1 28 33 37 45 46 47 48 71 52 70 69 67 53 54 55 56 59 58 57 66 65 64 60 61 62 63 ADDR
CONGERS-2 - 84  ::  1571 Palomino Trail
[ BUILD: 20230693 ]      
CRITICAL PATH   |   INSPECTIONS   |   FLOOR PLANS   |   SELECTIONS   |   SPECS   |   CHANGES   |   NHS
view photo archive
 
--   --   Blemish on side panel k. Island Fred
--   --   Cover carpet ASAP Jill
--   --   Carpet transition strip needed to the hallway bathroom Eric, Denny
--   --   Tint ding in fridge. Not sure anyone will notice but me-but making note of it. 1/10
--   --   Drywall repair needed outside of master bedroom Painter. In process 1/25. Needs finished 1/27
--   --   Lots of lightbulbs needed in 85 and 84 Jill, Electrician
--   --   Microwave vent not functioning Tom, CJ
--   --   With lights on 1/13 there are a few dings in fridge doors 2/21: should arrive Mon, Feb 26
--   --   Attic cover needed
--   --   Hall, bathroom, electric cover needed Electrician
--   --   Powder bath light needed Electrician
--   --   Can we get gray outlet covers for the kitchen island? Jill
--   --   HVAC covers needed HVAC
--   --   CODED LOCKBOX 8484
--   --   Mirrors needed Paul
--   --   Screens Jill
--   --   Grey receptacle covers neeed at kitchen island Electrician
--   --   Whiteboard needed below front porch
--   --   Touchup, screw holes in powder bath near light fixture Painter
--   --   Adjust deadbolt patio doors to deck Paul, Joe
--   --   Fill and paint screw holes by light and powder bath Painter
--   --   Adjust closet doors upstairs Jill
--   --   Missing, screw switch plate cover upstairs hall bathroom Electrician
--   --   Repaint attic, access store Painter
--   --   Clean mud off of carpet in master closet Jill
--   --   Mud to be cleaned off carpet all over the upstairs around the plastic Jill
--   --   Missing piece of shoe mold, on island, closest to pantry George
--   --   Actually missing shoe mold on both sides of island George - on site
--   --   Sod
--   --   The patio screen door is badly stained and doesn’t seem to close correctly Jill
--   --   Touch up paint Painter
--   --   Missing screw at the front door hinge Jill
--   --   Repair two nicks in hall bath shower wall Jill will check
--   --   Remove glue from master bath shower Jill
--   --   Adjust closet doors in bedrooms Jill
--   --   Paint shoe mold at the front door Painter
--   --   Re-clean floors before closing? Kristen 2/28
--   --   New refrigerator is inside the front door as of Feb 27, per Leisa
--   --   Piece of siding has fallen down in the front Davenport
--   --   New Amendment 4/4: sent to Jerry for signatures
--   --   Loose siding above main level front windows
--   --   Loose siding above main level front window roof Davenport
--   --   Damaged siding at back of townhouse by heat pump Davenport
--   --   Water entry into basement below back basement windows Tom
--   --   Remove insulation next to air handler electrical wiring Tom
--   --   Finish the taping at the HVAC plenum Tom
--   --   Repair cracked truss Tom
--   --   Need 1 piece of weather stripping in front door Jill
--   --   Living room window trim needs paint touch ups
--   --   Clean around the window of the deck door on inside Jill
--   --   Change white receptacles to grey ones Allen
--   --   Both sides of the kitchen window
--   --   Paint touch ups throughout home Painters
--   --   Master bathroom cabinets need some touch ups Jill
--   --   Kitchen cabinets need some touch ups Jill
--   --   Frame around the basement window on the inside needs replaced, it’s really knocked up bad George or Tom
--   --   Caulk the basement window on the outside Tom
--   --   Fill and paint inside of basement window frame Painter
-- -- Ratified Contract? (0)  07.02.2023    
-- -- $2500 Deposit Received (0)  07.06.2023    
-- -- Association Packet Requested (0)  07.02.2023    
-- -- Association Packet Received (0)  07.08.2023    
-- -- Selections Meeting (0)  07.22.2023    
-- -- Selections Sheet Signed (0)  09.13.2023     9/7: Sent to Kozhin; 9/11: Reminded Kozhin;
-- -- Amendment for Upgrades (B,S,L,T,BCP) (0)  09.14.2023     9/13: Sent to Jerry for signature
-- -- Deposit For Upgrades Received (0)  09.13.2023    
-- -- Building Permit (30)  06.01.2023    
-- -- Order Roof & Floor Trusses (1)  09.25.2023    
-- -- Order Windows & Doors (0)  10.28.2023    
-- -- Stake Out Home (1)  06.01.2023    
-- -- Excavate (2)  06.01.2023    
-- -- Inspection (Footers) (1)  06.01.2023    
-- -- Inspection (Concrete Wall) (1)  06.01.2023    
-- -- Pour Footers (1)  06.01.2023    
-- -- Set Forms (2)  06.12.2023    
-- -- Pour Foundation Walls (1)  06.12.2023    
-- -- Plumb Slab (2)  06.26.2023    
-- -- Inspection (Plumbing Under Slab) (1)  06.26.2023    
-- -- Inspection (Conduit Under Slab) (1)  07.24.2023    
-- -- Prepare Slab (1)  07.24.2023    
-- -- Inspection (Slab) (1)  07.24.2023    
-- -- Inspection (Drain Tile) (0)  07.24.2023    
-- -- Pour Slab (1)  07.24.2023    
-- -- Settlement Agent Confirmed (0)  09.15.2023    
-- -- Framing I (9)  09.11.2023     in process 8/30
-- -- Order Steps (0)  10.12.2023    
-- -- Order Tubs / Showers (0)  10.28.2023    
-- -- Framing II (8)  09.11.2023    
-- -- Framing III (8)  10.05.2023    
-- -- Verify Window & Roof Structure (0)  12.11.2023    
-- -- Install Stairs (0)  10.12.2023    
-- -- Windows & Doors (0)  11.01.2023    
-- -- House Number and Status in Window (0)  11.02.2023    
-- -- Roofing (0)  10.30.2023    
-- -- Order Cabinets (0)  10.30.2023    
-- -- Order Appliances (0)  09.14.2023     STANDARD SS
-- -- Deck (0)  10.28.2023     12 x 18 DECK
-- -- Gutters (0)  12.20.2023    
-- -- Driveway (0)  01.31.2024     NO UPGRADE - Tuesday, Jan 30
-- -- Patio (0)  11.15.2023     NO UPGRADE
-- -- Privacy Divider / Fence (0)  01.19.2024    
-- -- Sod / Seed / Landscaping (0)  02.10.2024    
-- -- HVAC Rough In (4)  10.26.2023     in process 10/14
-- -- Inspection (Rough In HVAC) (1)  11.12.2023    
-- -- Rough In Microwave Vent (0)  12.11.2023    
-- -- Plumbing Rough In (4)  10.28.2023     in process 10/25
-- -- Inspection (Rough In Plumbing) (1)  11.12.2023    
-- -- Electric Rough In (4)  11.08.2023     In process 11/4
-- -- Inspection (Rough In Electric) (1)  11.12.2023    
-- -- Inspection (Deck Piers) (0)  12.28.2023    
-- -- Inspection (Framing) (1)  11.12.2023    
-- -- Exterior Vinyl (0)  12.16.2023     In process 12/13
-- -- Exterior Stone (0)  12.20.2023    
-- -- Insulation (2)  11.12.2023    
-- -- Inspection (Insulation) (1)  11.16.2023    
-- -- Inspection (Electric Service) (0)  12.18.2023    
-- -- Set Electric Meter (0)  01.08.2024    
-- -- Inspection (Main Sewer Line) (0)  12.18.2023    
-- -- Inspection (Main Water Line) (0)  12.18.2023    
-- -- Order Interior Doors & Trim (0)  12.18.2023    
-- -- Drywall (Hang) (4)  11.20.2023     NO UPGRADE
-- -- Loan Approval (0)  05.07.2024     USDA
-- -- Deed Preparation (0)  01.18.2024    
-- -- Drywall (Tape, Block, Skim, Sand) (6)  11.29.2023     In process 11/25
-- -- Paint 1 (1)  12.03.2023     In process 11/29
-- -- Garage Door (0)  12.04.2023    
-- -- House Numbers (0)  01.29.2024    
-- -- Mailbox (0)  12.23.2023    
-- -- Cabinet Installation (2)  12.03.2023    
-- -- Granite Installation (1)  12.13.2023    
-- -- Interior Trim - Install (3)  12.09.2023     In process 12/6
-- -- Order Plumbing / Lighting Fixtures (0)  12.18.2023    
-- -- Interior Trim - Paint (1)  12.13.2023    
-- -- Luxury Vinyl Plank (3)  12.16.2023     In process 12/13
-- -- Luxury Vinyl Tile (0)  12.16.2023     In process 12/13
-- -- Paint 2 (3)  12.16.2023    
-- -- Cover Floors (1)  12.23.2023    
-- -- Deliver Plumbing / Lighting Fixtures (0)  01.10.2024    
-- -- Shoe Moulding (0)  12.23.2023     In process 12/20
-- -- Shelving, Door Knobs, Fire Extinguisher (0)  01.27.2024     All mirrors needed 1/19
-- -- Install Coded Lockbox (add extra keys) (0)  01.25.2024    
-- -- Pay Water / Sewer Taps (0)  12.28.2023    
-- -- Set Water Meter (0)  01.11.2024    
-- -- Electric Trim Out (3)  01.13.2024     Black. Almost completed 1/13
-- -- Ceiling Fans (0)  01.10.2024     NO UPGRADE
-- -- HVAC Trim Out (1)  01.17.2024    
-- -- Blower Door Test (1)  01.22.2024    
-- -- Plumbing Trim Out (2)  01.03.2024     Black. In process 12/23
-- -- Install Appliances (0)  01.10.2024     On site 12/20
-- -- Paint 3 (2)  12.20.2023    
-- -- Carpet (2)  12.16.2023    
-- -- Appraiser Confirms Construction Completion (0)  02.29.2024     Wed, Feb 28
-- -- Inspection (Final HVAC) (1)  02.01.2024    
-- -- Inspection (Final Plumbing) (1)  02.01.2024    
-- -- Inspection (Final Electric) (1)  02.01.2024    
-- -- Inspection (Final Building) (2)  02.05.2024     Reinspect, Fri, Feb 2
-- -- Pre Walk Through (0)  02.12.2024    
-- -- Stain Hardwood Stairs (1)  12.23.2023    
-- -- Cleaning (1)  02.14.2024     In process 2/10
-- -- Certificate of Occupancy (1)  02.10.2024    
-- -- C.O. to Lender (0)  02.10.2024    
-- -- Schedule Closing (0)  05.07.2024    
-- -- Buyer Walk Through (1)  02.15.2024     Tues, Feb 13, 2PM
-- -- Payment for Upgrades (0)  01.25.2024    
-- -- Keys to Settlement Agent (0)  01.25.2024    
-- -- Review Settlement Statement (0)  05.07.2024    
-- -- Jerry Signs Closing Documents (0)  05.07.2024    
-- -- Request Trash Tote From POA Manager (0)  02.02.2024    
-- -- Closing (1)  05.13.2024     Brittany @ West View Title
-- -- Remove Coded Lockbox (0)  05.16.2024