|
-- |
-- |
Fix board off master bath |
|
|
-- |
-- |
Trim holes need patched here as well by Davenport |
|
|
-- |
-- |
Is the garage really getting LVT? I think maybe that’s supposed to state something else |
|
|
-- |
-- |
Buyer Financing Issues - No Need To Rush This One! |
|
|
-- |
-- |
Cover carpet ASAP |
|
|
-- |
-- |
No Rush - Not Under Contract |
|
|
-- |
-- |
Appliances in garage here. Maybe fridge can be used for 42. |
|
|
-- |
-- |
Very large paint spill on the back deck |
|
|
-- |
-- |
I would recommend completing paint three and covering floors ASAP and high traffic areas. Cleaning up lots of trash and extra supplies laying around. |
|
|
-- |
-- |
Steps drying 3/9 |
|
|
-- |
-- |
Powder light needs set after plumber |
|
|
-- |
-- |
Dented fridge door |
Leisa has ordered. Entire new refrigerator has been ordered. |
|
-- |
-- |
Attic cover needed |
Painters |
|
-- |
-- |
Remove glue in master bathroom shower |
Drywallers/Jill |
|
-- |
-- |
Install attic cover |
Jill |
|
-- |
-- |
CODED LOCKBOX 4343 |
|
|
-- |
-- |
Clean few items out of the garage |
Jill |
|
-- |
-- |
Install screens |
Jill |
|
-- |
-- |
View cabinet, touch ups needed |
Few - Jill |
|
-- |
-- |
Side trim needed at island |
Corner, George - we have the material |
|
-- |
-- |
Scratch on island countertop |
Greg will take a look |
|
-- |
-- |
Mud to be removed on carpets |
Jill/Kristen |
|
-- |
-- |
Hammer nails down on eck |
|
|
-- |
-- |
pressure wash front and back |
Just front |
|
-- |
-- |
crack in upper right corner of pantry door |
|
|
-- |
-- |
paint touchup throughout |
painter |
|
-- |
-- |
Secure two snap lights to living room ceiling |
electrician |
|
-- |
-- |
redo trim at both roof posts |
Davenport |
|
-- |
-- |
secure feastener to front downspout |
Davenport |
|
-- |
-- |
Exterior- living room windows- gray vertical trim piece to be secured |
Davenport |
|
-- |
-- |
fix trim around garage door |
Davenport |
|
-- |
-- |
remove temporary piece of wood under deck |
Tom |
|
-- |
-- |
finish insulation in bonus room ( closet adn above door) |
|
|
-- |
-- |
Ratified Contract? (0) 10.04.2023 |
|
|
-- |
-- |
$2500 Deposit Received (0) 04.06.2024 |
Need new deposit |
|
-- |
-- |
Association Packet Requested (0) 10.04.2023 |
|
|
-- |
-- |
Association Packet Received (0) 10.08.2023 |
|
|
-- |
-- |
Selections Meeting (0) 11.02.2023 |
|
|
-- |
-- |
Selections Sheet Signed (0) 11.28.2023 |
11/6: Sent to Basu for signatures |
|
-- |
-- |
Amendment for Upgrades (B,S,L,T,BCP) (0) 11.29.2023 |
11/27: Sent to Jerry for signatures; |
|
-- |
-- |
Deposit For Upgrades Received (0) 11.28.2023 |
|
|
-- |
-- |
Building Permit (30) 08.14.2023 |
|
|
-- |
-- |
Order Roof & Floor Trusses (1) 11.06.2023 |
|
|
-- |
-- |
Order Windows & Doors (0) 11.20.2023 |
|
|
-- |
-- |
Stake Out Home (1) 08.14.2023 |
|
|
-- |
-- |
Excavate (2) 08.14.2023 |
|
|
-- |
-- |
Inspection (Footers) (1) 08.14.2023 |
|
|
-- |
-- |
Inspection (Concrete Wall) (1) 10.05.2023 |
|
|
-- |
-- |
Pour Footers (1) 08.14.2023 |
|
|
-- |
-- |
Set Forms (2) 09.11.2023 |
|
|
-- |
-- |
Pour Foundation Walls (1) 09.11.2023 |
|
|
-- |
-- |
Plumb Slab (2) 10.05.2023 |
|
|
-- |
-- |
Inspection (Plumbing Under Slab) (1) 10.05.2023 |
|
|
-- |
-- |
Inspection (Conduit Under Slab) (1) 10.05.2023 |
|
|
-- |
-- |
Prepare Slab (1) 09.18.2023 |
|
|
-- |
-- |
Inspection (Slab) (1) 10.05.2023 |
|
|
-- |
-- |
Inspection (Drain Tile) (0) 10.05.2023 |
|
|
-- |
-- |
Pour Slab (1) * 09.18.2023 |
|
|
-- |
-- |
Settlement Agent Confirmed (0) 12.01.2023 |
11/29: sent to Brittany |
|
-- |
-- |
Framing I (9) 10.26.2023 |
|
|
-- |
-- |
Order Steps (0) 11.20.2023 |
|
|
-- |
-- |
Order Tubs / Showers (0) 11.20.2023 |
|
|
-- |
-- |
Framing II (8) 10.26.2023 |
|
|
-- |
-- |
Framing III (8) * 11.25.2023 |
|
|
-- |
-- |
Verify Window & Roof Structure (0) 12.13.2023 |
|
|
-- |
-- |
Install Stairs (0) 11.25.2023 |
|
|
-- |
-- |
Windows & Doors (0) 12.13.2023 |
|
|
-- |
-- |
House Number and Status in Window (0) 12.13.2023 |
|
|
-- |
-- |
Roofing (0) 12.13.2023 |
|
|
-- |
-- |
Order Cabinets (0) 12.19.2023 |
|
|
-- |
-- |
Order Appliances (0) 03.14.2024 |
Standard |
|
-- |
-- |
Deck (0) 01.07.2024 |
|
|
-- |
-- |
Gutters (0) 02.05.2024 |
|
|
-- |
-- |
Driveway (0) 02.21.2024 |
|
|
-- |
-- |
Patio (0) 03.09.2024 |
|
|
-- |
-- |
Privacy Divider / Fence (0) 02.26.2024 |
Patio privacy panels needed. In process 2/21 |
|
-- |
-- |
Sod / Seed / Landscaping (0) 03.30.2024 |
|
|
-- |
-- |
HVAC Rough In (4) 12.16.2023 |
In process 12/9 |
|
-- |
-- |
Inspection (Rough In HVAC) (1) 12.26.2023 |
12/27/23 |
|
-- |
-- |
Rough In Microwave Vent (0) 12.16.2023 |
|
|
-- |
-- |
Plumbing Rough In (4) 12.13.2023 |
In process 12/9 |
|
-- |
-- |
Inspection (Rough In Plumbing) (1) 12.26.2023 |
|
|
-- |
-- |
Electric Rough In (4) 01.03.2024 |
In process 12/20 |
|
-- |
-- |
Inspection (Rough In Electric) (1) 01.03.2024 |
12/27/23 |
|
-- |
-- |
Inspection (Deck Piers) (0) 02.19.2024 |
|
|
-- |
-- |
Inspection (Framing) (1) 01.03.2024 |
12/27/23 |
|
-- |
-- |
Exterior Vinyl (0) * 01.27.2024 |
In process 1/19 |
|
-- |
-- |
Exterior Stone (0) 01.27.2024 |
|
|
-- |
-- |
Insulation (2) 01.03.2024 |
|
|
-- |
-- |
Inspection (Insulation) (1) 01.06.2024 |
|
|
-- |
-- |
Inspection (Electric Service) (0) 02.08.2024 |
|
|
-- |
-- |
Set Electric Meter (0) 03.06.2024 |
|
|
-- |
-- |
Inspection (Main Sewer Line) (0) 02.05.2024 |
|
|
-- |
-- |
Inspection (Main Water Line) (0) 02.05.2024 |
|
|
-- |
-- |
Order Interior Doors & Trim (0) 02.05.2024 |
|
|
-- |
-- |
Drywall (Hang) (4) * 01.10.2024 |
In process 1/10 |
|
-- |
-- |
Loan Approval (0) 04.04.2024 |
Cash |
|
-- |
-- |
Deed Preparation (0) 04.04.2024 |
|
|
-- |
-- |
Drywall (Tape, Block, Skim, Sand) (6) * 01.25.2024 |
In process 1/17 |
|
-- |
-- |
Paint 1 (1) 01.27.2024 |
|
|
-- |
-- |
Garage Door (0) 02.07.2024 |
|
|
-- |
-- |
House Numbers (0) 03.09.2024 |
|
|
-- |
-- |
Mailbox (0) 03.28.2024 |
|
|
-- |
-- |
Cabinet Installation (2) * 01.27.2024 |
|
|
-- |
-- |
Granite Installation (1) * 02.10.2024 |
|
|
-- |
-- |
Interior Trim - Install (3) 02.10.2024 |
In process 2/7 |
|
-- |
-- |
Order Plumbing / Lighting Fixtures (0) 02.08.2024 |
|
|
-- |
-- |
Interior Trim - Paint (1) 02.14.2024 |
|
|
-- |
-- |
Luxury Vinyl Plank (3) * 02.24.2024 |
In process 2/21 |
|
-- |
-- |
Luxury Vinyl Tile (0) 02.24.2024 |
|
|
-- |
-- |
Paint 2 (3) 01.31.2024 |
|
|
-- |
-- |
Cover Floors (1) 03.09.2024 |
|
|
-- |
-- |
Deliver Plumbing / Lighting Fixtures (0) 02.15.2024 |
|
|
-- |
-- |
Shoe Moulding (0) 02.28.2024 |
|
|
-- |
-- |
Shelving, Door Knobs, Fire Extinguisher (0) 04.03.2024 |
next week 3/18 |
|
-- |
-- |
Install Coded Lockbox (add extra keys) (0) 04.06.2024 |
|
|
-- |
-- |
Pay Water / Sewer Taps (0) 02.19.2024 |
|
|
-- |
-- |
Set Water Meter (0) 02.26.2024 |
|
|
-- |
-- |
Electric Trim Out (3) 03.13.2024 |
In process 3/9 |
|
-- |
-- |
Ceiling Fans (0) 03.09.2024 |
|
|
-- |
-- |
HVAC Trim Out (1) 03.09.2024 |
|
|
-- |
-- |
Blower Door Test (1) 03.14.2024 |
|
|
-- |
-- |
Plumbing Trim Out (2) 03.16.2024 |
In process 3/13 |
|
-- |
-- |
Install Appliances (0) * 03.16.2024 |
Standard DELIVERY 2/26 |
|
-- |
-- |
Paint 3 (2) * 03.09.2024 |
|
|
-- |
-- |
Carpet (2) 02.28.2024 |
In process 2/24 |
|
-- |
-- |
Appraiser Confirms Construction Completion (0) 04.04.2024 |
|
|
-- |
-- |
Inspection (Final HVAC) (1) 03.23.2024 |
|
|
-- |
-- |
Inspection (Final Plumbing) (1) 03.23.2024 |
|
|
-- |
-- |
Inspection (Final Electric) (1) 03.23.2024 |
|
|
-- |
-- |
Inspection (Final Building) (2) * 03.23.2024 |
3/22 |
|
-- |
-- |
Pre Walk Through (0) 04.04.2024 |
|
|
-- |
-- |
Stain Hardwood Stairs (1) 03.13.2024 |
|
|
-- |
-- |
Cleaning (1) 04.06.2024 |
|
|
-- |
-- |
Certificate of Occupancy (1) * 03.29.2024 |
|
|
-- |
-- |
C.O. to Lender (0) 04.08.2024 |
|
|
-- |
-- |
Schedule Closing (0) 04.11.2024 |
|
|
-- |
-- |
Buyer Walk Through (1) 04.10.2024 |
Monday, April 8 at 1PM |
|
-- |
-- |
Payment for Upgrades (0) 04.04.2024 |
|
|
-- |
-- |
Keys to Settlement Agent (0) 04.04.2024 |
|
|
-- |
-- |
Review Settlement Statement (0) 04.08.2024 |
|
|
-- |
-- |
Jerry Signs Closing Documents (0) 04.10.2024 |
|
|
-- |
-- |
Request Trash Tote From POA Manager (0) 03.28.2024 |
|
|
-- |
-- |
Closing (1) 04.12.2024 |
Brittany @ West View Title - Fri, Apr 12 @ 10AM |
|
-- |
-- |
Remove Coded Lockbox (0) 04.18.2024 |
|
|