CONGERS-2 - 44  ::  1438 Appaloosa Court
[ BUILD: 20230925 ]      
CRITICAL PATH   |   INSPECTIONS   |   FLOOR PLANS   |   SELECTIONS   |   SPECS   |   CHANGES   |   NHS
view photo archive
 
--   --   Finish drywall in garage Appears to just need to be painted
--   --   Loose trim around garage Davenport
--   --   Cover all the floors
--   --   USDA loan - delayed closing
--   --   Powder bath needs light 3/9 Electrician
--   --   More stone is going to be needed in front of townhouse Stone guys
--   --   Hall light switch cover needed in bath
--   --   Dent in refrigerator door
--   --   CODED LOCKBOX 4444
--   --   Reattach gutter hardware Davenport
--   --   Install shower bar in master bath Paul
--   --   Attic, cover needed Painters
--   --   Lots and lots of glue in hall bathtub Drywallers
--   --   Mud on bonus room carpet needs removed Jill
--   --   Few spots of glue on master bathroom floor Jill
--   --   Sweet out garage Jill
--   --   Glue on bonus room bathtub Jill
--   --   Townhouse needs touch up cleaning after paint touch up Lynn
--   --   A small bit of glue on hall bath Jill
--   --   Few spots of mud on upstairs carpet Jill
--   --   Need air filter
--   --   Remove cover from smoke detectoor
--   --   Remove cover from smoke detector Jill
--   --   Mark property line out back Tom
--   --   Pressure wash
--   --   Scrape garage floor
--   --   Siding is falling down in front of townhouse Davenport
--   --  
-- -- Ratified Contract? (0)  09.04.2023    
-- -- $2500 Deposit Received (0)  09.07.2023    
-- -- Association Packet Requested (0)  09.04.2023    
-- -- Association Packet Received (0)  09.07.2023    
-- -- Selections Meeting (0)  09.14.2023     Tuesday 9/12 at 1:00 PM
-- -- Selections Sheet Signed (0)  09.24.2023     9/21: Sent to Tekle
-- -- Amendment for Upgrades (B,S,L,T,BCP) (0)  09.27.2023     9/25: Sent to Jerry for signature
-- -- Deposit For Upgrades Received (0)  09.26.2023    
-- -- Building Permit (30)  09.11.2023    
-- -- Order Roof & Floor Trusses (1)  11.06.2023    
-- -- Order Windows & Doors (0)  11.20.2023    
-- -- Stake Out Home (1)  08.14.2023    
-- -- Excavate (2)  08.14.2023    
-- -- Inspection (Footers) (1)  08.14.2023    
-- -- Inspection (Concrete Wall) (1)  11.27.2023    
-- -- Pour Footers (1)  08.14.2023    
-- -- Set Forms (2)  09.11.2023    
-- -- Pour Foundation Walls (1)  09.11.2023    
-- -- Plumb Slab (2)  10.05.2023    
-- -- Inspection (Plumbing Under Slab) (1)  10.05.2023    
-- -- Inspection (Conduit Under Slab) (1)  10.05.2023    
-- -- Prepare Slab (1)  10.05.2023    
-- -- Inspection (Slab) (1)  10.05.2023    
-- -- Inspection (Drain Tile) (0)  10.05.2023    
-- -- Pour Slab (1) *   10.19.2023    
-- -- Settlement Agent Confirmed (0)  09.30.2023    
-- -- Framing I (9)  10.26.2023    
-- -- Order Steps (0)  11.20.2023    
-- -- Order Tubs / Showers (0)  11.20.2023    
-- -- Framing II (8)  10.26.2023    
-- -- Framing III (8) *   11.25.2023    
-- -- Verify Window & Roof Structure (0)  12.13.2023    
-- -- Install Stairs (0)  11.25.2023    
-- -- Windows & Doors (0)  12.13.2023    
-- -- House Number and Status in Window (0)  12.09.2023    
-- -- Roofing (0)  12.13.2023    
-- -- Order Cabinets (0)  12.19.2023    
-- -- Order Appliances (0)  03.06.2024     Standard
-- -- Deck (0)  01.07.2024    
-- -- Gutters (0)  02.05.2024    
-- -- Driveway (0)  02.21.2024    
-- -- Patio (0)  03.06.2024    
-- -- Privacy Divider / Fence (0)  02.26.2024    
-- -- Sod / Seed / Landscaping (0)  03.30.2024    
-- -- HVAC Rough In (4)  12.20.2023     In process 12/16
-- -- Inspection (Rough In HVAC) (1)  12.26.2023    
-- -- Rough In Microwave Vent (0)  12.20.2023    
-- -- Plumbing Rough In (4)  12.13.2023     In process 12/9
-- -- Inspection (Rough In Plumbing) (1)  12.26.2023    
-- -- Electric Rough In (4)  01.03.2024    
-- -- Inspection (Rough In Electric) (1)  01.03.2024    
-- -- Inspection (Deck Piers) (0)  02.19.2024    
-- -- Inspection (Framing) (1)  01.03.2024    
-- -- Exterior Vinyl (0) *   01.27.2024     In process 1/19
-- -- Exterior Stone (0)  03.02.2024    
-- -- Insulation (2)  01.03.2024    
-- -- Inspection (Insulation) (1)  01.06.2024    
-- -- Inspection (Electric Service) (0)  02.08.2024    
-- -- Set Electric Meter (0)  03.06.2024    
-- -- Inspection (Main Sewer Line) (0)  02.05.2024    
-- -- Inspection (Main Water Line) (0)  02.05.2024    
-- -- Order Interior Doors & Trim (0)  02.05.2024    
-- -- Drywall (Hang) (4) *   01.10.2024     In process 1/6
-- -- Loan Approval (0)  04.11.2024     USDA
-- -- Deed Preparation (0)  03.07.2024    
-- -- Drywall (Tape, Block, Skim, Sand) (6) *   01.25.2024     In process 1/17
-- -- Paint 1 (1)  01.27.2024    
-- -- Garage Door (0)  02.07.2024    
-- -- House Numbers (0)  03.09.2024    
-- -- Mailbox (0)  03.28.2024    
-- -- Cabinet Installation (2) *   01.27.2024    
-- -- Granite Installation (1) *   02.10.2024    
-- -- Interior Trim - Install (3)  02.10.2024     In process 2/7
-- -- Order Plumbing / Lighting Fixtures (0)  02.08.2024    
-- -- Interior Trim - Paint (1)  02.14.2024    
-- -- Luxury Vinyl Plank (3) *   02.28.2024    
-- -- Luxury Vinyl Tile (0)  03.02.2024    
-- -- Paint 2 (3)  02.28.2024    
-- -- Cover Floors (1)  03.06.2024    
-- -- Deliver Plumbing / Lighting Fixtures (0)  02.15.2024    
-- -- Shoe Moulding (0)  03.06.2024    
-- -- Shelving, Door Knobs, Fire Extinguisher (0)  04.01.2024     shelving week of 3/18. In process 3/13
-- -- Install Coded Lockbox (add extra keys) (0)  03.20.2024    
-- -- Pay Water / Sewer Taps (0)  02.19.2024    
-- -- Set Water Meter (0)  02.26.2024    
-- -- Electric Trim Out (3)  03.09.2024     In process 3/6
-- -- Ceiling Fans (0)  03.06.2024    
-- -- HVAC Trim Out (1)  03.06.2024     Thermostat being installed 2/28
-- -- Blower Door Test (1)  03.14.2024    
-- -- Plumbing Trim Out (2)  03.16.2024    
-- -- Install Appliances (0) *   03.16.2024     DELIVERY 2/26 STANDARD
-- -- Paint 3 (2) *   03.13.2024    
-- -- Carpet (2)  03.02.2024    
-- -- Appraiser Confirms Construction Completion (0)  04.11.2024    
-- -- Inspection (Final HVAC) (1)  03.23.2024    
-- -- Inspection (Final Plumbing) (1)  03.23.2024    
-- -- Inspection (Final Electric) (1)  03.23.2024    
-- -- Inspection (Final Building) (2) *   03.23.2024    
-- -- Pre Walk Through (0)  04.04.2024    
-- -- Stain Hardwood Stairs (1)  03.28.2024    
-- -- Cleaning (1)  04.03.2024     Started 3/30
-- -- Certificate of Occupancy (1) *   03.29.2024    
-- -- C.O. to Lender (0)  03.29.2024    
-- -- Schedule Closing (0)  04.11.2024    
-- -- Buyer Walk Through (1)  04.08.2024    
-- -- Payment for Upgrades (0)  03.29.2024    
-- -- Keys to Settlement Agent (0)  03.22.2024    
-- -- Review Settlement Statement (0)  04.11.2024    
-- -- Jerry Signs Closing Documents (0)  04.18.2024    
-- -- Request Trash Tote From POA Manager (0)  03.28.2024    
-- -- Closing (1)  04.20.2024     Brittany @ West View Title
-- -- Remove Coded Lockbox (0)  04.22.2024