Broken dining window room, trim, can this be repaired? |
|
|
-- |
-- |
Needs venting for microwave |
|
|
-- |
-- |
Broken window frame. Repairable? |
|
|
-- |
-- |
Make sure vinyl folks don’t forget to patch the nail holes on the whiteboard blew the top front windows |
Davenport - below the top front windows |
|
-- |
-- |
Cover carpet asap |
|
|
-- |
-- |
Patch drywall hole above closet door |
Blue taped, Painter, Drywaller |
|
-- |
-- |
Light needed in garage |
|
|
-- |
-- |
Grey glue stuck to door |
Jill |
|
-- |
-- |
Powder bath light needed |
Electrician |
|
-- |
-- |
Multiple light covers needed throughout. Switchplate. . |
In bonus room |
|
-- |
-- |
Attic cover needed |
Painter. Needs painting 3/13 |
|
-- |
-- |
CODED LOCKBOX 4141 |
|
|
-- |
-- |
Drywall repair needed in garage |
painters |
|
-- |
-- |
Drywall repair need near front door |
painters |
|
-- |
-- |
Drywall patch needed on ceiling of kitchen |
painters |
|
-- |
-- |
Appliances did not come with hoses for hookups. CJ is ordering Monday, will arrive Tuesday, and CJ will then install appliances. |
In process 3/13 |
|
-- |
-- |
Screen door needs installed |
Tom |
|
-- |
-- |
Paint touch up needed |
Painter |
|
-- |
-- |
Large scratch hall bath |
New cabinet front is in, but needs installed |
|
-- |
-- |
Variety of drywall repair is needed in garage |
|
|
-- |
-- |
Variety of the repairs needed in garage |
Drywall and paint |
|
-- |
-- |
Cover cable outlet in garage |
Tom |
|
-- |
-- |
Bathtub hole in bonus |
Tuesday, March 19 |
|
-- |
-- |
Significant gash in stair molding to bedroom level |
Skirt - trim, painter - on the way to bedroom level |
|
-- |
-- |
Tighten one snap light in living room to the ceiling |
Electrician |
|
-- |
-- |
Patio door to deck does not lock easily |
Paul or Joe or Savannah |
|
-- |
-- |
Clean out garage |
Jill |
|
-- |
-- |
Put attic, access panel in place |
Painter or Jill |
|
-- |
-- |
Remove stairs from master bedroom and master bathroom |
Remove ladders |
|
-- |
-- |
Upstairs closet doors to be adjusted |
Jill |
|
-- |
-- |
Small area to touch up paint in living room |
Painter |
|
-- |
-- |
Small area to touch up paint in living room |
|
|
-- |
-- |
Need sod before closing can happen |
|
|
-- |
-- |
|
|
|
-- |
-- |
Paint touchup needed in garage |
Painter |
|
-- |
-- |
Remove glue from master bath tub |
Jill |
|
-- |
-- |
Repaint molding at front door interior |
Painter |
|
-- |
-- |
Shampoo bonus room carpet |
Jill |
|
-- |
-- |
Scrape garage floor |
|
|
-- |
-- |
Change handrail brackets to black |
|
|
-- |
-- |
Paint touch up throughout |
|
|
-- |
-- |
Make sure buyers transferred utilities |
|
|
-- |
-- |
Fill in the nail holes in cabinet trim in all bathrooms |
Jill |
|
-- |
-- |
Fill in the nail holes in cabinet trim in all bathrooms |
|
|
-- |
-- |
scrape garage floor |
|
|
-- |
-- |
Remove glue master shower |
|
|
-- |
-- |
gash in trim to second floor |
|
|
-- |
-- |
change handrail brackets to black |
|
|
-- |
-- |
Paint touch up throughout |
|
|
-- |
-- |
Missing Exterior Attic Vent |
Jeremy - Davenport |
|
-- |
-- |
Missing Exterior Attic Vent |
|
|
-- |
-- |
Ratified Contract? (0) 10.04.2023 |
|
|
-- |
-- |
$2500 Deposit Received (0) 10.10.2023 |
|
|
-- |
-- |
Association Packet Requested (0) 10.04.2023 |
|
|
-- |
-- |
Association Packet Received (0) 10.08.2023 |
|
|
-- |
-- |
Selections Meeting (0) 10.08.2023 |
|
|
-- |
-- |
Selections Sheet Signed (0) 10.10.2023 |
10/8: Sent to Tekle; |
|
-- |
-- |
Amendment for Upgrades (B,S,L,T,BCP) (0) 10.11.2023 |
10/10: Sent to Jerry |
|
-- |
-- |
Deposit For Upgrades Received (0) 10.10.2023 |
|
|
-- |
-- |
Building Permit (30) 09.11.2023 |
|
|
-- |
-- |
Order Roof & Floor Trusses (1) 11.06.2023 |
|
|
-- |
-- |
Order Windows & Doors (0) 11.20.2023 |
|
|
-- |
-- |
Stake Out Home (1) 08.14.2023 |
|
|
-- |
-- |
Excavate (2) 08.14.2023 |
|
|
-- |
-- |
Inspection (Footers) (1) 08.14.2023 |
|
|
-- |
-- |
Inspection (Concrete Wall) (1) 10.05.2023 |
|
|
-- |
-- |
Pour Footers (1) 08.14.2023 |
|
|
-- |
-- |
Set Forms (2) 09.11.2023 |
|
|
-- |
-- |
Pour Foundation Walls (1) 09.11.2023 |
|
|
-- |
-- |
Plumb Slab (2) 09.18.2023 |
|
|
-- |
-- |
Inspection (Plumbing Under Slab) (1) 10.05.2023 |
|
|
-- |
-- |
Inspection (Conduit Under Slab) (1) 10.05.2023 |
|
|
-- |
-- |
Prepare Slab (1) 10.05.2023 |
|
|
-- |
-- |
Inspection (Slab) (1) 10.05.2023 |
|
|
-- |
-- |
Inspection (Drain Tile) (0) 10.05.2023 |
|
|
-- |
-- |
Pour Slab (1) * 10.19.2023 |
|
|
-- |
-- |
Settlement Agent Confirmed (0) 10.13.2023 |
|
|
-- |
-- |
Framing I (9) 10.26.2023 |
|
|
-- |
-- |
Order Steps (0) 11.20.2023 |
|
|
-- |
-- |
Order Tubs / Showers (0) 11.20.2023 |
|
|
-- |
-- |
Framing II (8) 10.26.2023 |
|
|
-- |
-- |
Framing III (8) * 11.25.2023 |
|
|
-- |
-- |
Verify Window & Roof Structure (0) 12.13.2023 |
|
|
-- |
-- |
Install Stairs (0) 11.25.2023 |
|
|
-- |
-- |
Windows & Doors (0) 12.13.2023 |
|
|
-- |
-- |
House Number and Status in Window (0) 12.13.2023 |
|
|
-- |
-- |
Roofing (0) 12.13.2023 |
|
|
-- |
-- |
Order Cabinets (0) 12.19.2023 |
|
|
-- |
-- |
Order Appliances (0) 03.07.2024 |
FRENCH. On site need installed. |
|
-- |
-- |
Deck (0) 01.10.2024 |
|
|
-- |
-- |
Gutters (0) 02.05.2024 |
|
|
-- |
-- |
Driveway (0) 03.06.2024 |
|
|
-- |
-- |
Patio (0) 03.06.2024 |
Needs poured 2/28 |
|
-- |
-- |
Privacy Divider / Fence (0) 02.24.2024 |
Patio privacy panels needed. In process 2/21 |
|
-- |
-- |
Sod / Seed / Landscaping (0) 03.28.2024 |
|
|
-- |
-- |
HVAC Rough In (4) 12.13.2023 |
in process 12/3 |
|
-- |
-- |
Inspection (Rough In HVAC) (1) 12.26.2023 |
|
|
-- |
-- |
Rough In Microwave Vent (0) 12.13.2023 |
|
|
-- |
-- |
Plumbing Rough In (4) 12.16.2023 |
in process 12/3 |
|
-- |
-- |
Inspection (Rough In Plumbing) (1) 12.26.2023 |
|
|
-- |
-- |
Electric Rough In (4) 12.20.2023 |
In process 12/16 |
|
-- |
-- |
Inspection (Rough In Electric) (1) 12.26.2023 |
|
|
-- |
-- |
Inspection (Deck Piers) (0) 02.19.2024 |
|
|
-- |
-- |
Inspection (Framing) (1) 12.26.2023 |
|
|
-- |
-- |
Exterior Vinyl (0) * 02.05.2024 |
In process 1/19 |
|
-- |
-- |
Exterior Stone (0) 02.28.2024 |
Patio privacy panels needed. In process 2/21 |
|
-- |
-- |
Insulation (2) 01.03.2024 |
Ready 12/21 |
|
-- |
-- |
Inspection (Insulation) (1) 01.03.2024 |
|
|
-- |
-- |
Inspection (Electric Service) (0) 02.08.2024 |
|
|
-- |
-- |
Set Electric Meter (0) 03.06.2024 |
|
|
-- |
-- |
Inspection (Main Sewer Line) (0) 02.05.2024 |
|
|
-- |
-- |
Inspection (Main Water Line) (0) 02.05.2024 |
|
|
-- |
-- |
Order Interior Doors & Trim (0) 02.05.2024 |
|
|
-- |
-- |
Drywall (Hang) (4) * 01.03.2024 |
|
|
-- |
-- |
Loan Approval (0) 11.10.2023 |
|
|
-- |
-- |
Deed Preparation (0) 02.22.2024 |
|
|
-- |
-- |
Drywall (Tape, Block, Skim, Sand) (6) * 01.17.2024 |
In process 1/10 |
|
-- |
-- |
Paint 1 (1) 01.25.2024 |
|
|
-- |
-- |
Garage Door (0) 02.24.2024 |
In process 2/21 |
|
-- |
-- |
House Numbers (0) 03.09.2024 |
|
|
-- |
-- |
Mailbox (0) 03.28.2024 |
|
|
-- |
-- |
Cabinet Installation (2) * 01.25.2024 |
Jan 24 |
|
-- |
-- |
Granite Installation (1) * 01.27.2024 |
|
|
-- |
-- |
Interior Trim - Install (3) 02.07.2024 |
In process 2/3 |
|
-- |
-- |
Order Plumbing / Lighting Fixtures (0) 02.08.2024 |
|
|
-- |
-- |
Interior Trim - Paint (1) 02.07.2024 |
|
|
-- |
-- |
Luxury Vinyl Plank (3) * 02.17.2024 |
In process 2/14 |
|
-- |
-- |
Luxury Vinyl Tile (0) 02.17.2024 |
In process 2/10 |
|
-- |
-- |
Paint 2 (3) 01.27.2024 |
|
|
-- |
-- |
Cover Floors (1) 02.24.2024 |
|
|
-- |
-- |
Deliver Plumbing / Lighting Fixtures (0) 02.15.2024 |
|
|
-- |
-- |
Shoe Moulding (0) 02.21.2024 |
|
|
-- |
-- |
Shelving, Door Knobs, Fire Extinguisher (0) 02.28.2024 |
Shelving in 2/24 |
|
-- |
-- |
Install Coded Lockbox (add extra keys) (0) 03.07.2024 |
|
|
-- |
-- |
Pay Water / Sewer Taps (0) 02.19.2024 |
|
|
-- |
-- |
Set Water Meter (0) 02.26.2024 |
|
|
-- |
-- |
Electric Trim Out (3) 03.09.2024 |
Still needs a bit done 3/2 |
|
-- |
-- |
Ceiling Fans (0) 03.02.2024 |
|
|
-- |
-- |
HVAC Trim Out (1) 03.02.2024 |
|
|
-- |
-- |
Blower Door Test (1) 03.14.2024 |
all 4 3/12 |
|
-- |
-- |
Plumbing Trim Out (2) 02.28.2024 |
In process 2/24 |
|
-- |
-- |
Install Appliances (0) * 03.14.2024 |
French. In process 3/13 |
|
-- |
-- |
Paint 3 (2) * 02.24.2024 |
|
|
-- |
-- |
Carpet (2) 02.21.2024 |
In process 2/14 |
|
-- |
-- |
Appraiser Confirms Construction Completion (0) 04.01.2024 |
|
|
-- |
-- |
Inspection (Final HVAC) (1) 03.18.2024 |
Anticipating final 3/13 |
|
-- |
-- |
Inspection (Final Plumbing) (1) 03.18.2024 |
|
|
-- |
-- |
Inspection (Final Electric) (1) 03.18.2024 |
|
|
-- |
-- |
Inspection (Final Building) (2) * 03.18.2024 |
|
|
-- |
-- |
Pre Walk Through (0) 03.22.2024 |
|
|
-- |
-- |
Stain Hardwood Stairs (1) 03.06.2024 |
|
|
-- |
-- |
Cleaning (1) 03.30.2024 |
after 42 |
|
-- |
-- |
Certificate of Occupancy (1) * 03.22.2024 |
|
|
-- |
-- |
C.O. to Lender (0) 03.22.2024 |
|
|
-- |
-- |
Schedule Closing (0) 03.26.2024 |
|
|
-- |
-- |
Buyer Walk Through (1) 04.01.2024 |
Monday, 1PM |
|
-- |
-- |
Payment for Upgrades (0) 03.22.2024 |
|
|
-- |
-- |
Keys to Settlement Agent (0) 03.22.2024 |
|
|
-- |
-- |
Review Settlement Statement (0) 03.22.2024 |
|
|
-- |
-- |
Jerry Signs Closing Documents (0) 03.22.2024 |
|
|
-- |
-- |
Request Trash Tote From POA Manager (0) 03.28.2024 |
|
|
-- |
-- |
Closing (1) 04.02.2024 |
Brittany @ West View Title |
|
-- |
-- |
Remove Coded Lockbox (0) 04.08.2024 |
|
|