There is an extra bathtub in this garage |
|
|
-- |
-- |
Odd hole in garage. Does anything need to be done here? |
|
|
-- |
-- |
The front door to this house does not close. Perhaps a framing problem? |
Framer |
|
-- |
-- |
Possible issue with door frame on powder bath |
Gap in drywall above top |
|
-- |
-- |
Cover carpet floor |
Jill |
|
-- |
-- |
Finish up trim since cabinets are installed |
|
|
-- |
-- |
Few lightbulbs needed and powder bath light needs installed |
Electrician |
|
-- |
-- |
Appears to be a large gap between the pantry cabinet and the refrigerator. Is this correct? |
Fred is fixing 7/8. Supplies are on order. |
|
-- |
-- |
Powder bath mirror needed, and door knobs needed everywhere |
Paul |
|
-- |
-- |
Ensure the garage door opener is fastened to the wall |
Tom |
|
-- |
-- |
Make sure that basement patio door lock functions |
Tom |
|
-- |
-- |
CODED LOCKBOX 5050 |
|
|
-- |
-- |
Remove ladder from master closet |
|
|
-- |
-- |
Clean out garage |
jill. Almost completed! |
|
-- |
-- |
screens need installed throughout home |
jill |
|
-- |
-- |
leave mailbox keys in drawer in kitchen |
jill |
|
-- |
-- |
transition strip needs replaced on 2nd set of stairs at landing |
denny |
|
-- |
-- |
add another noat of paint to painted stairs |
painters |
|
-- |
-- |
paint drips from the front door is on the floor inside the front door |
painters |
|
-- |
-- |
remove the co ers from all smoke detectors throughout home |
jill |
|
-- |
-- |
Only 2 paint touch ups in the whole townhouse!!!! |
painters |
|
-- |
-- |
Ratified Contract? (0) 04.30.2024 |
|
|
-- |
-- |
$2500 Deposit Received (0) 05.07.2024 |
|
|
-- |
-- |
Association Packet Requested (0) 04.30.2024 |
|
|
-- |
-- |
Association Packet Received (0) 05.05.2024 |
|
|
-- |
-- |
Selections Meeting (0) 05.07.2024 |
|
|
-- |
-- |
Selections Sheet Signed (0) 05.10.2024 |
5/7: sent to buyer for review |
|
-- |
-- |
Amendment for Upgrades (B,S,L,T,BCP) (0) 05.24.2024 |
5/23: sent to Jerry |
|
-- |
-- |
Deposit For Upgrades Received (0) 05.10.2024 |
|
|
-- |
-- |
Building Permit (30) 01.04.2024 |
|
|
-- |
-- |
Order Roof & Floor Trusses (1) 02.12.2024 |
|
|
-- |
-- |
Order Windows & Doors (0) 02.12.2024 |
|
|
-- |
-- |
Stake Out Home (1) 01.04.2024 |
|
|
-- |
-- |
Excavate (2) 01.04.2024 |
|
|
-- |
-- |
Inspection (Footers) (1) 01.04.2024 |
|
|
-- |
-- |
Inspection (Concrete Wall) (1) 01.04.2024 |
|
|
-- |
-- |
Pour Footers (1) 01.04.2024 |
|
|
-- |
-- |
Set Forms (2) 01.04.2024 |
|
|
-- |
-- |
Pour Foundation Walls (1) 01.04.2024 |
|
|
-- |
-- |
Plumb Slab (2) 01.07.2024 |
|
|
-- |
-- |
Inspection (Plumbing Under Slab) (1) 02.08.2024 |
|
|
-- |
-- |
Inspection (Conduit Under Slab) (1) 02.08.2024 |
|
|
-- |
-- |
Prepare Slab (1) 02.08.2024 |
|
|
-- |
-- |
Inspection (Slab) (1) 02.08.2024 |
|
|
-- |
-- |
Inspection (Drain Tile) (0) 02.08.2024 |
|
|
-- |
-- |
Pour Slab (1) * 02.08.2024 |
|
|
-- |
-- |
Settlement Agent Confirmed (0) 05.25.2024 |
sent |
|
-- |
-- |
Framing I (9) 02.15.2024 |
|
|
-- |
-- |
Order Steps (0) 03.11.2024 |
|
|
-- |
-- |
Order Tubs / Showers (0) 03.11.2024 |
|
|
-- |
-- |
Framing II (8) 02.19.2024 |
|
|
-- |
-- |
Framing III (8) * 02.22.2024 |
|
|
-- |
-- |
Verify Window & Roof Structure (0) 03.04.2024 |
|
|
-- |
-- |
Install Stairs (0) 03.11.2024 |
|
|
-- |
-- |
Windows & Doors (0) 04.03.2024 |
|
|
-- |
-- |
House Number and Status in Window (0) 04.03.2024 |
|
|
-- |
-- |
Roofing (0) 03.11.2024 |
|
|
-- |
-- |
Order Cabinets (0) 05.21.2024 |
|
|
-- |
-- |
Order Appliances (0) 06.10.2024 |
TBD |
|
-- |
-- |
Deck (0) 04.03.2024 |
|
|
-- |
-- |
Gutters (0) 05.26.2024 |
|
|
-- |
-- |
Driveway (0) 05.22.2024 |
|
|
-- |
-- |
Patio (0) 04.03.2024 |
|
|
-- |
-- |
Privacy Divider / Fence (0) 05.22.2024 |
|
|
-- |
-- |
Sod / Seed / Landscaping (0) 06.05.2024 |
|
|
-- |
-- |
HVAC Rough In (4) 03.16.2024 |
in process 3/9 |
|
-- |
-- |
Inspection (Rough In HVAC) (1) 04.24.2024 |
|
|
-- |
-- |
Rough In Microwave Vent (0) 03.13.2024 |
|
|
-- |
-- |
Plumbing Rough In (4) 04.10.2024 |
In process 4/6 |
|
-- |
-- |
Inspection (Rough In Plumbing) (1) 04.24.2024 |
|
|
-- |
-- |
Electric Rough In (4) 04.17.2024 |
|
|
-- |
-- |
Inspection (Rough In Electric) (1) 04.24.2024 |
|
|
-- |
-- |
Inspection (Deck Piers) (0) 06.10.2024 |
|
|
-- |
-- |
Inspection (Framing) (1) 04.24.2024 |
|
|
-- |
-- |
Exterior Vinyl (0) * 05.06.2024 |
|
|
-- |
-- |
Exterior Stone (0) 05.26.2024 |
|
|
-- |
-- |
Insulation (2) 04.19.2024 |
|
|
-- |
-- |
Inspection (Insulation) (1) 04.27.2024 |
|
|
-- |
-- |
Inspection (Electric Service) (0) 05.20.2024 |
|
|
-- |
-- |
Set Electric Meter (0) 05.30.2024 |
|
|
-- |
-- |
Inspection (Main Sewer Line) (0) 04.04.2024 |
|
|
-- |
-- |
Inspection (Main Water Line) (0) 04.04.2024 |
|
|
-- |
-- |
Order Interior Doors & Trim (0) 05.29.2024 |
|
|
-- |
-- |
Drywall (Hang) (4) * 04.27.2024 |
Stocked 4/24 |
|
-- |
-- |
Loan Approval (0) 07.10.2024 |
Zhane Evins, Cap Center (80% LTV) |
|
-- |
-- |
Deed Preparation (0) 06.10.2024 |
|
|
-- |
-- |
Drywall (Tape, Block, Skim, Sand) (6) * 05.11.2024 |
In process 5/8. Final sanding needed |
|
-- |
-- |
Paint 1 (1) 05.11.2024 |
|
|
-- |
-- |
Garage Door (0) 05.26.2024 |
|
|
-- |
-- |
House Numbers (0) 06.22.2024 |
|
|
-- |
-- |
Mailbox (0) 06.01.2024 |
|
|
-- |
-- |
Cabinet Installation (2) * 06.15.2024 |
June 14 |
|
-- |
-- |
Granite Installation (1) * 06.15.2024 |
|
|
-- |
-- |
Interior Trim - Install (3) 05.29.2024 |
In process 5/26 |
|
-- |
-- |
Order Plumbing / Lighting Fixtures (0) 06.10.2024 |
|
|
-- |
-- |
Interior Trim - Paint (1) 05.29.2024 |
|
|
-- |
-- |
Luxury Vinyl Plank (3) * 06.12.2024 |
In process 6/12 |
|
-- |
-- |
Luxury Vinyl Tile (0) 06.12.2024 |
In process 6/12 |
|
-- |
-- |
Paint 2 (3) 06.01.2024 |
In process 5/29 |
|
-- |
-- |
Cover Floors (1) 07.06.2024 |
|
|
-- |
-- |
Deliver Plumbing / Lighting Fixtures (0) 06.17.2024 |
|
|
-- |
-- |
Shoe Moulding (0) 06.22.2024 |
In process 6/19 |
|
-- |
-- |
Shelving, Door Knobs, Fire Extinguisher (0) 06.30.2024 |
In process. Door handles needed everywhere 6/30 |
|
-- |
-- |
Install Coded Lockbox (add extra keys) (0) 07.08.2024 |
|
|
-- |
-- |
Pay Water / Sewer Taps (0) 06.10.2024 |
|
|
-- |
-- |
Set Water Meter (0) 06.20.2024 |
|
|
-- |
-- |
Electric Trim Out (3) 06.22.2024 |
Standard Black. In process 6/22 |
|
-- |
-- |
Ceiling Fans (0) 06.22.2024 |
Master |
|
-- |
-- |
HVAC Trim Out (1) 06.30.2024 |
|
|
-- |
-- |
Blower Door Test (1) 07.08.2024 |
|
|
-- |
-- |
Plumbing Trim Out (2) 06.30.2024 |
In process 6/26 |
|
-- |
-- |
Install Appliances (0) * 06.30.2024 |
|
|
-- |
-- |
Paint 3 (2) * 06.15.2024 |
|
|
-- |
-- |
Carpet (2) 06.12.2024 |
|
|
-- |
-- |
Appraiser Confirms Construction Completion (0) 07.10.2024 |
|
|
-- |
-- |
Inspection (Final HVAC) (1) 07.08.2024 |
|
|
-- |
-- |
Inspection (Final Plumbing) (1) 07.08.2024 |
|
|
-- |
-- |
Inspection (Final Electric) (1) 07.08.2024 |
|
|
-- |
-- |
Inspection (Final Building) (2) * 07.08.2024 |
Tue, July 2 |
|
-- |
-- |
Pre Walk Through (0) 07.11.2024 |
|
|
-- |
-- |
Stain Hardwood Stairs (1) 06.30.2024 |
In process 6/26 |
|
-- |
-- |
Cleaning (1) 07.10.2024 |
Lynn starting 7/8 |
|
-- |
-- |
Certificate of Occupancy (1) * 07.08.2024 |
|
|
-- |
-- |
C.O. to Lender (0) 07.08.2024 |
|
|
-- |
-- |
Schedule Closing (0) 07.10.2024 |
|
|
-- |
-- |
Buyer Walk Through (1) 07.13.2024 |
11am 7/11 |
|
-- |
-- |
Payment for Upgrades (0) 07.08.2024 |
|
|
-- |
-- |
Keys to Settlement Agent (0) 07.19.2024 |
|
|
-- |
-- |
Review Settlement Statement (0) 07.11.2024 |
|
|
-- |
-- |
Jerry Signs Closing Documents (0) 07.11.2024 |
|
|
-- |
-- |
Request Trash Tote From POA Manager (0) 07.01.2024 |
|
|
-- |
-- |
Closing (1) 07.22.2024 |
July 15 - Homeland Title Settlement Agency |
|
-- |
-- |
Remove Coded Lockbox (0) 07.22.2024 |
|
|