CONGERS-2 - 75  ::  1441 Appaloosa Court
[ BUILD: 20230930 ]      
CRITICAL PATH   |   INSPECTIONS   |   FLOOR PLANS   |   SELECTIONS   |   SPECS   |   CHANGES   |   NHS
view photo archive
 
TO DO
---
UPGRADES
---
CRITICAL PATH
---
TO DO - COMPLETED OR DELETED
Broken bonus room window Sash on order
Patch holes in concrete in utility space? Tom
Preparing to paint trim 3/6
Why was trim removed in bedroom?
Cover carpet
Are they putting rock in between the driveways?
I think sinks got delivered to the wrong house They are sitting and 75 but likely need to be installed and 74
Put trim back in smaller bedrooms George
I don’t see the ceiling fan on site for living room Jill will check it out
Drywall repair needed and kitchen ceiling In process 4/17
Drywall repair, carpet repair from water leak in master In process 4/10
Home inspection - Monday
Home Inspection Monday, April 15 at 5PM
recaulk basement patio door/boards that are missing in spots
make sure drywall is secure on wall in basement utility space Drywaller
structural bolts need to be extended longer/add washers Jeremiah
add additional deck support brackets Should be every 4 feet
fasteners are too close to the edge of the decking. Remove nails and installing fasteners properly. Jeremiah
consider adding brackets or joist hangers on outer band connections to deck Jeremiah
caulking where wood is exposed at front porch awning supports Davenport
install white board below back door
deck railing and post were not secured properly to tie the outside corner frame together. make sure post cannot seperate. Add 2 bolts. Tighten privacy panel that’s wobbly.
kitchen window is slightly un-level Davenport - siding
secure garage door electrical wires to wall inside of garage Tom
install splashblocks correctly Tom
repaint attic cover Painter
caulk around meter base to create water barrier Painter
ensure HVAC outdoor condensing unit is level on the pad. Inspector says its not level or in the center. Tom will level
touch up paint Painter
fix window in front living room. Retention clip pops out when upper sash is operated.
Top door hinge on door leading to bonus room is loose. Tighten screws. Jill
Door to hallway bathroom is not level. Adjust the door so it will stay open. Jill
Install handrail on top few steps leading to upper level of home Not code
complete drywall repairs in kitchen Drywaller, Painter. Needs painting 4/19
Damage to front door trim Painter
Crack in tub Valley Tub Repair
Squeaky floor at top of stairs Eagle was looking at 4/17
Attic cover needed Painter
Patch nail holes top left window trim Davenport
Add one more plant in front landscaping Pettit
Titan to electrical outlets that are loose at wall in the hallway and smaller bedroom jill
Install door, knobs, shelving, and mirrors Thu, Apr 25
Adjust kitchen window to the deck. It’s an eighth of an inch out of plum. Davenport needs to take a look 4/22
Paint touchup throughout Painter
Vinyl box at hot water and laundry. One corner needs to be secured.
Replace the Wright sink vanity faucet in the master bathroom Mazur
Clean paint, overspray off all hinges Painter
Power wash the front and the back of the home
Plant front bush beside garage
Crack in the hall bathtub
CODED LOCKBOX 7575
Missing plant by front door Pettit
Pressure wash rear of home Jill
UPGRADES - COMPLETED
    Expanded Deck 12 x 18  
    Ceiling Fan in Living Room  
    Amendment to increase price by $3,160  
CRITICAL PATH - COMPLETED
-- -- Ratified Contract? (0)  10.01.2023    
-- -- $2500 Deposit Received (0)  10.06.2023    
-- -- Association Packet Requested (0)  10.01.2023    
-- -- Association Packet Received (0)  10.08.2023    
-- -- Selections Meeting (0)  10.12.2023    
-- -- Selections Sheet Signed (0)  10.14.2023     10/13: Sent to Courtney
-- -- Amendment for Upgrades (B,S,L,T,BCP) (0)  10.19.2023     10/18: sent to Jerry
-- -- Deposit For Upgrades Received (0)  10.18.2023    
-- -- Building Permit (30) *   09.11.2023    
-- -- Order Roof & Floor Trusses (1)  11.20.2023    
-- -- Order Windows & Doors (0)  11.20.2023    
-- -- Stake Out Home (1)  09.11.2023    
-- -- Excavate (2)  09.11.2023    
-- -- Inspection (Footers) (1)  10.05.2023    
-- -- Inspection (Concrete Wall) (1)  10.05.2023    
-- -- Pour Footers (1) *   09.11.2023    
-- -- Set Forms (2)  09.11.2023    
-- -- Pour Foundation Walls (1)  09.11.2023    
-- -- Plumb Slab (2)  10.05.2023    
-- -- Inspection (Plumbing Under Slab) (1)  10.16.2023    
-- -- Inspection (Conduit Under Slab) (1)  10.16.2023    
-- -- Prepare Slab (1)  10.16.2023    
-- -- Inspection (Slab) (1)  10.16.2023    
-- -- Inspection (Drain Tile) (0)  02.19.2024    
-- -- Pour Slab (1) *   10.16.2023    
-- -- Settlement Agent Confirmed (0)  10.26.2023    
-- -- Framing I (9)  11.27.2023    
-- -- Order Steps (0)  11.27.2023    
-- -- Order Tubs / Showers (0)  11.27.2023    
-- -- Framing II (8)  11.27.2023    
-- -- Framing III (8) *   11.27.2023    
-- -- Verify Window & Roof Structure (0)  01.04.2024    
-- -- Install Stairs (0) *   01.04.2024    
-- -- Windows & Doors (0) *   01.04.2024    
-- -- House Number and Status in Window (0)  01.31.2024    
-- -- Roofing (0) *   01.04.2024    
-- -- Order Cabinets (0)  01.16.2024    
-- -- Order Appliances (0)  03.11.2024     Standard
-- -- Deck (0)  01.04.2024    
-- -- Gutters (0)  03.09.2024    
-- -- Driveway (0) *   04.06.2024    
-- -- Patio (0)  04.01.2024    
-- -- Privacy Divider / Fence (0) *   04.10.2024    
-- -- Sod / Seed / Landscaping (0)  04.19.2024    
-- -- HVAC Rough In (4)  01.10.2024     In process 1/6
-- -- Rough In Microwave Vent (0)  01.10.2024    
-- -- Plumbing Rough In (4)  01.13.2024     In process 1/10
-- -- Electric Rough In (4)  01.27.2024     In process 1/25
-- -- Inspection (Rough In HVAC) (1)  01.25.2024    
-- -- Inspection (Rough In Plumbing) (1)  01.25.2024    
-- -- Inspection (Rough In Electric) (1)  01.31.2024    
-- -- Inspection (Framing) (1) *   01.31.2024    
-- -- Inspection (Deck Piers) (0)  03.28.2024    
-- -- Exterior Vinyl (0) *   03.07.2024    
-- -- Exterior Stone (0)  03.28.2024    
-- -- Insulation (2) *   01.31.2024    
-- -- Inspection (Insulation) (1)  02.03.2024    
-- -- Inspection (Electric Service) (0)  03.07.2024    
-- -- Set Electric Meter (0) *   03.29.2024    
-- -- Inspection (Main Sewer Line) (0)  02.15.2024    
-- -- Inspection (Main Water Line) (0)  02.15.2024    
-- -- Order Interior Doors & Trim (0)  03.11.2024    
-- -- Drywall (Hang) (4) *   02.03.2024    
-- -- Loan Approval (0)  10.13.2023     JoDee (90% LTV)
-- -- Deed Preparation (0)  03.28.2024    
-- -- Drywall (Tape, Block, Skim, Sand) (6) *   02.17.2024     In process 2/14
-- -- Paint 1 (1)  02.28.2024    
-- -- Garage Door (0)  03.30.2024    
-- -- House Numbers (0)  04.06.2024    
-- -- Mailbox (0)  03.28.2024    
-- -- Cabinet Installation (2) *   02.28.2024     On site 2/17
-- -- Granite Installation (1) *   02.28.2024    
-- -- Interior Trim - Install (3) *   03.02.2024     In process 2/28
-- -- Order Plumbing / Lighting Fixtures (0)  03.11.2024    
-- -- Interior Trim - Paint (1)  03.09.2024    
-- -- Luxury Vinyl Plank (3) *   03.20.2024    
-- -- Luxury Vinyl Tile (0)  03.20.2024    
-- -- Paint 2 (3)  03.13.2024    
-- -- Cover Floors (0)  03.25.2024    
-- -- Deliver Plumbing / Lighting Fixtures (0)  03.14.2024    
-- -- Shoe Moulding (0)  04.06.2024    
-- -- Shelving, Door Knobs, Fire Extinguisher (1) *   04.24.2024    
-- -- Install Coded Lockbox (add extra keys) (0)  04.18.2024    
-- -- Pay Water / Sewer Taps (0)  03.28.2024    
-- -- Set Water Meter (1) *   03.28.2024    
-- -- Electric Trim Out (3) *   04.03.2024     In process 3/30
-- -- Ceiling Fans (0)  03.30.2024    
-- -- HVAC Trim Out (1) *   03.30.2024    
-- -- Blower Door Test (1)  04.08.2024    
-- -- Plumbing Trim Out (2) *   04.03.2024     In process 3/30
-- -- Install Appliances (0) *   04.03.2024     Standard DELIVERY 3/18
-- -- Paint 3 (2) *   04.03.2024    
-- -- Carpet (2)  03.20.2024    
-- -- Appraiser Confirms Construction Completion (0)  04.22.2024     Johnny Hensley - Apr 15
-- -- Inspection (Final HVAC) (0)  04.11.2024    
-- -- Inspection (Final Plumbing) (0)  04.11.2024    
-- -- Inspection (Final Electric) (0)  04.11.2024    
-- -- Inspection (Final Building) (4) *   04.12.2024    
-- -- Pre Walk Through (0)  04.18.2024    
-- -- Stain Hardwood Stairs (1) *   04.14.2024     In process 4/12
-- -- Cleaning (1)  04.19.2024    
-- -- Certificate of Occupancy (1) *   04.19.2024    
-- -- C.O. to Lender (0)  04.19.2024    
-- -- Schedule Closing (0)  04.16.2024     Friday, April 19th
-- -- Buyer Walk Through (1) *   04.19.2024     Thursday, April 18th at 6:45pm
-- -- Payment for Upgrades (0)  04.16.2024    
-- -- Keys to Settlement Agent (0)  04.15.2024    
-- -- Review Settlement Statement (0)  04.16.2024    
-- -- Jerry Signs Closing Documents (0)  03.22.2024    
-- -- Request Trash Tote From POA Manager (0)  04.15.2024    
-- -- Closing (1)  04.22.2024     Brittany @ West View Title, Friday, April 19th
-- -- Remove Coded Lockbox (0)  05.02.2024