37 ADDR
CONGERS-2 - 41  ::  1450 Appaloosa Court
[ BUILD: 20230928 ]      
CRITICAL PATH   |   INSPECTIONS   |   FLOOR PLANS   |   SELECTIONS   |   SPECS   |   CHANGES   |   NHS
view photo archive
 
TO DO
---
UPGRADES
---
CRITICAL PATH
---
TO DO - COMPLETED OR DELETED
Broken dining window room, trim, can this be repaired?
Needs venting for microwave
Broken window frame. Repairable?
Make sure vinyl folks don’t forget to patch the nail holes on the whiteboard blew the top front windows Davenport - below the top front windows
Cover carpet asap
Patch drywall hole above closet door Blue taped, Painter, Drywaller
Light needed in garage
Grey glue stuck to door Jill
Powder bath light needed Electrician
Multiple light covers needed throughout. Switchplate. . In bonus room
Attic cover needed Painter. Needs painting 3/13
CODED LOCKBOX 4141
Drywall repair needed in garage painters
Drywall repair need near front door painters
Drywall patch needed on ceiling of kitchen painters
Appliances did not come with hoses for hookups. CJ is ordering Monday, will arrive Tuesday, and CJ will then install appliances. In process 3/13
Screen door needs installed Tom
Paint touch up needed Painter
Large scratch hall bath New cabinet front is in, but needs installed
Variety of drywall repair is needed in garage
Variety of the repairs needed in garage Drywall and paint
Cover cable outlet in garage Tom
Bathtub hole in bonus Tuesday, March 19
Significant gash in stair molding to bedroom level Skirt - trim, painter - on the way to bedroom level
Tighten one snap light in living room to the ceiling Electrician
Patio door to deck does not lock easily Paul or Joe or Savannah
Clean out garage Jill
Put attic, access panel in place Painter or Jill
Remove stairs from master bedroom and master bathroom Remove ladders
Upstairs closet doors to be adjusted Jill
Small area to touch up paint in living room Painter
Small area to touch up paint in living room
Need sod before closing can happen
Paint touchup needed in garage Painter
Remove glue from master bath tub Jill
Repaint molding at front door interior Painter
Shampoo bonus room carpet Jill
Scrape garage floor
Change handrail brackets to black
Paint touch up throughout
Make sure buyers transferred utilities
Fill in the nail holes in cabinet trim in all bathrooms Jill
Fill in the nail holes in cabinet trim in all bathrooms
scrape garage floor
Remove glue master shower
gash in trim to second floor
change handrail brackets to black
Paint touch up throughout
Missing Exterior Attic Vent Jeremy - Davenport
Missing Exterior Attic Vent
UPGRADES - COMPLETED
    Finished Bonus Room  
    Finished Bonus Bath  
    Expanded Driveway  
    Microwave vented to Exterior  
    French Model refrigeratorerator  
    Upgraded LVT in all baths adn laundry  
    Amendment to increase price by $19,695  
CRITICAL PATH - COMPLETED
-- -- Ratified Contract? (0)  10.04.2023    
-- -- $2500 Deposit Received (0)  10.10.2023    
-- -- Association Packet Requested (0)  10.04.2023    
-- -- Association Packet Received (0)  10.08.2023    
-- -- Selections Meeting (0)  10.08.2023    
-- -- Selections Sheet Signed (0)  10.10.2023     10/8: Sent to Tekle;
-- -- Amendment for Upgrades (B,S,L,T,BCP) (0)  10.11.2023     10/10: Sent to Jerry
-- -- Deposit For Upgrades Received (0)  10.10.2023    
-- -- Building Permit (30) *   09.11.2023    
-- -- Order Roof & Floor Trusses (1)  11.06.2023    
-- -- Order Windows & Doors (0)  11.20.2023    
-- -- Stake Out Home (1)  08.14.2023    
-- -- Excavate (2)  08.14.2023    
-- -- Inspection (Footers) (1)  08.14.2023    
-- -- Inspection (Concrete Wall) (1)  10.05.2023    
-- -- Pour Footers (1) *   08.14.2023    
-- -- Set Forms (2)  09.11.2023    
-- -- Pour Foundation Walls (1)  09.11.2023    
-- -- Plumb Slab (2)  09.18.2023    
-- -- Inspection (Plumbing Under Slab) (1)  10.05.2023    
-- -- Inspection (Conduit Under Slab) (1)  10.05.2023    
-- -- Prepare Slab (1)  10.05.2023    
-- -- Inspection (Slab) (1)  10.05.2023    
-- -- Inspection (Drain Tile) (0)  10.05.2023    
-- -- Pour Slab (1) *   10.19.2023    
-- -- Settlement Agent Confirmed (0)  10.13.2023    
-- -- Framing I (9)  10.26.2023    
-- -- Order Steps (0)  11.20.2023    
-- -- Order Tubs / Showers (0)  11.20.2023    
-- -- Framing II (8)  10.26.2023    
-- -- Framing III (8) *   11.25.2023    
-- -- Verify Window & Roof Structure (0)  12.13.2023    
-- -- Install Stairs (0) *   11.25.2023    
-- -- Windows & Doors (0) *   12.13.2023    
-- -- House Number and Status in Window (0)  12.13.2023    
-- -- Roofing (0) *   12.13.2023    
-- -- Order Cabinets (0)  12.19.2023    
-- -- Order Appliances (0)  03.07.2024     FRENCH. On site need installed.
-- -- Deck (0)  01.10.2024    
-- -- Gutters (0)  02.05.2024    
-- -- Driveway (0) *   03.06.2024    
-- -- Patio (0)  03.06.2024     Needs poured 2/28
-- -- Privacy Divider / Fence (0) *   02.24.2024     Patio privacy panels needed. In process 2/21
-- -- Sod / Seed / Landscaping (0)  03.28.2024    
-- -- HVAC Rough In (4)  12.13.2023     in process 12/3
-- -- Rough In Microwave Vent (0)  12.13.2023    
-- -- Plumbing Rough In (4)  12.16.2023     in process 12/3
-- -- Electric Rough In (4)  12.20.2023     In process 12/16
-- -- Inspection (Rough In HVAC) (1)  12.26.2023    
-- -- Inspection (Rough In Plumbing) (1)  12.26.2023    
-- -- Inspection (Rough In Electric) (1)  12.26.2023    
-- -- Inspection (Framing) (1) *   12.26.2023    
-- -- Inspection (Deck Piers) (0)  02.19.2024    
-- -- Exterior Vinyl (0) *   02.05.2024     In process 1/19
-- -- Exterior Stone (0)  02.28.2024     Patio privacy panels needed. In process 2/21
-- -- Insulation (2) *   01.03.2024     Ready 12/21
-- -- Inspection (Insulation) (1)  01.03.2024    
-- -- Inspection (Electric Service) (0)  02.08.2024    
-- -- Set Electric Meter (0) *   03.06.2024    
-- -- Inspection (Main Sewer Line) (0)  02.05.2024    
-- -- Inspection (Main Water Line) (0)  02.05.2024    
-- -- Order Interior Doors & Trim (0)  02.05.2024    
-- -- Drywall (Hang) (4) *   01.03.2024    
-- -- Loan Approval (0)  11.10.2023    
-- -- Deed Preparation (0)  02.22.2024    
-- -- Drywall (Tape, Block, Skim, Sand) (6) *   01.17.2024     In process 1/10
-- -- Paint 1 (1)  01.25.2024    
-- -- Garage Door (0)  02.24.2024     In process 2/21
-- -- House Numbers (0)  03.09.2024    
-- -- Mailbox (0)  03.28.2024    
-- -- Cabinet Installation (2) *   01.25.2024     Jan 24
-- -- Granite Installation (1) *   01.27.2024    
-- -- Interior Trim - Install (3) *   02.07.2024     In process 2/3
-- -- Order Plumbing / Lighting Fixtures (0)  02.08.2024    
-- -- Interior Trim - Paint (1)  02.07.2024    
-- -- Luxury Vinyl Plank (3) *   02.17.2024     In process 2/14
-- -- Luxury Vinyl Tile (0)  02.17.2024     In process 2/10
-- -- Paint 2 (3)  01.27.2024    
-- -- Cover Floors (0)  02.24.2024    
-- -- Deliver Plumbing / Lighting Fixtures (0)  02.15.2024    
-- -- Shoe Moulding (0)  02.21.2024    
-- -- Shelving, Door Knobs, Fire Extinguisher (1) *   02.28.2024     Shelving in 2/24
-- -- Install Coded Lockbox (add extra keys) (0)  03.07.2024    
-- -- Pay Water / Sewer Taps (0)  02.19.2024    
-- -- Set Water Meter (1) *   02.26.2024    
-- -- Electric Trim Out (3) *   03.09.2024     Still needs a bit done 3/2
-- -- Ceiling Fans (0)  03.02.2024    
-- -- HVAC Trim Out (1) *   03.02.2024    
-- -- Blower Door Test (1)  03.14.2024     all 4 3/12
-- -- Plumbing Trim Out (2) *   02.28.2024     In process 2/24
-- -- Install Appliances (0) *   03.14.2024     French. In process 3/13
-- -- Paint 3 (2) *   02.24.2024    
-- -- Carpet (2)  02.21.2024     In process 2/14
-- -- Appraiser Confirms Construction Completion (0)  04.01.2024    
-- -- Inspection (Final HVAC) (0)  03.18.2024     Anticipating final 3/13
-- -- Inspection (Final Plumbing) (0)  03.18.2024    
-- -- Inspection (Final Electric) (0)  03.18.2024    
-- -- Inspection (Final Building) (4) *   03.18.2024    
-- -- Pre Walk Through (0)  03.22.2024    
-- -- Stain Hardwood Stairs (1) *   03.06.2024    
-- -- Cleaning (1)  03.30.2024     after 42
-- -- Certificate of Occupancy (1) *   03.22.2024    
-- -- C.O. to Lender (0)  03.22.2024    
-- -- Schedule Closing (0)  03.26.2024    
-- -- Buyer Walk Through (1) *   04.01.2024     Monday, 1PM
-- -- Payment for Upgrades (0)  03.22.2024    
-- -- Keys to Settlement Agent (0)  03.22.2024    
-- -- Review Settlement Statement (0)  03.22.2024    
-- -- Jerry Signs Closing Documents (0)  03.22.2024    
-- -- Request Trash Tote From POA Manager (0)  03.28.2024    
-- -- Closing (1)  04.02.2024     Brittany @ West View Title
-- -- Remove Coded Lockbox (0)  04.08.2024