door - add pin |
|
|
-- |
-- |
Missing small front piece of gutter downspout |
Tom |
|
-- |
-- |
$1,200 escrow for landscaping |
|
|
-- |
-- |
Double escrow hold back? |
|
|
-- |
-- |
Ratified Contract? (0) 05.04.2023 |
|
|
-- |
-- |
$2500 Deposit Received (0) 05.09.2023 |
|
|
-- |
-- |
Association Packet Requested (0) 05.04.2023 |
|
|
-- |
-- |
Association Packet Received (0) 05.06.2023 |
|
|
-- |
-- |
Selections Meeting (0) 05.26.2023 |
|
|
-- |
-- |
Selections Sheet Signed (0) 06.07.2023 |
5/26: Sent to Matt |
|
-- |
-- |
Amendment for Upgrades (B,S,L,T,BCP) (0) 10.19.2023 |
6/6: sent to Matt for signature |
|
-- |
-- |
Deposit For Upgrades Received (0) 06.07.2023 |
|
|
-- |
-- |
Building Permit (30) 05.05.2023 |
|
|
-- |
-- |
Order Roof & Floor Trusses (1) 06.26.2023 |
|
|
-- |
-- |
Order Windows & Doors (0) 08.24.2023 |
|
|
-- |
-- |
Stake Out Home (1) 05.18.2023 |
|
|
-- |
-- |
Excavate (2) 05.18.2023 |
|
|
-- |
-- |
Inspection (Footers) (1) 05.18.2023 |
|
|
-- |
-- |
Inspection (Concrete Wall) (1) 05.18.2023 |
|
|
-- |
-- |
Pour Footers (1) 05.18.2023 |
|
|
-- |
-- |
Set Forms (2) 06.12.2023 |
|
|
-- |
-- |
Pour Foundation Walls (1) 06.12.2023 |
|
|
-- |
-- |
Plumb Slab (2) 06.12.2023 |
|
|
-- |
-- |
Inspection (Plumbing Under Slab) (1) 06.26.2023 |
|
|
-- |
-- |
Inspection (Conduit Under Slab) (1) 06.26.2023 |
|
|
-- |
-- |
Prepare Slab (1) 07.10.2023 |
|
|
-- |
-- |
Inspection (Slab) (1) 07.10.2023 |
|
|
-- |
-- |
Inspection (Drain Tile) (0) 10.05.2023 |
|
|
-- |
-- |
Pour Slab (1) * 07.10.2023 |
|
|
-- |
-- |
Settlement Agent Confirmed (0) 10.21.2023 |
|
|
-- |
-- |
Framing I (9) 08.03.2023 |
|
|
-- |
-- |
Order Steps (0) 09.18.2023 |
|
|
-- |
-- |
Order Tubs / Showers (0) 09.18.2023 |
|
|
-- |
-- |
Framing II (8) 08.10.2023 |
|
|
-- |
-- |
Framing III (8) * 08.23.2023 |
|
|
-- |
-- |
Verify Window & Roof Structure (0) 12.11.2023 |
|
|
-- |
-- |
Install Stairs (0) 09.18.2023 |
|
|
-- |
-- |
Windows & Doors (0) 10.04.2023 |
|
|
-- |
-- |
House Number and Status in Window (0) 09.20.2023 |
|
|
-- |
-- |
Roofing (0) 08.31.2023 |
|
|
-- |
-- |
Order Cabinets (0) 09.07.2023 |
|
|
-- |
-- |
Order Appliances (0) 09.14.2023 |
STANDARD SS |
|
-- |
-- |
Deck (0) 10.21.2023 |
In process 10/7 |
|
-- |
-- |
Gutters (0) 12.06.2023 |
|
|
-- |
-- |
Driveway (0) 12.03.2023 |
NO UPGRADE |
|
-- |
-- |
Patio (0) 11.15.2023 |
NO UPGRADE |
|
-- |
-- |
Privacy Divider / Fence (0) 12.03.2023 |
|
|
-- |
-- |
Sod / Seed / Landscaping (0) 11.06.2023 |
|
|
-- |
-- |
HVAC Rough In (4) 09.16.2023 |
|
|
-- |
-- |
Inspection (Rough In HVAC) (1) 10.04.2023 |
|
|
-- |
-- |
Rough In Microwave Vent (0) 12.11.2023 |
|
|
-- |
-- |
Plumbing Rough In (4) 09.30.2023 |
|
|
-- |
-- |
Inspection (Rough In Plumbing) (1) 10.04.2023 |
|
|
-- |
-- |
Electric Rough In (4) 09.30.2023 |
|
|
-- |
-- |
Inspection (Rough In Electric) (1) 10.04.2023 |
|
|
-- |
-- |
Inspection (Deck Piers) (0) 10.30.2023 |
|
|
-- |
-- |
Inspection (Framing) (1) 10.04.2023 |
|
|
-- |
-- |
Exterior Vinyl (0) * 11.30.2023 |
Almost completed 11/25 |
|
-- |
-- |
Exterior Stone (0) 12.06.2023 |
In process December 3 |
|
-- |
-- |
Insulation (2) 10.07.2023 |
|
|
-- |
-- |
Inspection (Insulation) (1) 10.09.2023 |
|
|
-- |
-- |
Inspection (Electric Service) (0) 10.30.2023 |
|
|
-- |
-- |
Set Electric Meter (0) 12.11.2023 |
|
|
-- |
-- |
Inspection (Main Sewer Line) (0) 11.09.2023 |
|
|
-- |
-- |
Inspection (Main Water Line) (0) 11.09.2023 |
|
|
-- |
-- |
Order Interior Doors & Trim (0) 11.09.2023 |
|
|
-- |
-- |
Drywall (Hang) (4) * 10.14.2023 |
Bonus Room, Bonus Bath |
|
-- |
-- |
Loan Approval (0) 12.06.2023 |
|
|
-- |
-- |
Deed Preparation (0) 11.09.2023 |
|
|
-- |
-- |
Drywall (Tape, Block, Skim, Sand) (6) * 10.28.2023 |
In process 10/25 |
|
-- |
-- |
Paint 1 (1) 11.01.2023 |
In process 10/28 |
|
-- |
-- |
Garage Door (0) 11.25.2023 |
|
|
-- |
-- |
House Numbers (0) 12.14.2023 |
Jill |
|
-- |
-- |
Mailbox (0) 12.21.2023 |
in process 12/20 |
|
-- |
-- |
Cabinet Installation (2) * 11.04.2023 |
In process 11/1 |
|
-- |
-- |
Granite Installation (1) * 11.08.2023 |
|
|
-- |
-- |
Interior Trim - Install (3) 11.25.2023 |
In process 11/15 |
|
-- |
-- |
Order Plumbing / Lighting Fixtures (0) 11.16.2023 |
|
|
-- |
-- |
Interior Trim - Paint (1) 11.29.2023 |
|
|
-- |
-- |
Luxury Vinyl Plank (3) * 12.03.2023 |
Was ready November 28, but Denny is on another job. Starting as soon as he’s finished. |
|
-- |
-- |
Luxury Vinyl Tile (0) 12.03.2023 |
|
|
-- |
-- |
Paint 2 (3) 12.09.2023 |
In process 12/6 |
|
-- |
-- |
Cover Floors (1) 12.13.2023 |
|
|
-- |
-- |
Deliver Plumbing / Lighting Fixtures (0) 11.30.2023 |
|
|
-- |
-- |
Shoe Moulding (0) 12.06.2023 |
|
|
-- |
-- |
Shelving, Door Knobs, Fire Extinguisher (0) 12.09.2023 |
BRUSHED NICKEL, BONUS. In process 12/6 |
|
-- |
-- |
Install Coded Lockbox (add extra keys) (0) 12.09.2023 |
|
|
-- |
-- |
Pay Water / Sewer Taps (0) 12.06.2023 |
|
|
-- |
-- |
Set Water Meter (0) 12.06.2023 |
|
|
-- |
-- |
Electric Trim Out (3) 12.15.2023 |
BRUSHED NICKEL. In process. Mostly basement needs completed |
|
-- |
-- |
Ceiling Fans (0) 12.13.2023 |
NO UPGRADE |
|
-- |
-- |
HVAC Trim Out (1) 12.06.2023 |
|
|
-- |
-- |
Blower Door Test (1) 12.15.2023 |
Mon, Dec 11 or Tue, Dec 12 |
|
-- |
-- |
Plumbing Trim Out (2) 12.09.2023 |
BRUSHED NICKEL. In process 12/6 |
|
-- |
-- |
Install Appliances (0) * 12.09.2023 |
|
|
-- |
-- |
Paint 3 (2) * 12.09.2023 |
|
|
-- |
-- |
Carpet (2) 12.06.2023 |
being installed 12/4 |
|
-- |
-- |
Appraiser Confirms Construction Completion (0) 12.19.2023 |
|
|
-- |
-- |
Inspection (Final HVAC) (1) 12.18.2023 |
|
|
-- |
-- |
Inspection (Final Plumbing) (1) 12.18.2023 |
|
|
-- |
-- |
Inspection (Final Electric) (1) 12.18.2023 |
|
|
-- |
-- |
Inspection (Final Building) (2) * 12.18.2023 |
Mon, Dec 18 |
|
-- |
-- |
Pre Walk Through (0) 12.19.2023 |
|
|
-- |
-- |
Stain Hardwood Stairs (1) 12.16.2023 |
In process 12/13 |
|
-- |
-- |
Cleaning (1) 12.20.2023 |
|
|
-- |
-- |
Certificate of Occupancy (1) * 12.19.2023 |
|
|
-- |
-- |
C.O. to Lender (0) 12.19.2023 |
|
|
-- |
-- |
Schedule Closing (0) 12.20.2023 |
|
|
-- |
-- |
Buyer Walk Through (1) 12.20.2023 |
Tuesday, Dec 19, 9AM |
|
-- |
-- |
Payment for Upgrades (0) 12.11.2023 |
|
|
-- |
-- |
Keys to Settlement Agent (0) 12.19.2023 |
|
|
-- |
-- |
Review Settlement Statement (0) 12.20.2023 |
|
|
-- |
-- |
Jerry Signs Closing Documents (0) 11.28.2023 |
|
|
-- |
-- |
Request Trash Tote From POA Manager (0) 12.11.2023 |
We have one extra already! |
|
-- |
-- |
Closing (1) 12.26.2023 |
Brittany @ West View Title - Fri, Dec 22 |
|
-- |
-- |
Remove Coded Lockbox (0) 01.15.2024 |
Leaving for repairs |
|