37 ADDR
CONGERS-2 - 50  ::  1402 Appaloosa Court
[ BUILD: 20231955 ]      
CRITICAL PATH   |   INSPECTIONS   |   FLOOR PLANS   |   SELECTIONS   |   SPECS   |   CHANGES   |   NHS
view photo archive
 
TO DO
---
UPGRADES
---
CRITICAL PATH
---
TO DO - COMPLETED OR DELETED
There is an extra bathtub in this garage
Odd hole in garage. Does anything need to be done here?
The front door to this house does not close. Perhaps a framing problem? Framer
Possible issue with door frame on powder bath Gap in drywall above top
Cover carpet floor Jill
Finish up trim since cabinets are installed
Few lightbulbs needed and powder bath light needs installed Electrician
Appears to be a large gap between the pantry cabinet and the refrigerator. Is this correct? Fred is fixing 7/8. Supplies are on order.
Powder bath mirror needed, and door knobs needed everywhere Paul
Ensure the garage door opener is fastened to the wall Tom
Make sure that basement patio door lock functions Tom
CODED LOCKBOX 5050
Remove ladder from master closet
Clean out garage jill. Almost completed!
screens need installed throughout home jill
leave mailbox keys in drawer in kitchen jill
transition strip needs replaced on 2nd set of stairs at landing denny
add another noat of paint to painted stairs painters
paint drips from the front door is on the floor inside the front door painters
remove the co ers from all smoke detectors throughout home jill
Only 2 paint touch ups in the whole townhouse!!!! painters
UPGRADES - COMPLETED
    Painted Pine Grade steps to bedroom Level (black)  
    Amendment to increase price by $840  
CRITICAL PATH - COMPLETED
-- -- Ratified Contract? (0)  04.30.2024    
-- -- $2500 Deposit Received (0)  05.07.2024    
-- -- Association Packet Requested (0)  04.30.2024    
-- -- Association Packet Received (0)  05.05.2024    
-- -- Selections Meeting (0)  05.07.2024    
-- -- Selections Sheet Signed (0)  05.10.2024     5/7: sent to buyer for review
-- -- Amendment for Upgrades (B,S,L,T,BCP) (0)  05.24.2024     5/23: sent to Jerry
-- -- Deposit For Upgrades Received (0)  05.10.2024    
-- -- Building Permit (30) *   01.04.2024    
-- -- Order Roof & Floor Trusses (1)  02.12.2024    
-- -- Order Windows & Doors (0)  02.12.2024    
-- -- Stake Out Home (1)  01.04.2024    
-- -- Excavate (2)  01.04.2024    
-- -- Inspection (Footers) (1)  01.04.2024    
-- -- Inspection (Concrete Wall) (1)  01.04.2024    
-- -- Pour Footers (1) *   01.04.2024    
-- -- Set Forms (2)  01.04.2024    
-- -- Pour Foundation Walls (1)  01.04.2024    
-- -- Plumb Slab (2)  01.07.2024    
-- -- Inspection (Plumbing Under Slab) (1)  02.08.2024    
-- -- Inspection (Conduit Under Slab) (1)  02.08.2024    
-- -- Prepare Slab (1)  02.08.2024    
-- -- Inspection (Slab) (1)  02.08.2024    
-- -- Inspection (Drain Tile) (0)  02.08.2024    
-- -- Pour Slab (1) *   02.08.2024    
-- -- Settlement Agent Confirmed (0)  05.25.2024     sent
-- -- Framing I (9)  02.15.2024    
-- -- Order Steps (0)  03.11.2024    
-- -- Order Tubs / Showers (0)  03.11.2024    
-- -- Framing II (8)  02.19.2024    
-- -- Framing III (8) *   02.22.2024    
-- -- Verify Window & Roof Structure (0)  03.04.2024    
-- -- Install Stairs (0) *   03.11.2024    
-- -- Windows & Doors (0) *   04.03.2024    
-- -- House Number and Status in Window (0)  04.03.2024    
-- -- Roofing (0) *   03.11.2024    
-- -- Order Cabinets (0)  05.21.2024    
-- -- Order Appliances (0)  06.10.2024     TBD
-- -- Deck (0)  04.03.2024    
-- -- Gutters (0)  05.26.2024    
-- -- Driveway (0) *   05.22.2024    
-- -- Patio (0)  04.03.2024    
-- -- Privacy Divider / Fence (0) *   05.22.2024    
-- -- Sod / Seed / Landscaping (0)  06.05.2024    
-- -- HVAC Rough In (4)  03.16.2024     in process 3/9
-- -- Rough In Microwave Vent (0)  03.13.2024    
-- -- Plumbing Rough In (4)  04.10.2024     In process 4/6
-- -- Electric Rough In (4)  04.17.2024    
-- -- Inspection (Rough In HVAC) (1)  04.24.2024    
-- -- Inspection (Rough In Plumbing) (1)  04.24.2024    
-- -- Inspection (Rough In Electric) (1)  04.24.2024    
-- -- Inspection (Framing) (1) *   04.24.2024    
-- -- Inspection (Deck Piers) (0)  06.10.2024    
-- -- Exterior Vinyl (0) *   05.06.2024    
-- -- Exterior Stone (0)  05.26.2024    
-- -- Insulation (2) *   04.19.2024    
-- -- Inspection (Insulation) (1)  04.27.2024    
-- -- Inspection (Electric Service) (0)  05.20.2024    
-- -- Set Electric Meter (0) *   05.30.2024    
-- -- Inspection (Main Sewer Line) (0)  04.04.2024    
-- -- Inspection (Main Water Line) (0)  04.04.2024    
-- -- Order Interior Doors & Trim (0)  05.29.2024    
-- -- Drywall (Hang) (4) *   04.27.2024     Stocked 4/24
-- -- Loan Approval (0)  07.10.2024     Zhane Evins, Cap Center (80% LTV)
-- -- Deed Preparation (0)  06.10.2024    
-- -- Drywall (Tape, Block, Skim, Sand) (6) *   05.11.2024     In process 5/8. Final sanding needed
-- -- Paint 1 (1)  05.11.2024    
-- -- Garage Door (0)  05.26.2024    
-- -- House Numbers (0)  06.22.2024    
-- -- Mailbox (0)  06.01.2024    
-- -- Cabinet Installation (2) *   06.15.2024     June 14
-- -- Granite Installation (1) *   06.15.2024    
-- -- Interior Trim - Install (3) *   05.29.2024     In process 5/26
-- -- Order Plumbing / Lighting Fixtures (0)  06.10.2024    
-- -- Interior Trim - Paint (1)  05.29.2024    
-- -- Luxury Vinyl Plank (3) *   06.12.2024     In process 6/12
-- -- Luxury Vinyl Tile (0)  06.12.2024     In process 6/12
-- -- Paint 2 (3)  06.01.2024     In process 5/29
-- -- Cover Floors (0)  07.06.2024    
-- -- Deliver Plumbing / Lighting Fixtures (0)  06.17.2024    
-- -- Shoe Moulding (0)  06.22.2024     In process 6/19
-- -- Shelving, Door Knobs, Fire Extinguisher (1) *   06.30.2024     In process. Door handles needed everywhere 6/30
-- -- Install Coded Lockbox (add extra keys) (0)  07.08.2024    
-- -- Pay Water / Sewer Taps (0)  06.10.2024    
-- -- Set Water Meter (1) *   06.20.2024    
-- -- Electric Trim Out (3) *   06.22.2024     Standard Black. In process 6/22
-- -- Ceiling Fans (0)  06.22.2024     Master
-- -- HVAC Trim Out (1) *   06.30.2024    
-- -- Blower Door Test (1)  07.08.2024    
-- -- Plumbing Trim Out (2) *   06.30.2024     In process 6/26
-- -- Install Appliances (0) *   06.30.2024    
-- -- Paint 3 (2) *   06.15.2024    
-- -- Carpet (2)  06.12.2024    
-- -- Appraiser Confirms Construction Completion (0)  07.10.2024    
-- -- Inspection (Final HVAC) (0)  07.08.2024    
-- -- Inspection (Final Plumbing) (0)  07.08.2024    
-- -- Inspection (Final Electric) (0)  07.08.2024    
-- -- Inspection (Final Building) (4) *   07.08.2024     Tue, July 2
-- -- Pre Walk Through (0)  07.11.2024    
-- -- Stain Hardwood Stairs (1) *   06.30.2024     In process 6/26
-- -- Cleaning (1)  07.10.2024     Lynn starting 7/8
-- -- Certificate of Occupancy (1) *   07.08.2024    
-- -- C.O. to Lender (0)  07.08.2024    
-- -- Schedule Closing (0)  07.10.2024    
-- -- Buyer Walk Through (1) *   07.13.2024     11am 7/11
-- -- Payment for Upgrades (0)  07.08.2024    
-- -- Keys to Settlement Agent (0)  07.19.2024    
-- -- Review Settlement Statement (0)  07.11.2024    
-- -- Jerry Signs Closing Documents (0)  07.11.2024    
-- -- Request Trash Tote From POA Manager (0)  07.01.2024    
-- -- Closing (1)  07.22.2024     July 15 - Homeland Title Settlement Agency
-- -- Remove Coded Lockbox (0)  07.22.2024