CONGERS-2 - 80  ::  1467 Appaloosa Court
[ BUILD: 20230717 ]      
CRITICAL PATH   |   INSPECTIONS   |   FLOOR PLANS   |   SELECTIONS   |   SPECS   |   CHANGES   |   NHS
view photo archive
 
--   --  
--   --  
--   --   Hardwood treads to third level installed Tom will swap them out
--   --   Finish drywall in garage
--   --   CODED LOCKBOX 8080
--   --   Few lightbulbs needed in bonus room ceiling fixture Jill
--   --   Touch up paint needed
--   --   Can Davenport check trim for nail holes and clean white board? Davenport, Jeremy. White board cleaned.
--   --   Electric trim out needs to install outlet for microwave Electrician
--   --   Electric trim out needs to be finished in front outlet Electrician
--   --   Install refrigerator. Where is it? CJ. In process 2/21
--   --   Install all HVAC covers
--   --   Strange wiring upstairs. The hall light switch operates the bathroom, light and fan, and the bathroom light switches don’t seem functional. Electrician
--   --   Plug holes in patio doors Kristen
--   --   Cable cover, needed in garage Buddy
--   --   Whiteboard needed below back patio doors Kenny
--   --   Glue in master shower Lynn says someone is coming to do it- KK
--   --   Fill trim holes in vanity shoe mold all baths Painter
--   --   Caulk in all vanity side spalshes Painter
--   --   Install screens Kristen
--   --   Patch trim holes in top board Davenport
--   --   Clean out garage Kenny. Very few items. Dust is in a pile.
--   --   clean off patio Pressure Wash- Buddy or Kenny
--   --   Back patio door sticks Paul
--   --   Repaint handrails Painter
--   --   Install switchplate in powder bath Electrician
--   --   reclean cabinets Lynn or Courtney
--   --   Repaint black stir treads Painter
--   --   Secure right side deck railing ( loose) Kenny
--   --   Clean our master shower after glue is removed - Courtney
--   --   Adjust patio door to make it easier to lock Paul
--   --   Paint attic cover Painter
--   --   Touch up paint door edges Painter
--   --   Secure remote holder for fan in master Kenny
--   --   Paint touch up throughout Painter
--   --   Order Mailbox! Should arrive by Thu, Mar 14
--   --   Floors will need to be re-cleaned before closing Lynn
--   --   Ceiling touch up needed at stairs Blue-Taped, Painter
--   --   Small paint touchup needed in garage Painter
--   --   Sweep up dust pile Kristen
--   --   Install mailboxes
--   --   Front door handle not working properly Savannah
--   --   Door to patio does not operate correctly
-- -- Ratified Contract? (0)  07.02.2023    
-- -- $2500 Deposit Received (0)  07.06.2023    
-- -- Association Packet Requested (0)  07.02.2023    
-- -- Association Packet Received (0)  07.08.2023    
-- -- Selections Meeting (0)  07.22.2023    
-- -- Selections Sheet Signed (0)  07.28.2023     7/22: Kate is waiting for buyer to review selections;
-- -- Amendment for Upgrades (B,S,L,T,BCP) (0)  01.29.2024     8/15: Sent to Jerry to sign
-- -- Deposit For Upgrades Received (0)  08.15.2023    
-- -- Building Permit (30)  06.22.2023    
-- -- Order Roof & Floor Trusses (1)  10.05.2023    
-- -- Order Windows & Doors (0)  10.26.2023    
-- -- Stake Out Home (1)  07.02.2023    
-- -- Excavate (2)  08.03.2023    
-- -- Inspection (Footers) (1)  09.25.2023    
-- -- Inspection (Concrete Wall) (1)  09.25.2023    
-- -- Pour Footers (1)  09.11.2023    
-- -- Set Forms (2)  09.11.2023    
-- -- Pour Foundation Walls (1)  09.11.2023    
-- -- Plumb Slab (2)  09.11.2023     in process 8/30
-- -- Inspection (Plumbing Under Slab) (1)  09.25.2023    
-- -- Inspection (Conduit Under Slab) (1)  09.25.2023    
-- -- Prepare Slab (1)  09.18.2023    
-- -- Inspection (Slab) (1)  09.25.2023    
-- -- Inspection (Drain Tile) (0)  09.25.2023    
-- -- Pour Slab (1) *   09.21.2023    
-- -- Settlement Agent Confirmed (0)  08.19.2023    
-- -- Framing I (9)  10.05.2023    
-- -- Order Steps (0)  10.26.2023    
-- -- Order Tubs / Showers (0)  10.26.2023    
-- -- Framing II (8)  10.16.2023    
-- -- Framing III (8) *   10.16.2023    
-- -- Verify Window & Roof Structure (0)  12.13.2023    
-- -- Install Stairs (0)  10.26.2023    
-- -- Windows & Doors (0)  11.09.2023    
-- -- House Number and Status in Window (0)  11.13.2023    
-- -- Roofing (0)  10.30.2023    
-- -- Order Cabinets (0)  12.06.2023    
-- -- Order Appliances (0)  09.14.2023     STANDARD SS
-- -- Deck (0)  10.28.2023     12 X 12 DECK
-- -- Gutters (0)  01.27.2024    
-- -- Driveway (0)  02.07.2024     EXPANDED
-- -- Patio (0)  01.03.2024     NO UPGRADE
-- -- Privacy Divider / Fence (0)  02.24.2024     Patio privacy panels needed. In process 2/21
-- -- Sod / Seed / Landscaping (0)  03.30.2024     Partially complete 2/17
-- -- HVAC Rough In (4)  11.12.2023     In process 11/1
-- -- Inspection (Rough In HVAC) (1)  12.20.2023    
-- -- Rough In Microwave Vent (0)  12.13.2023    
-- -- Plumbing Rough In (4)  12.03.2023    
-- -- Inspection (Rough In Plumbing) (1)  12.20.2023    
-- -- Electric Rough In (4)  12.20.2023    
-- -- Inspection (Rough In Electric) (1)  12.20.2023    
-- -- Inspection (Deck Piers) (0)  01.18.2024    
-- -- Inspection (Framing) (1)  12.20.2023    
-- -- Exterior Vinyl (0) *   01.18.2024     In process 1/10
-- -- Exterior Stone (0)  02.08.2024     in process 1/27
-- -- Insulation (2)  12.09.2023    
-- -- Inspection (Insulation) (1)  01.03.2024    
-- -- Inspection (Electric Service) (0)  01.15.2024    
-- -- Set Electric Meter (0)  01.18.2024    
-- -- Inspection (Main Sewer Line) (0)  01.18.2024    
-- -- Inspection (Main Water Line) (0)  01.18.2024    
-- -- Order Interior Doors & Trim (0)  01.18.2024    
-- -- Drywall (Hang) (4) *   12.20.2023     Bonus Room, Bonus Bath. In process 12/16
-- -- Loan Approval (0)  02.05.2024    
-- -- Deed Preparation (0)  01.29.2024    
-- -- Drywall (Tape, Block, Skim, Sand) (6) *   01.10.2024     In process 1/10
-- -- Paint 1 (1)  01.10.2024    
-- -- Garage Door (0)  02.03.2024    
-- -- House Numbers (0)  02.17.2024    
-- -- Mailbox (0)  02.24.2024     In process 2/21
-- -- Cabinet Installation (2) *   01.06.2024    
-- -- Granite Installation (1) *   01.27.2024    
-- -- Interior Trim - Install (3)  01.17.2024     In process 1/13
-- -- Order Plumbing / Lighting Fixtures (0)  01.25.2024    
-- -- Interior Trim - Paint (1)  01.25.2024    
-- -- Luxury Vinyl Plank (3) *   02.03.2024     In process 1/31
-- -- Luxury Vinyl Tile (0)  01.31.2024    
-- -- Paint 2 (3)  02.03.2024    
-- -- Cover Floors (1)  02.10.2024    
-- -- Deliver Plumbing / Lighting Fixtures (0)  02.05.2024    
-- -- Shoe Moulding (0)  02.14.2024     In process 2/10
-- -- Shelving, Door Knobs, Fire Extinguisher (0)  02.10.2024     Mirrors needed 2/7
-- -- Install Coded Lockbox (add extra keys) (0)  02.10.2024    
-- -- Pay Water / Sewer Taps (0)  02.05.2024    
-- -- Set Water Meter (0)  02.08.2024    
-- -- Electric Trim Out (3)  02.10.2024     Black Standard. In process 2/7
-- -- Ceiling Fans (0)  02.10.2024     NO UPGRADE
-- -- HVAC Trim Out (1)  02.17.2024     Needs hvac covers 2/10 and heat pump
-- -- Blower Door Test (1)  02.21.2024     Mon, Feb 19
-- -- Plumbing Trim Out (2)  02.10.2024     Black Standard. In process 2/7
-- -- Install Appliances (0) *   02.19.2024     Just need refrigerator
-- -- Paint 3 (2) *   02.07.2024    
-- -- Carpet (2)  02.07.2024    
-- -- Appraiser Confirms Construction Completion (0)  03.25.2024    
-- -- Inspection (Final HVAC) (1)  02.22.2024    
-- -- Inspection (Final Plumbing) (1)  02.22.2024    
-- -- Inspection (Final Electric) (1)  02.22.2024    
-- -- Inspection (Final Building) (2) *   02.22.2024     Wed, Feb 21
-- -- Pre Walk Through (0)  02.22.2024    
-- -- Stain Hardwood Stairs (1)  02.14.2024     In process 2/10
-- -- Cleaning (1)  02.24.2024     In process 2/21
-- -- Certificate of Occupancy (1) *   02.23.2024    
-- -- C.O. to Lender (0)  02.23.2024    
-- -- Schedule Closing (0)  03.25.2024    
-- -- Buyer Walk Through (1)  02.24.2024     Saturday, Feb 24 at 10AM
-- -- Payment for Upgrades (0)  02.22.2024    
-- -- Keys to Settlement Agent (0)  02.24.2024    
-- -- Review Settlement Statement (0)  03.05.2024    
-- -- Jerry Signs Closing Documents (0)  03.25.2024    
-- -- Request Trash Tote From POA Manager (0)  02.22.2024    
-- -- Closing (1)  03.25.2024     Brittany @ West View Title
-- -- Remove Coded Lockbox (0)  04.04.2024