1 33 37 89 47 73 67 55 56 59 57 66 65 64 60 61 62 63 ADDR
CONGERS-2 - 77  ::  1449 Appaloosa Court
[ BUILD: 20230932 ]      
CRITICAL PATH   |   INSPECTIONS   |   FLOOR PLANS   |   SELECTIONS   |   SPECS   |   CHANGES   |   NHS
view photo archive
 
--   --   Buyer Contact- 540-607-5199
--   --   Side, splashes of granite needed here Just one needs to be replaced
--   --   Cover carpet
--   --   Trim, missing on stairs, leading to main level Two spots
--   --   Lots of beeping smoke detectors Electrician
--   --   CODED LOCKBOX 7777
--   --   Needs all door knobs
--   --   Patch screw holes in powder bath light fixture Painter
--   --   Few larger paint touch up spots needed before final walk-through? Painter
--   --   Paint attic cover Painter
--   --   Master bedroom could use another coat of paint. Where they cut in and where they rolled it’s pretty obvious. Painter
--   --   Install screens
--   --   Install sliding screen doors
--   --   Return $676.25 to Buyer 4/12: waiting on check from Tina
--   --   Paint touchup throughout Painter
--   --   Adhere show mold, and trim piece in kitchen
--   --   Sweep out garage
--   --   Fix gash in door to deck near the lock Painter
--   --   Put splash block in place and add dirt behind heat pump Tom
--   --   Paint, touchup throughout
--   --   Hide the very large wire, that sticking out of the side of the townhouse Tom
-- -- Ratified Contract? (0)  10.04.2023    
-- -- $2500 Deposit Received (0)  10.12.2023    
-- -- Association Packet Requested (0)  10.04.2023    
-- -- Association Packet Received (0)  10.08.2023    
-- -- Selections Meeting (0)  11.02.2023    
-- -- Selections Sheet Signed (0)  11.28.2023     11/2: Sent to Basu for signatures
-- -- Amendment for Upgrades (B,S,L,T,BCP) (0)  11.29.2023     11/27: Sent to Jerry for signatures;
-- -- Deposit For Upgrades Received (0)  11.28.2023    
-- -- Building Permit (30)  09.11.2023    
-- -- Order Roof & Floor Trusses (1)  11.20.2023    
-- -- Order Windows & Doors (0)  11.20.2023    
-- -- Stake Out Home (1)  09.11.2023    
-- -- Excavate (2)  09.11.2023    
-- -- Inspection (Footers) (1)  10.05.2023    
-- -- Inspection (Concrete Wall) (1)  10.05.2023    
-- -- Pour Footers (1)  09.11.2023    
-- -- Set Forms (2)  09.11.2023    
-- -- Pour Foundation Walls (1)  09.11.2023    
-- -- Plumb Slab (2)  10.05.2023    
-- -- Inspection (Plumbing Under Slab) (1)  10.16.2023    
-- -- Inspection (Conduit Under Slab) (1)  10.16.2023    
-- -- Prepare Slab (1)  10.16.2023    
-- -- Inspection (Slab) (1)  10.16.2023    
-- -- Inspection (Drain Tile) (0)  02.19.2024    
-- -- Pour Slab (1) *   10.16.2023    
-- -- Settlement Agent Confirmed (0)  12.02.2023     11/29: sent to Brittany
-- -- Framing I (9)  11.27.2023    
-- -- Order Steps (0)  11.27.2023    
-- -- Order Tubs / Showers (0)  11.27.2023    
-- -- Framing II (8)  11.27.2023    
-- -- Framing III (8) *   11.27.2023    
-- -- Verify Window & Roof Structure (0)  12.20.2023    
-- -- Install Stairs (0)  12.20.2023    
-- -- Windows & Doors (0)  12.20.2023    
-- -- House Number and Status in Window (0)  01.31.2024    
-- -- Roofing (0)  12.20.2023    
-- -- Order Cabinets (0)  01.16.2024    
-- -- Order Appliances (0)  03.11.2024     delivering 3/18
-- -- Deck (0)  12.20.2023    
-- -- Gutters (0)  03.09.2024    
-- -- Driveway (0)  03.28.2024    
-- -- Patio (0)  02.07.2024    
-- -- Privacy Divider / Fence (0)  04.10.2024    
-- -- Sod / Seed / Landscaping (0)  04.19.2024    
-- -- HVAC Rough In (4)  01.03.2024     In process 1/3
-- -- Inspection (Rough In HVAC) (1)  01.25.2024    
-- -- Rough In Microwave Vent (0)  01.03.2024    
-- -- Plumbing Rough In (4)  01.13.2024     In process 1/10
-- -- Inspection (Rough In Plumbing) (1)  01.25.2024    
-- -- Electric Rough In (4)  01.19.2024    
-- -- Inspection (Rough In Electric) (1)  01.25.2024    
-- -- Inspection (Deck Piers) (0)  01.25.2024    
-- -- Inspection (Framing) (1)  01.25.2024    
-- -- Exterior Vinyl (0) *   03.07.2024     In process 2/21
-- -- Exterior Stone (0)  03.11.2024     in process 3/11
-- -- Insulation (2)  01.27.2024    
-- -- Inspection (Insulation) (1)  01.31.2024    
-- -- Inspection (Electric Service) (0)  03.07.2024    
-- -- Set Electric Meter (0)  03.29.2024    
-- -- Inspection (Main Sewer Line) (0)  02.15.2024    
-- -- Inspection (Main Water Line) (0)  02.15.2024    
-- -- Order Interior Doors & Trim (0)  02.28.2024    
-- -- Drywall (Hang) (4) *   02.03.2024     In process 1/31
-- -- Loan Approval (0)  04.11.2024     EMET Mortgage (80% LTV)
-- -- Deed Preparation (0)  03.25.2024    
-- -- Drywall (Tape, Block, Skim, Sand) (6) *   02.10.2024     In process 2/7
-- -- Paint 1 (1)  02.14.2024    
-- -- Garage Door (0)  03.11.2024     Davenport
-- -- House Numbers (0)  04.06.2024    
-- -- Mailbox (0)  03.28.2024    
-- -- Cabinet Installation (2) *   02.21.2024     On site 2/17
-- -- Granite Installation (1) *   02.28.2024    
-- -- Interior Trim - Install (3)  02.21.2024     In process 2/17
-- -- Order Plumbing / Lighting Fixtures (0)  03.14.2024     Delivering this week 3/11
-- -- Interior Trim - Paint (1)  02.24.2024    
-- -- Luxury Vinyl Plank (3) *   03.06.2024     In process 3/2
-- -- Luxury Vinyl Tile (0)  03.06.2024     In process 3/2
-- -- Paint 2 (3)  03.06.2024    
-- -- Cover Floors (1)  03.11.2024    
-- -- Deliver Plumbing / Lighting Fixtures (0)  03.14.2024    
-- -- Shoe Moulding (0)  03.09.2024     In process 3/6
-- -- Shelving, Door Knobs, Fire Extinguisher (0)  04.10.2024     In process 4/3
-- -- Install Coded Lockbox (add extra keys) (0)  04.10.2024    
-- -- Pay Water / Sewer Taps (0)  03.28.2024    
-- -- Set Water Meter (0)  03.28.2024    
-- -- Electric Trim Out (3)  03.28.2024    
-- -- Ceiling Fans (0)  04.03.2024    
-- -- HVAC Trim Out (1)  03.23.2024     Heat pump is set
-- -- Blower Door Test (1)  04.06.2024    
-- -- Plumbing Trim Out (2)  03.30.2024    
-- -- Install Appliances (0) *   04.04.2024     In process 4/3
-- -- Paint 3 (2) *   03.30.2024     In process 3/16
-- -- Carpet (2)  03.06.2024    
-- -- Appraiser Confirms Construction Completion (0)  04.18.2024    
-- -- Inspection (Final HVAC) (1)  04.06.2024     Fri, April 5
-- -- Inspection (Final Plumbing) (1)  04.06.2024    
-- -- Inspection (Final Electric) (1)  04.06.2024    
-- -- Inspection (Final Building) (2) *   04.06.2024    
-- -- Pre Walk Through (0)  04.11.2024    
-- -- Stain Hardwood Stairs (1)  04.03.2024    
-- -- Cleaning (1)  04.17.2024    
-- -- Certificate of Occupancy (1) *   04.11.2024    
-- -- C.O. to Lender (0)  04.11.2024    
-- -- Schedule Closing (0)  04.20.2024    
-- -- Buyer Walk Through (1)  04.16.2024     Tuesday, April 16 at 1PM
-- -- Payment for Upgrades (0)  04.11.2024    
-- -- Keys to Settlement Agent (0)  04.15.2024    
-- -- Review Settlement Statement (0)  04.17.2024    
-- -- Jerry Signs Closing Documents (0)  03.22.2024    
-- -- Request Trash Tote From POA Manager (0)  04.15.2024    
-- -- Closing (1)  04.20.2024     Brittany @ West View Title
-- -- Remove Coded Lockbox (0)  05.01.2024