37 ADDR
CONGERS-2 - 84  ::  1571 Palomino Trail
[ BUILD: 20230693 ]      
CRITICAL PATH   |   INSPECTIONS   |   FLOOR PLANS   |   SELECTIONS   |   SPECS   |   CHANGES   |   NHS
view photo archive
 
TO DO
---
UPGRADES
---
CRITICAL PATH
---
TO DO - COMPLETED OR DELETED
Blemish on side panel k. Island Fred
Cover carpet ASAP Jill
Carpet transition strip needed to the hallway bathroom Eric, Denny
Tint ding in fridge. Not sure anyone will notice but me-but making note of it. 1/10
Drywall repair needed outside of master bedroom Painter. In process 1/25. Needs finished 1/27
Lots of lightbulbs needed in 85 and 84 Jill, Electrician
Microwave vent not functioning Tom, CJ
With lights on 1/13 there are a few dings in fridge doors 2/21: should arrive Mon, Feb 26
Attic cover needed
Hall, bathroom, electric cover needed Electrician
Powder bath light needed Electrician
Can we get gray outlet covers for the kitchen island? Jill
HVAC covers needed HVAC
CODED LOCKBOX 8484
Mirrors needed Paul
Screens Jill
Grey receptacle covers neeed at kitchen island Electrician
Whiteboard needed below front porch
Touchup, screw holes in powder bath near light fixture Painter
Adjust deadbolt patio doors to deck Paul, Joe
Fill and paint screw holes by light and powder bath Painter
Adjust closet doors upstairs Jill
Missing, screw switch plate cover upstairs hall bathroom Electrician
Repaint attic, access store Painter
Clean mud off of carpet in master closet Jill
Mud to be cleaned off carpet all over the upstairs around the plastic Jill
Missing piece of shoe mold, on island, closest to pantry George
Actually missing shoe mold on both sides of island George - on site
Sod
The patio screen door is badly stained and doesn’t seem to close correctly Jill
Touch up paint Painter
Missing screw at the front door hinge Jill
Repair two nicks in hall bath shower wall Jill will check
Remove glue from master bath shower Jill
Adjust closet doors in bedrooms Jill
Paint shoe mold at the front door Painter
Re-clean floors before closing? Kristen 2/28
New refrigerator is inside the front door as of Feb 27, per Leisa
Piece of siding has fallen down in the front Davenport
New Amendment 4/4: sent to Jerry for signatures
Loose siding above main level front windows
Loose siding above main level front window roof Davenport
Damaged siding at back of townhouse by heat pump Davenport
Water entry into basement below back basement windows Tom
Remove insulation next to air handler electrical wiring Tom
Finish the taping at the HVAC plenum Tom
Repair cracked truss Tom
Need 1 piece of weather stripping in front door Jill
Living room window trim needs paint touch ups
Clean around the window of the deck door on inside Jill
Change white receptacles to grey ones Allen
Both sides of the kitchen window
Paint touch ups throughout home Painters
Master bathroom cabinets need some touch ups Jill
Kitchen cabinets need some touch ups Jill
Frame around the basement window on the inside needs replaced, it’s really knocked up bad George or Tom
Caulk the basement window on the outside Tom
Fill and paint inside of basement window frame Painter
What small repairs remain?
UPGRADES - COMPLETED
    White painted cabinetry  
    Calcatta Classique level III quarts  
    Painted steps to the bedroom level  
    Microwave vented to the exterior  
    Expand a 12 x 18 deck  
    Upgraded Carpet Pad  
    Digital Deadbolt  
    Amendment to increase price by $8,060  
CRITICAL PATH - COMPLETED
-- -- Ratified Contract? (0)  07.02.2023    
-- -- $2500 Deposit Received (0)  07.06.2023    
-- -- Association Packet Requested (0)  07.02.2023    
-- -- Association Packet Received (0)  07.08.2023    
-- -- Selections Meeting (0)  07.22.2023    
-- -- Selections Sheet Signed (0)  09.13.2023     9/7: Sent to Kozhin; 9/11: Reminded Kozhin;
-- -- Amendment for Upgrades (B,S,L,T,BCP) (0)  09.14.2023     9/13: Sent to Jerry for signature
-- -- Deposit For Upgrades Received (0)  09.13.2023    
-- -- Building Permit (30) *   06.01.2023    
-- -- Order Roof & Floor Trusses (1)  09.25.2023    
-- -- Order Windows & Doors (0)  10.28.2023    
-- -- Stake Out Home (1)  06.01.2023    
-- -- Excavate (2)  06.01.2023    
-- -- Inspection (Footers) (1)  06.01.2023    
-- -- Inspection (Concrete Wall) (1)  06.01.2023    
-- -- Pour Footers (1) *   06.01.2023    
-- -- Set Forms (2)  06.12.2023    
-- -- Pour Foundation Walls (1)  06.12.2023    
-- -- Plumb Slab (2)  06.26.2023    
-- -- Inspection (Plumbing Under Slab) (1)  06.26.2023    
-- -- Inspection (Conduit Under Slab) (1)  07.24.2023    
-- -- Prepare Slab (1)  07.24.2023    
-- -- Inspection (Slab) (1)  07.24.2023    
-- -- Inspection (Drain Tile) (0)  07.24.2023    
-- -- Pour Slab (1) *   07.24.2023    
-- -- Settlement Agent Confirmed (0)  09.15.2023    
-- -- Framing I (9)  09.11.2023     in process 8/30
-- -- Order Steps (0)  10.12.2023    
-- -- Order Tubs / Showers (0)  10.28.2023    
-- -- Framing II (8)  09.11.2023    
-- -- Framing III (8) *   10.05.2023    
-- -- Verify Window & Roof Structure (0)  12.11.2023    
-- -- Install Stairs (0) *   10.12.2023    
-- -- Windows & Doors (0) *   11.01.2023    
-- -- House Number and Status in Window (0)  11.02.2023    
-- -- Roofing (0) *   10.30.2023    
-- -- Order Cabinets (0)  10.30.2023    
-- -- Order Appliances (0)  09.14.2023     STANDARD SS
-- -- Deck (0)  10.28.2023     12 x 18 DECK
-- -- Gutters (0)  12.20.2023    
-- -- Driveway (0) *   01.31.2024     NO UPGRADE - Tuesday, Jan 30
-- -- Patio (0)  11.15.2023     NO UPGRADE
-- -- Privacy Divider / Fence (0) *   01.19.2024    
-- -- Sod / Seed / Landscaping (0)  02.10.2024    
-- -- HVAC Rough In (4)  10.26.2023     in process 10/14
-- -- Rough In Microwave Vent (0)  12.11.2023    
-- -- Plumbing Rough In (4)  10.28.2023     in process 10/25
-- -- Electric Rough In (4)  11.08.2023     In process 11/4
-- -- Inspection (Rough In HVAC) (1)  11.12.2023    
-- -- Inspection (Rough In Plumbing) (1)  11.12.2023    
-- -- Inspection (Rough In Electric) (1)  11.12.2023    
-- -- Inspection (Framing) (1) *   11.12.2023    
-- -- Inspection (Deck Piers) (0)  12.28.2023    
-- -- Exterior Vinyl (0) *   12.16.2023     In process 12/13
-- -- Exterior Stone (0)  12.20.2023    
-- -- Insulation (2) *   11.12.2023    
-- -- Inspection (Insulation) (1)  11.16.2023    
-- -- Inspection (Electric Service) (0)  12.18.2023    
-- -- Set Electric Meter (0) *   01.08.2024    
-- -- Inspection (Main Sewer Line) (0)  12.18.2023    
-- -- Inspection (Main Water Line) (0)  12.18.2023    
-- -- Order Interior Doors & Trim (0)  12.18.2023    
-- -- Drywall (Hang) (4) *   11.20.2023     NO UPGRADE
-- -- Loan Approval (0)  05.07.2024     USDA
-- -- Deed Preparation (0)  01.18.2024    
-- -- Drywall (Tape, Block, Skim, Sand) (6) *   11.29.2023     In process 11/25
-- -- Paint 1 (1)  12.03.2023     In process 11/29
-- -- Garage Door (0)  12.04.2023    
-- -- House Numbers (0)  01.29.2024    
-- -- Mailbox (0)  12.23.2023    
-- -- Cabinet Installation (2) *   12.03.2023    
-- -- Granite Installation (1) *   12.13.2023    
-- -- Interior Trim - Install (3) *   12.09.2023     In process 12/6
-- -- Order Plumbing / Lighting Fixtures (0)  12.18.2023    
-- -- Interior Trim - Paint (1)  12.13.2023    
-- -- Luxury Vinyl Plank (3) *   12.16.2023     In process 12/13
-- -- Luxury Vinyl Tile (0)  12.16.2023     In process 12/13
-- -- Paint 2 (3)  12.16.2023    
-- -- Cover Floors (0)  12.23.2023    
-- -- Deliver Plumbing / Lighting Fixtures (0)  01.10.2024    
-- -- Shoe Moulding (0)  12.23.2023     In process 12/20
-- -- Shelving, Door Knobs, Fire Extinguisher (1) *   01.27.2024     All mirrors needed 1/19
-- -- Install Coded Lockbox (add extra keys) (0)  01.25.2024    
-- -- Pay Water / Sewer Taps (0)  12.28.2023    
-- -- Set Water Meter (1) *   01.11.2024    
-- -- Electric Trim Out (3) *   01.13.2024     Black. Almost completed 1/13
-- -- Ceiling Fans (0)  01.10.2024     NO UPGRADE
-- -- HVAC Trim Out (1) *   01.17.2024    
-- -- Blower Door Test (1)  01.22.2024    
-- -- Plumbing Trim Out (2) *   01.03.2024     Black. In process 12/23
-- -- Install Appliances (0) *   01.10.2024     On site 12/20
-- -- Paint 3 (2) *   12.20.2023    
-- -- Carpet (2)  12.16.2023    
-- -- Appraiser Confirms Construction Completion (0)  02.29.2024     Wed, Feb 28
-- -- Inspection (Final HVAC) (0)  02.01.2024    
-- -- Inspection (Final Plumbing) (0)  02.01.2024    
-- -- Inspection (Final Electric) (0)  02.01.2024    
-- -- Inspection (Final Building) (4) *   02.05.2024     Reinspect, Fri, Feb 2
-- -- Pre Walk Through (0)  02.12.2024    
-- -- Stain Hardwood Stairs (1) *   12.23.2023    
-- -- Cleaning (1)  02.14.2024     In process 2/10
-- -- Certificate of Occupancy (1) *   02.10.2024    
-- -- C.O. to Lender (0)  02.10.2024    
-- -- Schedule Closing (0)  05.07.2024    
-- -- Buyer Walk Through (1) *   02.15.2024     Tues, Feb 13, 2PM
-- -- Payment for Upgrades (0)  01.25.2024    
-- -- Keys to Settlement Agent (0)  01.25.2024    
-- -- Review Settlement Statement (0)  05.07.2024    
-- -- Jerry Signs Closing Documents (0)  05.07.2024    
-- -- Request Trash Tote From POA Manager (0)  02.02.2024    
-- -- Closing (1)  05.13.2024     Brittany @ West View Title
-- -- Remove Coded Lockbox (0)  05.16.2024