Buyer Contact- 540-607-5199 |
|
|
|
-- |
-- |
Side, splashes of granite needed here |
Just one needs to be replaced |
|
-- |
-- |
Cover carpet |
|
|
-- |
-- |
Trim, missing on stairs, leading to main level |
Two spots |
|
-- |
-- |
Lots of beeping smoke detectors |
Electrician |
|
-- |
-- |
CODED LOCKBOX 7777 |
|
|
-- |
-- |
Needs all door knobs |
|
|
-- |
-- |
Patch screw holes in powder bath light fixture |
Painter |
|
-- |
-- |
Few larger paint touch up spots needed before final walk-through? |
Painter |
|
-- |
-- |
Paint attic cover |
Painter |
|
-- |
-- |
Master bedroom could use another coat of paint. Where they cut in and where they rolled it’s pretty obvious. |
Painter |
|
-- |
-- |
Install screens |
|
|
-- |
-- |
Install sliding screen doors |
|
|
-- |
-- |
Return $676.25 to Buyer |
4/12: waiting on check from Tina |
|
-- |
-- |
Paint touchup throughout |
Painter |
|
-- |
-- |
Adhere show mold, and trim piece in kitchen |
|
|
-- |
-- |
Sweep out garage |
|
|
-- |
-- |
Fix gash in door to deck near the lock |
Painter |
|
-- |
-- |
Put splash block in place and add dirt behind heat pump |
Tom |
|
-- |
-- |
Paint, touchup throughout |
|
|
-- |
-- |
Hide the very large wire, that sticking out of the side of the townhouse |
Tom |
|
-- |
-- |
Ratified Contract? (0) 10.04.2023 |
|
|
-- |
-- |
$2500 Deposit Received (0) 10.12.2023 |
|
|
-- |
-- |
Association Packet Requested (0) 10.04.2023 |
|
|
-- |
-- |
Association Packet Received (0) 10.08.2023 |
|
|
-- |
-- |
Selections Meeting (0) 11.02.2023 |
|
|
-- |
-- |
Selections Sheet Signed (0) 11.28.2023 |
11/2: Sent to Basu for signatures |
|
-- |
-- |
Amendment for Upgrades (B,S,L,T,BCP) (0) 11.29.2023 |
11/27: Sent to Jerry for signatures; |
|
-- |
-- |
Deposit For Upgrades Received (0) 11.28.2023 |
|
|
-- |
-- |
Building Permit (30) 09.11.2023 |
|
|
-- |
-- |
Order Roof & Floor Trusses (1) 11.20.2023 |
|
|
-- |
-- |
Order Windows & Doors (0) 11.20.2023 |
|
|
-- |
-- |
Stake Out Home (1) 09.11.2023 |
|
|
-- |
-- |
Excavate (2) 09.11.2023 |
|
|
-- |
-- |
Inspection (Footers) (1) 10.05.2023 |
|
|
-- |
-- |
Inspection (Concrete Wall) (1) 10.05.2023 |
|
|
-- |
-- |
Pour Footers (1) 09.11.2023 |
|
|
-- |
-- |
Set Forms (2) 09.11.2023 |
|
|
-- |
-- |
Pour Foundation Walls (1) 09.11.2023 |
|
|
-- |
-- |
Plumb Slab (2) 10.05.2023 |
|
|
-- |
-- |
Inspection (Plumbing Under Slab) (1) 10.16.2023 |
|
|
-- |
-- |
Inspection (Conduit Under Slab) (1) 10.16.2023 |
|
|
-- |
-- |
Prepare Slab (1) 10.16.2023 |
|
|
-- |
-- |
Inspection (Slab) (1) 10.16.2023 |
|
|
-- |
-- |
Inspection (Drain Tile) (0) 02.19.2024 |
|
|
-- |
-- |
Pour Slab (1) * 10.16.2023 |
|
|
-- |
-- |
Settlement Agent Confirmed (0) 12.02.2023 |
11/29: sent to Brittany |
|
-- |
-- |
Framing I (9) 11.27.2023 |
|
|
-- |
-- |
Order Steps (0) 11.27.2023 |
|
|
-- |
-- |
Order Tubs / Showers (0) 11.27.2023 |
|
|
-- |
-- |
Framing II (8) 11.27.2023 |
|
|
-- |
-- |
Framing III (8) * 11.27.2023 |
|
|
-- |
-- |
Verify Window & Roof Structure (0) 12.20.2023 |
|
|
-- |
-- |
Install Stairs (0) 12.20.2023 |
|
|
-- |
-- |
Windows & Doors (0) 12.20.2023 |
|
|
-- |
-- |
House Number and Status in Window (0) 01.31.2024 |
|
|
-- |
-- |
Roofing (0) 12.20.2023 |
|
|
-- |
-- |
Order Cabinets (0) 01.16.2024 |
|
|
-- |
-- |
Order Appliances (0) 03.11.2024 |
delivering 3/18 |
|
-- |
-- |
Deck (0) 12.20.2023 |
|
|
-- |
-- |
Gutters (0) 03.09.2024 |
|
|
-- |
-- |
Driveway (0) 03.28.2024 |
|
|
-- |
-- |
Patio (0) 02.07.2024 |
|
|
-- |
-- |
Privacy Divider / Fence (0) 04.10.2024 |
|
|
-- |
-- |
Sod / Seed / Landscaping (0) 04.19.2024 |
|
|
-- |
-- |
HVAC Rough In (4) 01.03.2024 |
In process 1/3 |
|
-- |
-- |
Inspection (Rough In HVAC) (1) 01.25.2024 |
|
|
-- |
-- |
Rough In Microwave Vent (0) 01.03.2024 |
|
|
-- |
-- |
Plumbing Rough In (4) 01.13.2024 |
In process 1/10 |
|
-- |
-- |
Inspection (Rough In Plumbing) (1) 01.25.2024 |
|
|
-- |
-- |
Electric Rough In (4) 01.19.2024 |
|
|
-- |
-- |
Inspection (Rough In Electric) (1) 01.25.2024 |
|
|
-- |
-- |
Inspection (Deck Piers) (0) 01.25.2024 |
|
|
-- |
-- |
Inspection (Framing) (1) 01.25.2024 |
|
|
-- |
-- |
Exterior Vinyl (0) * 03.07.2024 |
In process 2/21 |
|
-- |
-- |
Exterior Stone (0) 03.11.2024 |
in process 3/11 |
|
-- |
-- |
Insulation (2) 01.27.2024 |
|
|
-- |
-- |
Inspection (Insulation) (1) 01.31.2024 |
|
|
-- |
-- |
Inspection (Electric Service) (0) 03.07.2024 |
|
|
-- |
-- |
Set Electric Meter (0) 03.29.2024 |
|
|
-- |
-- |
Inspection (Main Sewer Line) (0) 02.15.2024 |
|
|
-- |
-- |
Inspection (Main Water Line) (0) 02.15.2024 |
|
|
-- |
-- |
Order Interior Doors & Trim (0) 02.28.2024 |
|
|
-- |
-- |
Drywall (Hang) (4) * 02.03.2024 |
In process 1/31 |
|
-- |
-- |
Loan Approval (0) 04.11.2024 |
EMET Mortgage (80% LTV) |
|
-- |
-- |
Deed Preparation (0) 03.25.2024 |
|
|
-- |
-- |
Drywall (Tape, Block, Skim, Sand) (6) * 02.10.2024 |
In process 2/7 |
|
-- |
-- |
Paint 1 (1) 02.14.2024 |
|
|
-- |
-- |
Garage Door (0) 03.11.2024 |
Davenport |
|
-- |
-- |
House Numbers (0) 04.06.2024 |
|
|
-- |
-- |
Mailbox (0) 03.28.2024 |
|
|
-- |
-- |
Cabinet Installation (2) * 02.21.2024 |
On site 2/17 |
|
-- |
-- |
Granite Installation (1) * 02.28.2024 |
|
|
-- |
-- |
Interior Trim - Install (3) 02.21.2024 |
In process 2/17 |
|
-- |
-- |
Order Plumbing / Lighting Fixtures (0) 03.14.2024 |
Delivering this week 3/11 |
|
-- |
-- |
Interior Trim - Paint (1) 02.24.2024 |
|
|
-- |
-- |
Luxury Vinyl Plank (3) * 03.06.2024 |
In process 3/2 |
|
-- |
-- |
Luxury Vinyl Tile (0) 03.06.2024 |
In process 3/2 |
|
-- |
-- |
Paint 2 (3) 03.06.2024 |
|
|
-- |
-- |
Cover Floors (1) 03.11.2024 |
|
|
-- |
-- |
Deliver Plumbing / Lighting Fixtures (0) 03.14.2024 |
|
|
-- |
-- |
Shoe Moulding (0) 03.09.2024 |
In process 3/6 |
|
-- |
-- |
Shelving, Door Knobs, Fire Extinguisher (0) 04.10.2024 |
In process 4/3 |
|
-- |
-- |
Install Coded Lockbox (add extra keys) (0) 04.10.2024 |
|
|
-- |
-- |
Pay Water / Sewer Taps (0) 03.28.2024 |
|
|
-- |
-- |
Set Water Meter (0) 03.28.2024 |
|
|
-- |
-- |
Electric Trim Out (3) 03.28.2024 |
|
|
-- |
-- |
Ceiling Fans (0) 04.03.2024 |
|
|
-- |
-- |
HVAC Trim Out (1) 03.23.2024 |
Heat pump is set |
|
-- |
-- |
Blower Door Test (1) 04.06.2024 |
|
|
-- |
-- |
Plumbing Trim Out (2) 03.30.2024 |
|
|
-- |
-- |
Install Appliances (0) * 04.04.2024 |
In process 4/3 |
|
-- |
-- |
Paint 3 (2) * 03.30.2024 |
In process 3/16 |
|
-- |
-- |
Carpet (2) 03.06.2024 |
|
|
-- |
-- |
Appraiser Confirms Construction Completion (0) 04.18.2024 |
|
|
-- |
-- |
Inspection (Final HVAC) (1) 04.06.2024 |
Fri, April 5 |
|
-- |
-- |
Inspection (Final Plumbing) (1) 04.06.2024 |
|
|
-- |
-- |
Inspection (Final Electric) (1) 04.06.2024 |
|
|
-- |
-- |
Inspection (Final Building) (2) * 04.06.2024 |
|
|
-- |
-- |
Pre Walk Through (0) 04.11.2024 |
|
|
-- |
-- |
Stain Hardwood Stairs (1) 04.03.2024 |
|
|
-- |
-- |
Cleaning (1) 04.17.2024 |
|
|
-- |
-- |
Certificate of Occupancy (1) * 04.11.2024 |
|
|
-- |
-- |
C.O. to Lender (0) 04.11.2024 |
|
|
-- |
-- |
Schedule Closing (0) 04.20.2024 |
|
|
-- |
-- |
Buyer Walk Through (1) 04.16.2024 |
Tuesday, April 16 at 1PM |
|
-- |
-- |
Payment for Upgrades (0) 04.11.2024 |
|
|
-- |
-- |
Keys to Settlement Agent (0) 04.15.2024 |
|
|
-- |
-- |
Review Settlement Statement (0) 04.17.2024 |
|
|
-- |
-- |
Jerry Signs Closing Documents (0) 03.22.2024 |
|
|
-- |
-- |
Request Trash Tote From POA Manager (0) 04.15.2024 |
|
|
-- |
-- |
Closing (1) 04.20.2024 |
Brittany @ West View Title |
|
-- |
-- |
Remove Coded Lockbox (0) 05.01.2024 |
|
|