37 ADDR
CONGERS-2 - 77  ::  1449 Appaloosa Court
[ BUILD: 20230932 ]      
CRITICAL PATH   |   INSPECTIONS   |   FLOOR PLANS   |   SELECTIONS   |   SPECS   |   CHANGES   |   NHS
view photo archive
 
TO DO
Buyer Contact- 540-607-5199
UPGRADES
---
CRITICAL PATH
---
TO DO - COMPLETED OR DELETED
Side, splashes of granite needed here Just one needs to be replaced
Cover carpet
Trim, missing on stairs, leading to main level Two spots
Lots of beeping smoke detectors Electrician
CODED LOCKBOX 7777
Needs all door knobs
Patch screw holes in powder bath light fixture Painter
Few larger paint touch up spots needed before final walk-through? Painter
Paint attic cover Painter
Master bedroom could use another coat of paint. Where they cut in and where they rolled it’s pretty obvious. Painter
Install screens
Install sliding screen doors
Return $676.25 to Buyer 4/12: waiting on check from Tina
Paint touchup throughout Painter
Adhere show mold, and trim piece in kitchen
Sweep out garage
Fix gash in door to deck near the lock Painter
Put splash block in place and add dirt behind heat pump Tom
Paint, touchup throughout
Hide the very large wire, that sticking out of the side of the townhouse Tom
UPGRADES - COMPLETED
    Microwave vented to Exterior  
    Garage Keypad  
    Digital Deadbolt  
    Expanded Driveway  
    Gardenia LVT  
    Amendment to increase price by $2,705  
CRITICAL PATH - COMPLETED
-- -- Ratified Contract? (0)  10.04.2023    
-- -- $2500 Deposit Received (0)  10.12.2023    
-- -- Association Packet Requested (0)  10.04.2023    
-- -- Association Packet Received (0)  10.08.2023    
-- -- Selections Meeting (0)  11.02.2023    
-- -- Selections Sheet Signed (0)  11.28.2023     11/2: Sent to Basu for signatures
-- -- Amendment for Upgrades (B,S,L,T,BCP) (0)  11.29.2023     11/27: Sent to Jerry for signatures;
-- -- Deposit For Upgrades Received (0)  11.28.2023    
-- -- Building Permit (30) *   09.11.2023    
-- -- Order Roof & Floor Trusses (1)  11.20.2023    
-- -- Order Windows & Doors (0)  11.20.2023    
-- -- Stake Out Home (1)  09.11.2023    
-- -- Excavate (2)  09.11.2023    
-- -- Inspection (Footers) (1)  10.05.2023    
-- -- Inspection (Concrete Wall) (1)  10.05.2023    
-- -- Pour Footers (1) *   09.11.2023    
-- -- Set Forms (2)  09.11.2023    
-- -- Pour Foundation Walls (1)  09.11.2023    
-- -- Plumb Slab (2)  10.05.2023    
-- -- Inspection (Plumbing Under Slab) (1)  10.16.2023    
-- -- Inspection (Conduit Under Slab) (1)  10.16.2023    
-- -- Prepare Slab (1)  10.16.2023    
-- -- Inspection (Slab) (1)  10.16.2023    
-- -- Inspection (Drain Tile) (0)  02.19.2024    
-- -- Pour Slab (1) *   10.16.2023    
-- -- Settlement Agent Confirmed (0)  12.02.2023     11/29: sent to Brittany
-- -- Framing I (9)  11.27.2023    
-- -- Order Steps (0)  11.27.2023    
-- -- Order Tubs / Showers (0)  11.27.2023    
-- -- Framing II (8)  11.27.2023    
-- -- Framing III (8) *   11.27.2023    
-- -- Verify Window & Roof Structure (0)  12.20.2023    
-- -- Install Stairs (0) *   12.20.2023    
-- -- Windows & Doors (0) *   12.20.2023    
-- -- House Number and Status in Window (0)  01.31.2024    
-- -- Roofing (0) *   12.20.2023    
-- -- Order Cabinets (0)  01.16.2024    
-- -- Order Appliances (0)  03.11.2024     delivering 3/18
-- -- Deck (0)  12.20.2023    
-- -- Gutters (0)  03.09.2024    
-- -- Driveway (0) *   03.28.2024    
-- -- Patio (0)  02.07.2024    
-- -- Privacy Divider / Fence (0) *   04.10.2024    
-- -- Sod / Seed / Landscaping (0)  04.19.2024    
-- -- HVAC Rough In (4)  01.03.2024     In process 1/3
-- -- Rough In Microwave Vent (0)  01.03.2024    
-- -- Plumbing Rough In (4)  01.13.2024     In process 1/10
-- -- Electric Rough In (4)  01.19.2024    
-- -- Inspection (Rough In HVAC) (1)  01.25.2024    
-- -- Inspection (Rough In Plumbing) (1)  01.25.2024    
-- -- Inspection (Rough In Electric) (1)  01.25.2024    
-- -- Inspection (Framing) (1) *   01.25.2024    
-- -- Inspection (Deck Piers) (0)  01.25.2024    
-- -- Exterior Vinyl (0) *   03.07.2024     In process 2/21
-- -- Exterior Stone (0)  03.11.2024     in process 3/11
-- -- Insulation (2) *   01.27.2024    
-- -- Inspection (Insulation) (1)  01.31.2024    
-- -- Inspection (Electric Service) (0)  03.07.2024    
-- -- Set Electric Meter (0) *   03.29.2024    
-- -- Inspection (Main Sewer Line) (0)  02.15.2024    
-- -- Inspection (Main Water Line) (0)  02.15.2024    
-- -- Order Interior Doors & Trim (0)  02.28.2024    
-- -- Drywall (Hang) (4) *   02.03.2024     In process 1/31
-- -- Loan Approval (0)  04.11.2024     EMET Mortgage (80% LTV)
-- -- Deed Preparation (0)  03.25.2024    
-- -- Drywall (Tape, Block, Skim, Sand) (6) *   02.10.2024     In process 2/7
-- -- Paint 1 (1)  02.14.2024    
-- -- Garage Door (0)  03.11.2024     Davenport
-- -- House Numbers (0)  04.06.2024    
-- -- Mailbox (0)  03.28.2024    
-- -- Cabinet Installation (2) *   02.21.2024     On site 2/17
-- -- Granite Installation (1) *   02.28.2024    
-- -- Interior Trim - Install (3) *   02.21.2024     In process 2/17
-- -- Order Plumbing / Lighting Fixtures (0)  03.14.2024     Delivering this week 3/11
-- -- Interior Trim - Paint (1)  02.24.2024    
-- -- Luxury Vinyl Plank (3) *   03.06.2024     In process 3/2
-- -- Luxury Vinyl Tile (0)  03.06.2024     In process 3/2
-- -- Paint 2 (3)  03.06.2024    
-- -- Cover Floors (0)  03.11.2024    
-- -- Deliver Plumbing / Lighting Fixtures (0)  03.14.2024    
-- -- Shoe Moulding (0)  03.09.2024     In process 3/6
-- -- Shelving, Door Knobs, Fire Extinguisher (1) *   04.10.2024     In process 4/3
-- -- Install Coded Lockbox (add extra keys) (0)  04.10.2024    
-- -- Pay Water / Sewer Taps (0)  03.28.2024    
-- -- Set Water Meter (1) *   03.28.2024    
-- -- Electric Trim Out (3) *   03.28.2024    
-- -- Ceiling Fans (0)  04.03.2024    
-- -- HVAC Trim Out (1) *   03.23.2024     Heat pump is set
-- -- Blower Door Test (1)  04.06.2024    
-- -- Plumbing Trim Out (2) *   03.30.2024    
-- -- Install Appliances (0) *   04.04.2024     In process 4/3
-- -- Paint 3 (2) *   03.30.2024     In process 3/16
-- -- Carpet (2)  03.06.2024    
-- -- Appraiser Confirms Construction Completion (0)  04.18.2024    
-- -- Inspection (Final HVAC) (0)  04.06.2024     Fri, April 5
-- -- Inspection (Final Plumbing) (0)  04.06.2024    
-- -- Inspection (Final Electric) (0)  04.06.2024    
-- -- Inspection (Final Building) (4) *   04.06.2024    
-- -- Pre Walk Through (0)  04.11.2024    
-- -- Stain Hardwood Stairs (1) *   04.03.2024    
-- -- Cleaning (1)  04.17.2024    
-- -- Certificate of Occupancy (1) *   04.11.2024    
-- -- C.O. to Lender (0)  04.11.2024    
-- -- Schedule Closing (0)  04.20.2024    
-- -- Buyer Walk Through (1) *   04.16.2024     Tuesday, April 16 at 1PM
-- -- Payment for Upgrades (0)  04.11.2024    
-- -- Keys to Settlement Agent (0)  04.15.2024    
-- -- Review Settlement Statement (0)  04.17.2024    
-- -- Jerry Signs Closing Documents (0)  03.22.2024    
-- -- Request Trash Tote From POA Manager (0)  04.15.2024    
-- -- Closing (1)  04.20.2024     Brittany @ West View Title
-- -- Remove Coded Lockbox (0)  05.01.2024