| -- | -- | Buyer Contact- 540-607-5199 | ||
| -- | -- | Side, splashes of granite needed here | Just one needs to be replaced | |
| -- | -- | Cover carpet | ||
| -- | -- | Trim, missing on stairs, leading to main level | Two spots | |
| -- | -- | Lots of beeping smoke detectors | Electrician | |
| -- | -- | CODED LOCKBOX 7777 | ||
| -- | -- | Needs all door knobs | ||
| -- | -- | Patch screw holes in powder bath light fixture | Painter | |
| -- | -- | Few larger paint touch up spots needed before final walk-through? | Painter | |
| -- | -- | Paint attic cover | Painter | |
| -- | -- | Master bedroom could use another coat of paint. Where they cut in and where they rolled it’s pretty obvious. | Painter | |
| -- | -- | Install screens | ||
| -- | -- | Install sliding screen doors | ||
| -- | -- | Return $676.25 to Buyer | 4/12: waiting on check from Tina | |
| -- | -- | Paint touchup throughout | Painter | |
| -- | -- | Adhere show mold, and trim piece in kitchen | ||
| -- | -- | Sweep out garage | ||
| -- | -- | Fix gash in door to deck near the lock | Painter | |
| -- | -- | Put splash block in place and add dirt behind heat pump | Tom | |
| -- | -- | Paint, touchup throughout | ||
| -- | -- | Hide the very large wire, that sticking out of the side of the townhouse | Tom | |
| -- | -- | Ratified Contract? (0) 10.04.2023 | ||
| Microwave vented to Exterior | ||||
| Garage Keypad | ||||
| Digital Deadbolt | ||||
| Expanded Driveway | ||||
| Gardenia LVT | ||||
| Amendment to increase price by $2,705 | ||||
| -- | -- | $2500 Deposit Received (0) 10.12.2023 | ||
| -- | -- | Association Packet Requested (0) 10.04.2023 | ||
| -- | -- | Association Packet Received (0) 10.08.2023 | ||
| -- | -- | Selections Meeting (0) 11.02.2023 | ||
| -- | -- | Selections Sheet Signed (0) 11.28.2023 | 11/2: Sent to Basu for signatures | |
| -- | -- | Amendment for Upgrades (B,S,L,T,BCP) (0) 11.29.2023 | 11/27: Sent to Jerry for signatures; | |
| -- | -- | Deposit For Upgrades Received (0) 11.28.2023 | ||
| -- | -- | Building Permit (30) * 09.11.2023 | ||
| -- | -- | Order Roof & Floor Trusses (1) 11.20.2023 | ||
| -- | -- | Order Windows & Doors (0) 11.20.2023 | ||
| -- | -- | Stake Out Home (1) 09.11.2023 | ||
| -- | -- | Excavate (2) 09.11.2023 | ||
| -- | -- | Inspection (Footers) (1) 10.05.2023 | ||
| -- | -- | Inspection (Concrete Wall) (1) 10.05.2023 | ||
| -- | -- | Pour Footers (1) * 09.11.2023 | ||
| -- | -- | Set Forms (2) 09.11.2023 | ||
| -- | -- | Pour Foundation Walls (1) 09.11.2023 | ||
| -- | -- | Plumb Slab (2) 10.05.2023 | ||
| -- | -- | Inspection (Plumbing Under Slab) (1) 10.16.2023 | ||
| -- | -- | Inspection (Conduit Under Slab) (1) 10.16.2023 | ||
| -- | -- | Prepare Slab (1) 10.16.2023 | ||
| -- | -- | Inspection (Slab) (1) 10.16.2023 | ||
| -- | -- | Inspection (Drain Tile) (0) 02.19.2024 | ||
| -- | -- | Pour Slab (1) * 10.16.2023 | ||
| -- | -- | Settlement Agent Confirmed (0) 12.02.2023 | 11/29: sent to Brittany | |
| -- | -- | Framing I (9) 11.27.2023 | ||
| -- | -- | Order Steps (0) 11.27.2023 | ||
| -- | -- | Order Tubs / Showers (0) 11.27.2023 | ||
| -- | -- | Framing II (8) 11.27.2023 | ||
| -- | -- | Framing III (8) * 11.27.2023 | ||
| -- | -- | Verify Window & Roof Structure (0) 12.20.2023 | ||
| -- | -- | Install Stairs (0) * 12.20.2023 | ||
| -- | -- | Windows & Doors (0) * 12.20.2023 | ||
| -- | -- | House Number and Status in Window (0) 01.31.2024 | ||
| -- | -- | Roofing (0) * 12.20.2023 | ||
| -- | -- | Order Cabinets (0) 01.16.2024 | ||
| -- | -- | Order Appliances (0) 03.11.2024 | delivering 3/18 | |
| -- | -- | Deck (0) 12.20.2023 | ||
| -- | -- | Gutters (0) 03.09.2024 | ||
| -- | -- | Driveway (0) * 03.28.2024 | ||
| -- | -- | Patio (0) 02.07.2024 | ||
| -- | -- | Privacy Divider / Fence (0) * 04.10.2024 | ||
| -- | -- | Sod / Seed / Landscaping (0) 04.19.2024 | ||
| -- | -- | HVAC Rough In (4) 01.03.2024 | In process 1/3 | |
| -- | -- | Rough In Microwave Vent (0) 01.03.2024 | ||
| -- | -- | Plumbing Rough In (4) 01.13.2024 | In process 1/10 | |
| -- | -- | Electric Rough In (4) 01.19.2024 | ||
| -- | -- | Inspection (Rough In HVAC) (1) 01.25.2024 | ||
| -- | -- | Inspection (Rough In Plumbing) (1) 01.25.2024 | ||
| -- | -- | Inspection (Rough In Electric) (1) 01.25.2024 | ||
| -- | -- | Inspection (Framing) (1) * 01.25.2024 | ||
| -- | -- | Inspection (Deck Piers) (0) 01.25.2024 | ||
| -- | -- | Exterior Vinyl (0) * 03.07.2024 | In process 2/21 | |
| -- | -- | Exterior Stone (0) 03.11.2024 | in process 3/11 | |
| -- | -- | Insulation (2) * 01.27.2024 | ||
| -- | -- | Inspection (Insulation) (1) 01.31.2024 | ||
| -- | -- | Inspection (Electric Service) (0) 03.07.2024 | ||
| -- | -- | Set Electric Meter (0) * 03.29.2024 | ||
| -- | -- | Inspection (Main Sewer Line) (0) 02.15.2024 | ||
| -- | -- | Inspection (Main Water Line) (0) 02.15.2024 | ||
| -- | -- | Order Interior Doors & Trim (0) 02.28.2024 | ||
| -- | -- | Drywall (Hang) (4) * 02.03.2024 | In process 1/31 | |
| -- | -- | Loan Approval (0) 04.11.2024 | EMET Mortgage (80% LTV) | |
| -- | -- | Deed Preparation (0) 03.25.2024 | ||
| -- | -- | Drywall (Tape, Block, Skim, Sand) (6) * 02.10.2024 | In process 2/7 | |
| -- | -- | Paint 1 (1) 02.14.2024 | ||
| -- | -- | Garage Door (0) 03.11.2024 | Davenport | |
| -- | -- | House Numbers (0) 04.06.2024 | ||
| -- | -- | Mailbox (0) 03.28.2024 | ||
| -- | -- | Cabinet Installation (2) * 02.21.2024 | On site 2/17 | |
| -- | -- | Granite Installation (1) * 02.28.2024 | ||
| -- | -- | Interior Trim - Install (3) * 02.21.2024 | In process 2/17 | |
| -- | -- | Order Plumbing / Lighting Fixtures (0) 03.14.2024 | Delivering this week 3/11 | |
| -- | -- | Interior Trim - Paint (1) 02.24.2024 | ||
| -- | -- | Luxury Vinyl Plank (3) * 03.06.2024 | In process 3/2 | |
| -- | -- | Luxury Vinyl Tile (0) 03.06.2024 | In process 3/2 | |
| -- | -- | Paint 2 (3) 03.06.2024 | ||
| -- | -- | Cover Floors (1) 03.11.2024 | ||
| -- | -- | Deliver Plumbing / Lighting Fixtures (0) 03.14.2024 | ||
| -- | -- | Shoe Moulding (0) 03.09.2024 | In process 3/6 | |
| -- | -- | Shelving, Door Knobs, Fire Extinguisher (0) * 04.10.2024 | In process 4/3 | |
| -- | -- | Install Coded Lockbox (add extra keys) (0) 04.10.2024 | ||
| -- | -- | Pay Water / Sewer Taps (0) 03.28.2024 | ||
| -- | -- | Set Water Meter (0) * 03.28.2024 | ||
| -- | -- | Electric Trim Out (3) * 03.28.2024 | ||
| -- | -- | Ceiling Fans (0) 04.03.2024 | ||
| -- | -- | HVAC Trim Out (1) * 03.23.2024 | Heat pump is set | |
| -- | -- | Blower Door Test (1) 04.06.2024 | ||
| -- | -- | Plumbing Trim Out (2) * 03.30.2024 | ||
| -- | -- | Install Appliances (0) * 04.04.2024 | In process 4/3 | |
| -- | -- | Paint 3 (2) * 03.30.2024 | In process 3/16 | |
| -- | -- | Carpet (2) 03.06.2024 | ||
| -- | -- | Appraiser Confirms Construction Completion (0) 04.18.2024 | ||
| -- | -- | Inspection (Final HVAC) (1) 04.06.2024 | Fri, April 5 | |
| -- | -- | Inspection (Final Plumbing) (1) 04.06.2024 | ||
| -- | -- | Inspection (Final Electric) (1) 04.06.2024 | ||
| -- | -- | Inspection (Final Building) (2) * 04.06.2024 | ||
| -- | -- | Pre Walk Through (0) 04.11.2024 | ||
| -- | -- | Stain Hardwood Stairs (1) * 04.03.2024 | ||
| -- | -- | Cleaning (1) 04.17.2024 | ||
| -- | -- | Certificate of Occupancy (1) * 04.11.2024 | ||
| -- | -- | C.O. to Lender (0) 04.11.2024 | ||
| -- | -- | Schedule Closing (0) 04.20.2024 | ||
| -- | -- | Buyer Walk Through (1) * 04.16.2024 | Tuesday, April 16 at 1PM | |
| -- | -- | Payment for Upgrades (0) 04.11.2024 | ||
| -- | -- | Keys to Settlement Agent (0) 04.15.2024 | ||
| -- | -- | Review Settlement Statement (0) 04.17.2024 | ||
| -- | -- | Jerry Signs Closing Documents (0) 03.22.2024 | ||
| -- | -- | Request Trash Tote From POA Manager (0) 04.15.2024 | ||
| -- | -- | Closing (1) 04.20.2024 | Brittany @ West View Title | |
| -- | -- | Remove Coded Lockbox (0) 05.01.2024 | ||