1 28 33 37 45 46 47 48 71 52 70 69 67 53 54 55 56 59 58 57 66 65 64 60 61 62 63 ADDR
CONGERS-2 - 43  ::  1442 Appaloosa Court
[ BUILD: 20230926 ]      
CRITICAL PATH   |   INSPECTIONS   |   FLOOR PLANS   |   SELECTIONS   |   SPECS   |   CHANGES   |   NHS
view photo archive
 
--   --   Fix board off master bath
--   --   Trim holes need patched here as well by Davenport
--   --   Is the garage really getting LVT? I think maybe that’s supposed to state something else
--   --   Buyer Financing Issues - No Need To Rush This One!
--   --   Cover carpet ASAP
--   --   No Rush - Not Under Contract
--   --   Appliances in garage here. Maybe fridge can be used for 42.
--   --   Very large paint spill on the back deck
--   --   I would recommend completing paint three and covering floors ASAP and high traffic areas. Cleaning up lots of trash and extra supplies laying around.
--   --   Steps drying 3/9
--   --   Powder light needs set after plumber
--   --   Dented fridge door Leisa has ordered. Entire new refrigerator has been ordered.
--   --   Attic cover needed Painters
--   --   Remove glue in master bathroom shower Drywallers/Jill
--   --   Install attic cover Jill
--   --   CODED LOCKBOX 4343
--   --   Clean few items out of the garage Jill
--   --   Install screens Jill
--   --   View cabinet, touch ups needed Few - Jill
--   --   Side trim needed at island Corner, George - we have the material
--   --   Scratch on island countertop Greg will take a look
--   --   Mud to be removed on carpets Jill/Kristen
--   --   Hammer nails down on eck
--   --   pressure wash front and back Just front
--   --   crack in upper right corner of pantry door
--   --   paint touchup throughout painter
--   --   Secure two snap lights to living room ceiling electrician
--   --   redo trim at both roof posts Davenport
--   --   secure feastener to front downspout Davenport
--   --   Exterior- living room windows- gray vertical trim piece to be secured Davenport
--   --   fix trim around garage door Davenport
--   --   remove temporary piece of wood under deck Tom
--   --   finish insulation in bonus room ( closet adn above door)
-- -- Ratified Contract? (0)  10.04.2023    
-- -- $2500 Deposit Received (0)  04.06.2024     Need new deposit
-- -- Association Packet Requested (0)  10.04.2023    
-- -- Association Packet Received (0)  10.08.2023    
-- -- Selections Meeting (0)  11.02.2023    
-- -- Selections Sheet Signed (0)  11.28.2023     11/6: Sent to Basu for signatures
-- -- Amendment for Upgrades (B,S,L,T,BCP) (0)  11.29.2023     11/27: Sent to Jerry for signatures;
-- -- Deposit For Upgrades Received (0)  11.28.2023    
-- -- Building Permit (30)  08.14.2023    
-- -- Order Roof & Floor Trusses (1)  11.06.2023    
-- -- Order Windows & Doors (0)  11.20.2023    
-- -- Stake Out Home (1)  08.14.2023    
-- -- Excavate (2)  08.14.2023    
-- -- Inspection (Footers) (1)  08.14.2023    
-- -- Inspection (Concrete Wall) (1)  10.05.2023    
-- -- Pour Footers (1)  08.14.2023    
-- -- Set Forms (2)  09.11.2023    
-- -- Pour Foundation Walls (1)  09.11.2023    
-- -- Plumb Slab (2)  10.05.2023    
-- -- Inspection (Plumbing Under Slab) (1)  10.05.2023    
-- -- Inspection (Conduit Under Slab) (1)  10.05.2023    
-- -- Prepare Slab (1)  09.18.2023    
-- -- Inspection (Slab) (1)  10.05.2023    
-- -- Inspection (Drain Tile) (0)  10.05.2023    
-- -- Pour Slab (1)  09.18.2023    
-- -- Settlement Agent Confirmed (0)  12.01.2023     11/29: sent to Brittany
-- -- Framing I (9)  10.26.2023    
-- -- Order Steps (0)  11.20.2023    
-- -- Order Tubs / Showers (0)  11.20.2023    
-- -- Framing II (8)  10.26.2023    
-- -- Framing III (8)  11.25.2023    
-- -- Verify Window & Roof Structure (0)  12.13.2023    
-- -- Install Stairs (0)  11.25.2023    
-- -- Windows & Doors (0)  12.13.2023    
-- -- House Number and Status in Window (0)  12.13.2023    
-- -- Roofing (0)  12.13.2023    
-- -- Order Cabinets (0)  12.19.2023    
-- -- Order Appliances (0)  03.14.2024     Standard
-- -- Deck (0)  01.07.2024    
-- -- Gutters (0)  02.05.2024    
-- -- Driveway (0)  02.21.2024    
-- -- Patio (0)  03.09.2024    
-- -- Privacy Divider / Fence (0)  02.26.2024     Patio privacy panels needed. In process 2/21
-- -- Sod / Seed / Landscaping (0)  03.30.2024    
-- -- HVAC Rough In (4)  12.16.2023     In process 12/9
-- -- Inspection (Rough In HVAC) (1)  12.26.2023     12/27/23
-- -- Rough In Microwave Vent (0)  12.16.2023    
-- -- Plumbing Rough In (4)  12.13.2023     In process 12/9
-- -- Inspection (Rough In Plumbing) (1)  12.26.2023    
-- -- Electric Rough In (4)  01.03.2024     In process 12/20
-- -- Inspection (Rough In Electric) (1)  01.03.2024     12/27/23
-- -- Inspection (Deck Piers) (0)  02.19.2024    
-- -- Inspection (Framing) (1)  01.03.2024     12/27/23
-- -- Exterior Vinyl (0)  01.27.2024     In process 1/19
-- -- Exterior Stone (0)  01.27.2024    
-- -- Insulation (2)  01.03.2024    
-- -- Inspection (Insulation) (1)  01.06.2024    
-- -- Inspection (Electric Service) (0)  02.08.2024    
-- -- Set Electric Meter (0)  03.06.2024    
-- -- Inspection (Main Sewer Line) (0)  02.05.2024    
-- -- Inspection (Main Water Line) (0)  02.05.2024    
-- -- Order Interior Doors & Trim (0)  02.05.2024    
-- -- Drywall (Hang) (4)  01.10.2024     In process 1/10
-- -- Loan Approval (0)  04.04.2024     Cash
-- -- Deed Preparation (0)  04.04.2024    
-- -- Drywall (Tape, Block, Skim, Sand) (6)  01.25.2024     In process 1/17
-- -- Paint 1 (1)  01.27.2024    
-- -- Garage Door (0)  02.07.2024    
-- -- House Numbers (0)  03.09.2024    
-- -- Mailbox (0)  03.28.2024    
-- -- Cabinet Installation (2)  01.27.2024    
-- -- Granite Installation (1)  02.10.2024    
-- -- Interior Trim - Install (3)  02.10.2024     In process 2/7
-- -- Order Plumbing / Lighting Fixtures (0)  02.08.2024    
-- -- Interior Trim - Paint (1)  02.14.2024    
-- -- Luxury Vinyl Plank (3)  02.24.2024     In process 2/21
-- -- Luxury Vinyl Tile (0)  02.24.2024    
-- -- Paint 2 (3)  01.31.2024    
-- -- Cover Floors (1)  03.09.2024    
-- -- Deliver Plumbing / Lighting Fixtures (0)  02.15.2024    
-- -- Shoe Moulding (0)  02.28.2024    
-- -- Shelving, Door Knobs, Fire Extinguisher (0)  04.03.2024     next week 3/18
-- -- Install Coded Lockbox (add extra keys) (0)  04.06.2024    
-- -- Pay Water / Sewer Taps (0)  02.19.2024    
-- -- Set Water Meter (0)  02.26.2024    
-- -- Electric Trim Out (3)  03.13.2024     In process 3/9
-- -- Ceiling Fans (0)  03.09.2024    
-- -- HVAC Trim Out (1)  03.09.2024    
-- -- Blower Door Test (1)  03.14.2024    
-- -- Plumbing Trim Out (2)  03.16.2024     In process 3/13
-- -- Install Appliances (0)  03.16.2024     Standard DELIVERY 2/26
-- -- Paint 3 (2)  03.09.2024    
-- -- Carpet (2)  02.28.2024     In process 2/24
-- -- Appraiser Confirms Construction Completion (0)  04.04.2024    
-- -- Inspection (Final HVAC) (1)  03.23.2024    
-- -- Inspection (Final Plumbing) (1)  03.23.2024    
-- -- Inspection (Final Electric) (1)  03.23.2024    
-- -- Inspection (Final Building) (2)  03.23.2024     3/22
-- -- Pre Walk Through (0)  04.04.2024    
-- -- Stain Hardwood Stairs (1)  03.13.2024    
-- -- Cleaning (1)  04.06.2024    
-- -- Certificate of Occupancy (1)  03.29.2024    
-- -- C.O. to Lender (0)  04.08.2024    
-- -- Schedule Closing (0)  04.11.2024    
-- -- Buyer Walk Through (1)  04.10.2024     Monday, April 8 at 1PM
-- -- Payment for Upgrades (0)  04.04.2024    
-- -- Keys to Settlement Agent (0)  04.04.2024    
-- -- Review Settlement Statement (0)  04.08.2024    
-- -- Jerry Signs Closing Documents (0)  04.10.2024    
-- -- Request Trash Tote From POA Manager (0)  03.28.2024    
-- -- Closing (1)  04.12.2024     Brittany @ West View Title - Fri, Apr 12 @ 10AM
-- -- Remove Coded Lockbox (0)  04.18.2024